Housing Forward Investment Programme 2026/27 (and 2025/26 review)

Noted Executive 1 paper

AI summaryHillingdon Cabinet approves £45 million housing investment programme for 2026/27, including around 1,000 kitchen and 800 bathroom renewals and 500 window replacements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet agreed 2026/27 HRA Works to Stock Programme
Money£45 millionTotal investment in the coming year
What happens nextImplement from late March 2026Call-in deadline 5pm Friday 27 March 2026
Who it affectsCouncil housing tenants and leaseholdersAcross Hillingdon, including disabled residents

What was decided

Cabinet noted the delivery of the 2025/26 HRA Works to Stock Programme, which has provided essential upgrades and higher energy efficiency standards. Report P80

Cabinet agreed the HRA Works to Stock Programme for 2026/27 and approved release of the HRA WTS Capital Programme budget. Report P48, P55

Cabinet delegated authority to the Corporate Director of Residents Services, in consultation with the Cabinet Member for Corporate Services and Property, to procure, award and release funds for specific projects within the programme. Report P69, P70

Why

The council is committed to improving its social housing stock, with £45 million to be invested in 2026/27, including just under £31 million in direct capital works, over £10 million through the Green Homes Initiative and more than £4 million for HRA adaptations. Report P2, P9, P48

The programme supports the council's aim for all homes to meet a minimum EPC rating of C by 2030, contributes to compliance with the Decent Homes Standard, and supports residents with disabilities under the Equality Act 2010. Report P18, P20, P22, P24

What happens next

Officers will progress framework agreements, tendering, and Section 20 leaseholder consultation, with roofing works due to start in Spring 2026 and complete by Autumn 2027. Report P12, P46, P47, P58

Relevant portfolio Cabinet Members will receive regular updates on progress, capital released, spend to date, and forecast spend, with quarterly monitoring and reporting. Report P54, P59, P60, P68

Any significant variations or changes to the approved programme budget will be reported back to Cabinet for approval. Report P60, P68

The money

  • £45 million Total investment in the coming year across capital works, Green Homes Initiative and adaptations
  • just under £31 million Direct capital works in 2026/27
  • over £10 million Green Homes Initiative in 2026/27
  • more than £4 million HRA adaptations for residents with disability and mobility needs
  • £30,997.0 HRA Works to Stock Programme revised budget 2026/27 (£'000) Report P57
  • £10,250.0 Green Homes Initiatives Programme revised budget 2026/27 (£'000) Report P57
  • £41,247.0 HRA Programme of works Total 2026/27 (£'000) Report P57
  • £141.0m Works to Stock five-year MTFS profile 2026/27 to 2030/31 Report P51
  • £34.9m Green Homes Initiative five-year MTFS profile 2026/27 to 2030/31 Report P51
  • £181.3m Existing five-year MTFS profile for the combined programmes Report P50

Options considered

  • Chosen: Agree the 2026/27 programme and delegate delivery to officers. Streamlined delegated authority is important to ensure timely project delivery each year, while Cabinet retains overall strategy, programme and budget control. Report P4, P6
  • Rejected: Amend the specific works programme as set out in the report for 2026/27. Not considered necessary; programme approved as set out. Report P4
  • Rejected: Not delegate to officers and maintain existing authority levels at Cabinet or Cabinet Member level for individual projects. Would slow decision-making and timely project delivery. Report P4, P6

Implications

  • Financial: The 2026/27 HRA Programme of Works and Green Homes Initiatives capital profile has been approved as part of the council's 2026/27 Medium-Term Financial Strategy; any material variation requires further Cabinet approval. Report P48, P52
  • Financial: All associated expenditure exceeding £500 will be subject to the Spend Control Panel process, with monthly budget monitoring and quarterly summary reports to the Cabinet Member. Report P68
  • Legal: Council has statutory responsibilities under sections 9-10 of the Housing Act 1985, sections 9A, 10A and 11 of the Landlord and Tenant Act 1985, the Regulatory Reform (Fire Safety) Order 2005, and duties under the Equality Act 2010. Report P24, P72
  • Legal: As a registered provider of social housing, the council is subject to the Regulator for Social Housing's Safety and Quality Standard, effective 1 April 2024, with potential enforcement action under Chapter 7 of the Housing and Regeneration Act 2008. Report P73, P74
  • Equalities: HRA adaptations will continue to be delivered to support residents with disabilities and mobility needs in line with the council's duties under the Equality Act 2010. Report P24
  • Climate: Green Homes Initiative targets street properties with EPC below band C, upgrading homes to meet the government requirement for all properties to achieve a minimum EPC rating of C by 2030, supporting the council's climate change strategy. Report P18, P81
  • Risk: Leaseholder Section 20 consultation and recharges will be required for some elements of the works, and any significant variations or budget changes will be reported back to Cabinet. Report P58, P60

Who and where

  • Hillingdon council housing tenants receiving upgrades to kitchens, bathrooms, windows, roofs, boilers and energy efficiency measures Report P12, P14, P19, P21, P26
  • Residents with disabilities and mobility needs receiving HRA adaptations under the Equality Act 2010 Report P24
  • Leaseholders subject to Section 20 consultation and recharges for qualifying works Report P58
  • Residents in street properties with EPC below band C, prioritised for Green Homes Initiative works Report P18
  • Residents in approximately 120 general needs communal blocks receiving access control upgrades Report P32

Timeline

  • 13 March 2025: Previous Cabinet approved tender for supply and installation of stairlifts, hoists and through-floor lifts Report P91
  • 2025/26 financial year: HRA Works to Stock Programme and Green Homes Initiative delivered, with 2025/26 forecast outturn of £34.7m against a revised budget of £51.0m (rephasing variance of £16.2m) Report P49, P80
  • February 2026: Capital programme budget approved at Cabinet and Council as part of the 2026/27 MTFS Report P67
  • 19 March 2026: Cabinet decision taken to agree the 2026/27 programme and delegate authority
  • 5pm Friday 27 March 2026: Deadline for the Corporate Resources and Infrastructure Select Committee to call in the decision
  • Spring 2026 to Autumn 2027: Roofing programme: surveys, Section 20 consultation, tendering, then commencement and completion Report P12

Plain English for the jargon

  • HRA: Housing Revenue Account: a ring-fenced account for income and spending on council housing
  • WTS: Works to Stock: planned capital investment to upgrade council housing
  • MTFS: Medium-Term Financial Strategy: the council's multi-year budget and capital planning framework
  • EPC: Energy Performance Certificate: rating of a home's energy efficiency
  • EICR: Electrical Installation Condition Report: periodic safety inspection of electrical systems
  • Section 20: Consultation process under the Landlord and Tenant Act 1985 for qualifying leasehold works
  • SHDF: Social Housing Decarbonisation Fund: government grant for energy efficiency upgrades
  • MVHR: Mechanical Ventilation with Heat Recovery: system that recovers heat from extracted air
  • FRA: Fire Risk Assessment
  • AOV: Automatic Opening Vent: smoke ventilation opening in buildings
  • Awaab's Law: Legal duty on social landlords to address specified hazards in homes within set timescales
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

That the Cabinet: 1) Note the delivery of the 2025/26 Housing Revenue Account (HRA) Works to Stock Programme set out in the report, which has continued to provide essential upgrades to the Council’s housing stock, along with higher energy efficiency standards and improvements to the quality of life of tenants, set out in Appendix 1. 2) Agrees the HRA Works to Stock Programme for the ensuing 2026/27 financial year; and approves the release of the HRA WTS Capital Programme budget, as set out in this report. 3) To deliver this Programme, delegate authority to the Corporate Director of Residents Services, in consultation with the Cabinet Member for Corporate Services & Property to: a) Utilise existing internal or external framework agreements or develop new LBH framework agreements for Cabinet approval, to enable the effective delivery of appropriate works, tenders, and contracts. b) Approve the procurement of individual projects and works set out, including using any approved LBH framework or term contract by Cabinet. c) Release project specific capital funds for the specific works, as set out in the programme, and strictly within approved budgets and subject to any internal spend control requirements. d) Agree minor variations to specific projects within the programme, subject to agreement from the Cabinet Member for Corporate Services & Property. e) Make any other operational decisions required to implement the programme and works agreed by the Cabinet. 4) Agree that relevant portfolio Cabinet Members receive regular updates on progress delivering the programme and spend. Reasons for decision The Cabinet Member for Corporate Services and Property introduced a report on the Council’s housing investment programme, highlighting the Council’s continued commitment to improving its social housing stock. It was reported that £45 million would be invested in the coming year, including just under £31 million in direct capital works, over £10 million through the Green Homes Initiative, and more than £4 million for Housing Revenue Account (HRA) adaptations to support residents with disability and mobility needs. The programme included extensive roofing works, replacement of windows in around 500 homes to improve thermal efficiency and reduce heating costs, and the renewal of approximately 1,000 kitchens and 800 bathrooms. Investment under the Green Homes Initiative would focus on homes with an EPC rating below C, supporting the Council’s aim to meet government standards by 2030 through measures such as insulation, heat recovery systems and window upgrades. Further works included boiler replacements, lift upgrades, door entry and access control systems, emergency lighting and fire safety improvements. The Cabinet Member remarked that the programme would improve living conditions and help the Council meet its decency standards. The Leader of the Council welcomed the comprehensive programme, noting that it would significantly improve the condition of the housing stock and that reinvesting rental income back into homes was essential to ensuring residents lived in decent, well?maintained properties. Cabinet, therefore agreed the forward investment programme and delegated authority to carry out the works efficiently. Alternative options considered and rejected Cabinet could have chosen to amend the works programme or not delegate its delivery as such to officers. Relevant Select Committee Corporate Resources & Infrastructure Expiry date for any scrutiny call-in / date decision can be implemented (if no call-in) Cabinet’s decisions on this matter can be called in by a majority of the select committee by 5pm, Friday 27 March 2026. If not called-in by then, Cabinet’s decisions can then be implemented. Officer(s) to action Gary Penticost Directorate Residents Services Classification Public - The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET

Reasons for recommendation

This is an annual report to agree the programme of works and projects for the ensuing financial year and to also provide delegated authority to officers to streamline decision-making where necessary for efficient delivery of the programme, subject to Cabinet agreement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Forward Investment Programme 2026/27 (and 2025/26 review)Report 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
IE
Councillor Ian EdwardsChair, present
JB
Councillor Jonathan BiancoVice-Chair, present
SO
Councillor Susan O'BrienCommittee Member, present
JP
Councillor Jane PalmerCommittee Member, apologies
EL
Councillor Eddie LaveryCommittee Member, present
ST
Councillor Steve TuckwellCommittee Member, present
WB
Councillor Wayne BridgesCommittee Member, present
SM
Councillor Stuart MathersCouncillor, in attendance
SP
Councillor Sital PunjaCouncillor, in attendance
JS
Councillor Jan SweetingCouncillor, in attendance

On this subject at Hillingdon

Search all
  1. Housing Forward Investment Programme 2026/27 (and 2025/26 review)This decision
  2. Housing Forward Investment Programme 2025/26 and 2024/25 reviewNoted
  3. Housing Forward Investment Programme 2024/25 and 2023/24 reviewNoted
  4. Housing Forward Investment Programme 2023/24 - interim reportAgreed

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies