Resolved
RESOLVED (i) Members agreed that option 4.1 be put forward to Council; (ii) Members agreed with the bids set out in the report (iii) Members note the financial implications set out in section 7.
Finance, Audit & Performance Committee agreed this item on Monday 12 December 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (i) Members agreed that option 4.1 be put forward to Council; (ii) Members agreed with the bids set out in the report (iii) Members note the financial implications set out in section 7.
1.1To consider the Capital Programme for the years 2011/12 to 2014/15.
2.1Members consider the programme that will be presented to Council for approval. In particular:
• to note the funding options set out in section 4 below to recommend to Council, and • to note the applications for new bids as set out in section 5 and to decide which of these bids to support and build into the capital programme.
2.2Note the financial implications contained in section 7.
3.1Projects in the programme have been submitted by Project Officers and reflect outcomes from the Officers Capital Forum Group, SLB and changes after the report being presented to Executive Briefing on the 10th November 2011
3.2Members will be aware of the issues surrounding future capital funding in particular the drawdown on the current capital receipts reserve as highlighted in section 4 below. The pressure on future funding of the capital programme and the depletion of reserves has previously been raised with members and were reported to Council in February 2011.
3.3A historitcal summary of the reduction in the capital receipts reserve is attached in Appendix A. The large receipt from Montgomery Road received in 2005/06 has been used to fund projects. No major receipts have been received after 2008/09, which together with a reduction from Right to Buy Sales has meant the reserve balance has reduced from £7.58m in 2007/08 to £1.26m by the end of March 2011.
3.3The attached programme Appendix B assumes a virtual standstill position on schemes for future years.
3.4Projects have been reprofiled in line with the latest spending and external funding forecasts. The major change being the reprofiling of the Richmond Park Project as a result of funding approval delays with the Football Association (FA).
3.5Within the current financial year there may be an underspend on Private Sector Housing on minor and major works of around £180,000. Due to changes in the referral system the amount of approvals have reduced. There may however be 1 a backlog that would need to be covered by this underspend. Additionally, the Disabled Facilities Grant budget will, in the future, no longer be supported through decent homes funding. This means that the level of expenditure will need to reduce to £295,000. Because of these uncertain compensating pressures, the potential underspend of around £180,000 has not been built into the funding assumptions below.
4.0Programme to 2014-15 – Funding Issues
4.1Due to major schemes now being completed the programme will be relatively small in future years. However, due to reduced funding even a status quo programme will have an impact on the council’s general fund revenue account. The estimated cost of borrowing will be £12,873 in financial year 2012/13 rising to £99,589 by 2014/15. This assumption is based on a major use of the capital receipts reserve, estimated receipts from right to buy sales and disposal of other small plots. At the end of 2014/15 only £192,000 will be left in the capital receipts reserve. The position is summarised below:-
Table 1
2011/12 2012/13 2013/14 2014/15 Opening Bal (1260) (1227) (178) (48) Receipts (1484) (520) (274) (144) Funding used 1517 1,569 404 0 Cl (Bal) (1227) (178) (48) (192)
Financially, this option carries a great risk due to the application of receipts from land sales before they have materialised. The anticipated sales are detailed within Appendix C.
4.2If an assumption is made that apart from sales in the current financial year only estimated right to buy sales are used the impact would be as follows:-
Table 2
2011/12 2012/13 2013/14 2014/15 Opening (Bal) (1260) (1227) 0 0 Receipts (1484) (120) (144) (144) Funding used 1517 1,569 404 0 Cl (Bal) (1227) 221 302 (144) Borrowing - (221) (302) -
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
4. Appendix AAppendix | 32 KB | Download |
PDF |
4. Appendix CAppendix | 15 KB | Download |
PDF |
4. AppendixBAppendix | 24 KB | Download |
PDF |
Capital Programme 2011/12 to 2013/14Report | 63 KB | DownloadRead as text |
Follow Finance, Audit & Performance Committee at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2016 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 8 February 2016 be confirmed and signed by the Chairman. Councillor Wal... | Decided | Open |
| 8 Feb 2016 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 7 December 2015 be approved. | Approved | Open |
| 8 Feb 2016 | External Audit Grants Certification Report 2014/15RESOLVED – the report be noted. | Noted | Open |
| 8 Feb 2016 | Internal Audit Progress ReportRESOLVED – the report be noted. | Noted | Open |
| 8 Feb 2016 | Business Rates and Pooling UpdateRESOLVED – the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.