Executive, Thursday 22 March 2012 at 6.30pm

HRA SUBSIDY BUDGET DEBT STRUCTURE

Decided Executive 2 papers

Executive decided this item on Thursday 22 March 2012. Below is the council's own wording, with the papers it was decided on.

Item439

Resolved

RESOLVED – (i) the debt arising from the buyout of the HRA Subsidy system be repaid in equal instalments over a period of 23 years starting in 2020/21; and (II) the Council borrows the sum of £67,652,000 in a series of 23 equal maturity PWLB loans from 8 to 30 years as set out in option 4.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Executive, 3 pages

Purpose of report

To seek Executive’s approval to the structuring of the borrowing required to finance the HRA subsidy buyout payment that the Council is due to make on 28 March 2012.

Recommendation

The Executive is recommended to approve

1. that the debt arising from the authority buying itself out of the HRA Subsidy system is repaid in equal instalments over a period of 23 years starting in 2020/21

2. that the Council borrows the sum of £67,652,000 in a series of 23 equal Maturity PWLB loans from 8 to 30 years.

3. BACKGROUND TO THE REPORT

As members will be aware the Council is required to buy itself out of the HRA subsidy system with a payment to DCLG of £67.652m on 28 March 2012 and intends to finance this by borrowing. It is considered that, following the announcement in September 2011 by the Chief Secretary to the Treasury that the margins charged by the PWLB over Gilt rates would be reduced by 0.85% for loans taken out to finance these payments, the most cost effective borrowing vehicle would be PWLB Loans.

At the present time the PWLB rates curve is structured so that short term money is very cheap with say 5 year money at around 2.15% (which would mean that for the buyout transaction the authority would be charged 1.3% for a 5 year loan). Longer term loans whilst cheap in historical terms are more expensive at 4.3% (3.45% for buyout purposes). Whilst short term borrowing would appear to be good value it must be remembered that at the end of the term the loan would either need to be repaid (with a charge to the revenue account) or refinanced probably at a significantly higher cost, which at the present time is unknown but as interest rates are at an all time low presently it must be assumed that future rates will be higher than now.

In order to obtain a degree of stability in the interest costs but also to take advantage of the cheaper shorter term rates it is recommended that the total sum borrowed is divided into a series of maturity loans linked to the repayment profile.

At a special meeting of the Scrutiny Commission on 13 March 2012 it was recommended

1. that the Executive adopts a debt repayment structure for the buyout of HRA subsidy based on the model commencing repayment in year 15, as that option maximises the potential for the council to increase its stock capacity over time on as well as improving the quality of the existing stock within 30 years overall debt repayment period. 2. that detailed requests on the use of the headroom generated be conceived during 2012, as part of the development of the long term strategy on the use of available funding.

3. that council confirms the change to a term of 30 years at its next scheduled meeting.

Officers have since undertaken further work on some options and are now of the opinion that if repayments were to start in year 8 the Council would be able to take advantage of the lower short term rates reducing the overall interest cost by £10m over the 30 year period whilst still providing a significant amount of headroom for investment in new and existing stock in the early part of the plan period.

The suggested debt profile and first year interest cost is shown as option 4 on appendix 1

4. FINANCIAL IMPLICATIONS [DB]

In the draft HRA budget for 2012/13 provision was made for a principal repayment of £2,719,720 and interest of £1,808,580 based on the projected debt profile and interest rates ruling on 14 March 2012 it is estimated that the cost of the loans will be £2,098,000. This means that an amount of £2,430,300 would be available in 2012/13 for transfer to reserves for future capital financing or balances.

5. LEGAL IMPLICATIONS [LH]

The decision of the Council to repay the loan over a maximum of 25 years will require amendment by Council, this can be done by motion to amend signed by at least eight Members.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Copy of Appendix B: Borrowing Profile 140312Appendix 1 pages Download
PDF
HRA SUBSIDY BUDGET DEBT STRUCTUREReport 3 pages DownloadRead as text

At this meeting

Whole meeting
439HRA SUBSIDY BUDGET DEBT STRUCTUREThis decision

On this subject at Hinckley and Bosworth

Search all
  1. HRA SUBSIDY BUDGET DEBT STRUCTUREThis decision
  2. HRA Subsidy BuyoutDecided

More from Hinckley and Bosworth Executive

All decisions
MeetingDecisionOutcome
23 Sep 2026 Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... Decided Open
23 Sep 2026 Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... Approved Open
23 Sep 2026 Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. Approved Open
29 Jul 2026 Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... Noted Open
29 Jul 2026 Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies