West London Waste Plan - Regulation 19 Consultation (policy framework)

Noted Executive 4 papers

AI summaryHillingdon Cabinet recommends Full Council approve publishing the proposed West London Waste Plan for an 8-week public consultation starting August 2026, safeguarding 21 waste sites in the borough to 2041.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPublish and consult on Regulation 19 West London Waste Plan
Money£3k for this decisionFrom existing Planning Service revenue budget for consultation
What happens nextFull Council 9 July 2026Then 8-week Regulation 19 consultation in August 2026
Who it affectsWaste planning in Hillingdon21 safeguarded waste sites; collaborative plan with 6 other authorities

What was decided

Cabinet recommended Full Council authorise publication and consultation of the Proposed Submission (Regulation 19) West London Waste Plan, attached at Appendix A. Report P1, P2

Cabinet recommended delegating authority to the Director of Planning and Sustainable Growth to make minor modifications before, during and after consultation, and to submit the plan under Regulation 22. Report P84

Cabinet endorsed using the Regulation 19 plan for development management purposes, with weight given in line with paragraph 49 of the National Planning Policy Framework. Report P6

Why

The current West London Waste Plan was adopted in 2015 and is considered out of date against national and regional planning policy. Report P1, P7

A new plan is needed to manage expected waste arisings over the next 15 years and to meet the government's 31 December 2026 submission deadline under the current plan-making system. Report P7, P10, P22

The plan has been developed jointly with the west London boroughs of Brent, Ealing, Harrow, Hounslow, Richmond upon Thames and the Old Oak and Park Royal Development Corporation (OPDC). Report P8, P16, P19

What happens next

Full Council is scheduled to consider the recommendations on 9 July 2026. Report P2

If approved, the Regulation 19 plan will be published for an 8-week consultation in August 2026, with representations reviewed afterwards. Report P59, P60

The plan is to be submitted to the Secretary of State by December 2026, with examination in early to mid 2027 and adoption targeted for late 2027 or early 2028. Report P22, P62

The money

  • £29,500 per year per borough Overall consultancy and project management cost (2023/24 to 2027/28), funded from the Strategic Planning Earmarked Reserve Report P63
  • £30k per borough per year Total consultancy and project management cost over the five-year period, per Corporate Finance Report P74
  • no more than £3k Cost of this decision to administer consultation at borough level (newspaper adverts, printing, distribution) Report P64
  • 192,370 tonnes per annum HIC waste capacity Tower Hamlets Council is seeking to transfer to the west London waste area Report P30
  • 56,935 tonnes per annum C, D and E waste capacity Tower Hamlets Council is seeking to transfer to the west London waste area Report P30

Options considered

  • Chosen: Consult on the Regulation 19 version of the plan and supporting evidence, then submit the plan for examination. Provides an up-to-date Waste Local Plan, keeps the process on track and meets the December 2026 government deadline Report P5, P10
  • Rejected: Do not proceed with the Regulation 19 consultation and submission. Would delay an up-to-date Waste Plan, weaken planning decisions across West London, risk missing the deadline and could require restarting the process Report P8, P9, P10

Implications

  • Legal: The plan must follow the Town and Country Planning (Local Planning) (England) Regulations 2012 procedures, and the duty to cooperate under section 33A of the Planning and Compulsory Purchase Act 2004 applies. Report P76, P78, P79
  • Financial: The £3k consultation cost is funded from the existing Planning Service revenue budget; wider project costs are met from the Strategic Planning Earmarked Reserve. Report P64, P74
  • Risk: If the December 2026 deadline is missed, the whole plan process including consultation would have to be restarted under the new plan-making system. Report P10, P22
  • Other: The potential expansion of Heathrow Airport has not been incorporated at this stage; the plan acknowledges the issue and will be revisited if required. Report P33, P34

Who and where

  • Hillingdon residents and communities affected by waste management decisions Report P66
  • Operators of the 21 safeguarded waste sites in Hillingdon Report P50, P53
  • Participating west London boroughs and OPDC: Brent, Ealing, Harrow, Hillingdon, Hounslow, Richmond upon Thames, OPDC Report P8, P16
  • Other London boroughs seeking to use surplus waste capacity, including Westminster, Tower Hamlets and Lambeth Report P29, P30, P31
  • Heathrow Airport Ltd, which raised concerns about safeguarded sites in its proposed expansion area Report P33

Timeline

  • 20th November 2025: Cabinet approved Regulation 18 Draft Plan for consultation Report P12
  • 11th December 2025 to 5th February 2026: Regulation 18 public consultation across west London Report P20, P25
  • 18th February 2026: Draft plan considered at Residents' Services Select Committee Report P14
  • 25th March 2026: The Town and Country Planning (Local Planning) (England) Regulations 2026 came into effect Report P22
  • June / July 2026: Cabinet and Full Council approval of Regulation 19 Proposed Submission Report P62
  • 9th July 2026: Full Council scheduled to consider the recommendations Report P2
  • August 2026: 8-week Regulation 19 publication and consultation Report P59, P62
  • October / November 2026: Cabinet and then Full Council approval of Regulation 22 submission version Report P62
  • December 2026: Plan submitted to Secretary of State for independent examination Report P22, P62
  • Early / Mid 2027: Examination hearings (if needed) Report P62
  • Mid 2027: Main modifications (if needed) published for representations Report P62
  • Late 2027: Inspector's Report expected Report P62
  • Late 2027 / Early 2028: Plan adoption targeted Report P62

Plain English for the jargon

  • WLWP: West London Waste Plan, a joint local development document for west London
  • Regulation 19: Stage of local plan preparation requiring publication of the proposed submission plan for consultation before examination
  • Regulation 22: Stage at which the plan and supporting documents are submitted to the Secretary of State for examination
  • HIC waste: Household, Industrial and Commercial waste
  • C&D waste: Construction and Demolition waste
  • OPDC: Old Oak and Park Royal Development Corporation
  • NPPF: National Planning Policy Framework
  • Duty to cooperate: Duty under section 33A of the Planning and Compulsory Purchase Act 2004 on local planning authorities to engage constructively on strategic matters
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the Cabinet recommend to Full Council to: 1) Authorise the publication and consultation of the Proposed Submission (Regulation 19) West London Waste Plan attached in Appendix A; 2) Delegate authority to the Director of Planning and Sustainable Growth (as Chief Planning Officer) to, in conjunction with other participating boroughs: a. Make minor modifications to the Proposed Submission (Regulation 19) West London Waste Plan and accompanying documents before consultation launch; b. Suggest any necessary proposed modifications to the West London Waste Plan and accompanying documents as well as undertaking any associated consultation required throughout the examination process to ensure that the West London Waste Plan can be found sound by the Planning Inspector; and c. Make minor modifications to the Proposed Submission (Regulation 19) West London Waste Plan and accompanying documents following consultation and submit these documents under Regulation 22 to the Secretary of State. 3) Endorse that the Proposed Submission (Regulation 19) West London Waste Plan to be used for development management purposes in determining planning applications related to waste management development, with appropriate weight given in accordance with paragraph 49 of the National Planning Policy Framework. Reasons for decision The Cabinet Member for Planning, Housing and Property introduced a report on the proposed Regulation 19 consultation for the draft West London Waste Plan. It was explained that the plan had been developed collaboratively with neighbouring West London boroughs to ensure a coordinated and effective approach to waste management across the sub - region. The draft plan had been supported by extensive joint working and independent testing to ensure it was robust, deliverable and capable of meeting future waste capacity needs. It was noted that the potential expansion of Heathrow Airport remained an area of uncertainty and had not been incorporated at this stage, with the plan to be revisited if required. The Cabinet Member advised that for Hillingdon, the proposed sites remained unchanged from the existing plan, with previously considered additional sites having been discounted as unsuitable. The Leader of the Council highlighted the importance of the plan, noting that although it operated largely in the background, it had a direct impact on residents. He confirmed that the recommendations, if agreed, would be referred to full Council. The Corporate Director of Residents Services advised that the programme remained on track to meet government deadlines. Cabinet noted the report and approved the recommendations. Alternative options considered and rejected Not proceeding was rejected as it would have delayed an up-to-date Waste Plan, weakened planning decisions across West London, risked missing the required deadlines, and potentially required restarting the plan process. Relevant Committee Corporate Resources & Infrastructure Expiry date for any scrutiny call-in / date decision can be implemented (if no call-in) Not for call-in, as a policy framework document that will ultimately be considered by the full Council. This decision takes immediate effect. Officer(s) to action Gavin Polkinghorn Directorate Residents Services Classification Public - The report and any background papers relating to this decision by the Cabinet are available to view on the Council's website or by visiting the Civic Centre, Uxbridge
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET

Reasons for recommendations

The West London Waste Plan (WLWP) is part of the Council’s development plan and, therefore a policy framework document. The current plan was adopted in 2015 and is considered in many respects to be out-of-date in the context of national and regional planning policy and therefore needs to be replaced.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Regulation 19 Proposed Submission West London Waste PlanAppendix A 5.1 MB Download
PDF
Regulation 18 Plan Consultation StatementAppendix B 1.4 MB Download
PDF
Integrated Impact Assessment for the West London Waste Plan Regulation 19 ConsultationAppendix C 6.3 MB Download
PDF
West London Waste Plan: Regulation 19 Consultation (policy framework)Report 428 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 16 attended
ST
Councillor Steve TuckwellChair, present
RM
Councillor Richard MillsVice-Chair, present
EL
Councillor Eddie LaveryCommittee Member, apologies
SO
Councillor Susan O'BrienCommittee Member, present
WB
Councillor Wayne BridgesCommittee Member, present
ND
Councillor Nick DenysCommittee Member, present
AB
Councillor Adam BennettCommittee Member, present
DM
Councillor Douglas MillsAttendee of the Cabinet meeting as Chief Whip - non-voting, present
TZ
Tony ZamanOfficer, present
PC
Pete CarpenterOfficer, present
JK
Julie KellyOfficer, present
ST
Sandra TaylorOfficer, present

All 16 on the meeting page

On this subject at Hillingdon

Search all
  1. West London Waste Plan - Regulation 19 Consultation (policy framework)This decision
  2. West London Waste PlanNoted
  3. West London Waste Plan Regulation 19Approved
  4. West London Waste Plan Regulation 18 Consultation - Policy FrameworkAgreed
  5. Hillingdon Council's membership of the West London Economic Prosperity BoardApproved
  6. Health and Care Strategy for North West LondonAgreed

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies