Resolved
RESOLVED – ( i ) previously agreed reports be noted; (ii) the revised head lease term of 35 years in return for which the freehold of the development would transfer to HBBC on completion of the extended term, be agreed.
Council agreed this item on Tuesday 25 October 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – ( i ) previously agreed reports be noted; (ii) the revised head lease term of 35 years in return for which the freehold of the development would transfer to HBBC on completion of the extended term, be agreed.
1.1Members note previously agreed reports on the relocation of the Council Offices to the Hinckley Hub development including the co-location of partners to provide a public service hub.
1.2To seek Members approval for the council to commit to the revised head lease term of 35yrs in return for which the freehold of the development (building and land) will transfer to Hinckley & Bosworth Borough Council on completion of the extended term.
2.1That Members note the previously agreed reports.
2.2That Members approve the revised head lease term of 35yrs in return for which the freehold of the development to transfer to Hinckley & Bosworth Borough Council on completion of the extended term.
3.1Positive progress has been made over the past 6 months in bringing forward the Hinckley Hub project and the initiative to co-locate with other public partners to the proposed new Masterplan development.
3.2June 2010 – Members were provided with an options appraisal report to consider the future location for the Council Offices. This report effectively gave the Members the choice of development options providing a solution for relocating the council offices along with the associated risks and likely timescales for delivery. It was agreed that the Deputy Chief Executive (Corporate Direction) and the Estates and Asset Manager be given delegated responsibility for agreeing with MRP Developments Ltd the office development specification and BREEAM rating and contractual terms of the lease in conjunction with the Chief Officer for Corporate Resources.
3.3April 2011 - Executive Members agreed with the concept of co-location with other public partners to the Hinckley Hub whilst acknowledging the associated risks and mitigating developer incentives. At this time Executive Members also confirmed support for signing of the head lease of the Hinckley Hub building allowing the project to be developed within the agreed timescales.
3.4August 2011 – Report to update Council on the final position with regard to partner organisations co-locating their services within the Hinckley Hub development on the corner of Hawley Road and Rugby Road in Hinckley. It was agreed at this time for the Council to enter into the Head Lease for 41,042 sq/ft.
4. ADDITIONAL FINANCIAL INCENTIVE PROPOSED BY THE DEVELOPER
4.1Recent negotiations with MRP Developments Ltd and change in funding provider for the project have lead to an additional developer incentive over and above those already agreed at Full Council. In return for extending the 30 year lease term for the Hinckley Hub development to 35 years it has been offered that the freehold of the development can be transferred to Hinckley and Bosworth Borough Council for the consideration of £1.00 on completion of the extended lease term. The freehold will include the Hinckley Hub building and the land on which it is developed as identified in the agreed contract documentation.
5. FINANCIAL IMPLICATIONS (IB)
5.1Since this report seeks a revision to the head lease term and a change in title to the development there are no additional financial implications other than those already as reported to Council in August 2011.
6. LEGAL IMPLICATIONS (AB)
6.1The freehold transfer will be dealt with by insertion in the lease of options in favour of both the Council and the Landlord to require to the other party to either transfer or accept the transfer of the property as the case may be. As stated above the consideration for the transfer will be one pound
7. CORPORATE PLAN IMPLICATIONS
None identified arising directly from the report.
8.1Consultation with all partner organisations and the Council staff will need to be undertaken and has begun and will continue to be undertaken throughout the life of the project.
9.1Risks have been considered and stated within the project management of this development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Hinckley Hub Final Developer IncentiveReport | 30 KB | DownloadRead as text |
Follow Council at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Minutes of the previous meetingRESOLVED – the minutes of the meeting held on 29 September be approved. | Approved | Open |
| 27 Oct 2026 | Review of the council's constitutionRESOLVED – the changes to the constitution be approved. | Approved | Open |
| 27 Oct 2026 | Community Governance Review - Witherley - final recommendationsRESOLVED – (i) The current parish of Witherley and Witherley Parish Council be abolished; (ii) Fenny Drayton parish a... | Decided | Open |
| 29 Sep 2026 | Minutes of the previous meetingsRESOLVED – the minutes of the meetings held on 23 July and 4 August 2026 be confirmed as a correct record. | Decided | Open |
| 29 Sep 2026 | Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.