What was decided
The application was approved, with the decision to grant full planning permission for demolition and redevelopment of the site to provide two modern employment units for flexible use across classes E(g)(iii), B2 and B8, alongside car parking, service yards, landscaping and associated works. Report 3.1, 1.10
Approval is subject to the planning conditions set out in Appendix 1 of the report and to securing a Section 106 legal agreement covering the heads of terms listed in the recommendation summary. Report 1.10
Why
The site is within a designated Strategic Industrial Location and the proposed industrial uses are supported in principle under national, London and local plan policies, with the redevelopment of small, out-of-date units into modern flexible floorspace considered acceptable on balance despite a 783 sqm reduction in built footprint. Report 7.2, 7.3, 7.6, 7.7, 1.2
The proposal would not harm the character of the surrounding industrial area, neighbouring residential amenities, the safe operation of the highway network, and would meet policy expectations on flood risk, sustainable drainage, biodiversity net gain and climate change, with the energy strategy delivering a 101.1% reduction in CO2 emissions. Report 1.4, 1.5, 1.7, 1.8, 7.39, 7.67
All consulted statutory and internal consultees raised no objections or only objections that could be addressed by condition or planning obligation, and no representations were received from the public. Report 6.3, 7.4, 7.31, 7.53
What happens next
Finalise the Section 106 legal agreement to secure air quality mitigation, healthy streets contribution, 'Be Seen' energy monitoring, an employment and construction training scheme, and a project management and monitoring fee equal to 5% of total financial contributions. Report 1.9, P200
Apply the planning conditions set out in Appendix 1 covering, among other matters, contamination remediation, noise management, drainage strategy and verification, fire evacuation lifts, landscaping, materials, biodiversity net gain, travel plan, parking, EV charging and cycle parking. Report 7.48, 7.28, 7.45, 7.18, 7.39, 7.63
A CIL Liability Notice will be issued after determination, applying the Mayoral CIL rate of £60 per square metre and the Hillingdon CIL rate of £5 per square metre for industrial development, subject to indexation. Report 8.8, 8.9, 8.10
The money
- £223,266 Level of air quality mitigation required by the Council's Air Quality Officer for traffic emissions Report 7.31, P61
- £196,096 Air Quality Mitigation contribution to be secured under S106 Head of Term (i) Report P200
- £27,170 Healthy Streets contribution to be secured under S106 Head of Term (ii) Report 7.53, P200
- 101.1% Reduction in CO2 emissions beyond the Baseline Part L 2021 anticipated by the Energy Strategy Report 7.67
- £60 per square metre Mayoral Community Infrastructure Levy rate (from April 2019), subject to indexation Report 8.8
- £5 per square metre Hillingdon Community Infrastructure Levy rate for industrial development, subject to indexation Report 8.9
- 5% of the total financial contributions Project Management and Monitoring Fee to be secured under S106 Report P200
Options considered
- Chosen: Approve the application subject to conditions and a Section 106 legal agreement. Officers considered the redevelopment acceptable in land use, design, amenity, transport, environmental, sustainability and climate terms, with impacts mitigated by conditions and obligations Report 1.10, 9.1
- Rejected: Refuse the application. No consultees objected in principle, no public representations were received, and the proposal was found to accord with relevant national, London and local plan policies when conditions and obligations are applied Report 6.3, 7.4, 7.9
Implications
- Financial: The developer will pay Section 106 contributions for air quality mitigation and healthy streets, and a project management and monitoring fee equal to 5% of those contributions, plus Mayoral and Hillingdon CIL on additional floor space. Report 8.8, 8.9
- Legal: Approval is conditional on completion of a Section 106 legal agreement to secure the listed heads of terms; without this, the application would not be acceptable in planning terms. Report 1.10, 8.4
- Equalities: The Council's Public Sector Equality Duty under section 149 of the Equality Act 2010 was considered and no adverse equality impacts were identified. Report 8.3, P191
- Climate: The Energy Strategy claims a 101.1% reduction in CO2 emissions beyond the Baseline Part L 2021, significantly exceeding the 35% minimum on-site reduction required by London Plan Policy SI 2, and the development is to be future-proofed for district heat network connection. Report 7.66, 7.67, 7.70
- Risk: Contamination, drainage, fire safety, secured by design, noise, landscaping, biodiversity and other detailed matters are to be controlled by planning conditions to manage identified risks on this potentially contaminated and air quality sensitive site. Report 7.22, 7.33, 7.40, 7.45, 7.48, 2.2
- Other: The development is exempt from Environmental Impact Assessment under the Town and Country Planning (Environmental Impact Assessment) Regulations 2017. Report 8.1
Who and where
- The applicant (owner of land within the wider Orbital Industrial Estate) Report P15, 2.1
- Future occupiers of the two proposed modern employment units Report 3.1, 3.2
- Residents of the four-storey flats and maisonettes on the northern side of Horton Road Report 2.3, 7.24
- Canal & River Trust, as the Grand Union Canal lies to the south of the site Report 2.1, P55
- Users of the local highway network, including HGV and car traffic accessing the industrial estate Report 7.52
Timeline
- 12th November 2025: Expiry of the neighbour consultation process Report 6.1
- 11th March 2026: Re-consultation issued following receipt of amended drawings and reports Report 6.2
- 16th July 2026: GLA consultation on a draft new London Plan opens Report 5.3
- 6th October 2026: Hillingdon Planning Committee considers and approves the application Report P6
- 15th October 2026: GLA consultation on the draft new London Plan closes Report 5.3
- Early 2028: Expected final adoption of the new London Plan following Examination in Public Report 5.3
Plain English for the jargon
- SIL: Strategic Industrial Location, a designation under the Hillingdon Local Plan and London Plan for areas protected for industrial-type uses
- PTAL: Public Transport Accessibility Level, scored 0 to 6b, with 6b the highest; the site scored 1b/2
- BNG: Biodiversity Net Gain, the measurable improvement in biodiversity required by the Environment Act 2021, with a minimum 10% uplift
- S106: Section 106 legal agreement under the Town and Country Planning Act 1990 used to secure planning obligations from developers
- CIL: Community Infrastructure Levy, a charge applied to new development to fund infrastructure, including a Mayoral rate and a Hillingdon rate
- SuDS: Sustainable Urban Drainage Systems, drainage techniques that manage surface water close to source and reduce flood risk
- UGF: Urban Greening Factor, a London Plan measure of the amount and quality of urban greening on a site
- EVCP: Electric Vehicle Charging Point