Resolved
RESOLVED – the committee endorse the report and agree a report be brought to the next meeting on the progress regarding risk management.
Finance, Audit & Performance Committee agreed this item on Monday 31 October 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the committee endorse the report and agree a report be brought to the next meeting on the progress regarding risk management.
HINCKLEY AND BOSWORTH BOROUGH COUNCIL
Internal Audit Progress Report
Finance and Audit Select Committee Meeting – 31st October 2011 st HINCKLEY AND BOSWORTH BOROUGH COUNCIL Internal Audit Progress Report – 31 October 2011
CONTENTS SECTION Page 1 Introduction 1 2 Final reports issued 1 3 Key Findings from Internal Audit Work 2 4 Work in Progress or Planned 4 5 Liaison with Management and External Audit 4 6 Changes to our Plan 4 Appendix A Hinckley and Bosworth Borough Council – Operational Plan Performance 2011/12 5 Appendix B Hinckley and Bosworth Borough Council – Executive Summaries and Action Plans: 9 Risk Management Housing Allocations and Voids
Health and Safety Homelessness
Project Management Treasury Management
Key Performance Indicators IT Strategy Review
Planning
The matters raised in this report are only those which came to our attention during our internal audit work and are not necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required. Whilst every care has been taken to ensure that the information provided in this report is as accurate as possible, based on the information provided and documentation reviewed, no complete guarantee or warranty can be given with regard to the advice and information contained herein. Our work does not provide absolute assurance that material errors, loss or fraud do not exist.
This report is prepared solely for the use of Board and senior management of Hinckley and Bosworth Borough Council. Details may be made available to specified external agencies, including external auditors, but otherwise the report should not be quoted or referred to in whole or in part without prior consent. No responsibility to any third party is accepted as the report has not been prepared, and is not intended for any other purpose.
© 2011 RSM Tenon Limited. RSM Tenon Limited is a member of RSM Tenon Group. RSM Tenon Limited is an independent member firm of RSM International an affiliation of independent accounting and consulting firms. RSM International is the name given to a network of independent accounting and consulting firms each of which practices in its own right. RSM International does not exist in any jurisdiction as a separate legal entity.
RSM Tenon Limited (No 4066924) is registered in England and Wales. Registered Office 66 Chiltern Street, London W1U 4GB. England
1 st HINCKLEY AND BOSWORTH BOROUGH COUNCIL Internal Audit Progress Report – 31 October 2011
1. INTRODUCTION th 1.1 The periodic internal audit plan for 2011/12 was approved by the Finance and Audit Select Committee on 14 February 2011. This report summarises the outcome of work completed to date against that plan, and Appendix A provides cumulative data in support of internal audit performance.
2. FINAL REPORTS ISSUED 2.1 We have finalised 9 reports since the last Committee meeting; these are in the areas of:
Risk Management; Health and Safety; Project Management; Key Performance Indicators; Planning; Housing Allocations and Voids; Homelessness; Treasury Management; and IT Strategy Review. 2.2 The executive summaries and agreed action plans for recommendations classified as ‘High’ and ‘Medium’ risk are included at Appendix B. Full reports of all recommendations including ‘Low’ risk can be provided upon request. The ‘Low’ risk recommendations are not included in this report, as it is felt that time and attention should be focused on the more significant risks facing the Authority (i.e. ‘High’ and ‘Medium’ recommendations).
1 st HINCKLEY AND BOSWORTH BOROUGH COUNCIL Internal Audit Progress Report – 31 October 2011
3. KEY FINDINGS FROM INTERNAL AUDIT WORK 3.1 We have raised 48 recommendations across the 9 reviews that are being presented to this Committee; eight recommendations have been classified as ‘High’ Risk, 10 recommendations have been classified as ‘Medium’ Risk and the remaining 30 recommendations have been classified as ‘Low’ Risk.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT PROGRESS REPORTReport | 641 KB | DownloadRead as text |
Follow Finance, Audit & Performance Committee at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2016 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 8 February 2016 be confirmed and signed by the Chairman. Councillor Wal... | Decided | Open |
| 8 Feb 2016 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 7 December 2015 be approved. | Approved | Open |
| 8 Feb 2016 | External Audit Grants Certification Report 2014/15RESOLVED – the report be noted. | Noted | Open |
| 8 Feb 2016 | Internal Audit Progress ReportRESOLVED – the report be noted. | Noted | Open |
| 8 Feb 2016 | Business Rates and Pooling UpdateRESOLVED – the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.