Finance, Audit & Performance Committee agreed this item on Monday 26 March 2012. Below is the council's own wording, with the papers it was decided on.
It was agreed that a structure chart and a copy of the Plan be made available to the Committee. Data Protection Compliance It was reported that subcontractors are now complying with the Act. Sheltered Accommodation (Tenants’ Funds) Guidelines and training will be given to tenants to help them manage their funds effectively and transparently. The Deputy Chief Executive (Corporate Direction) gave his thanks to RSM Tenon for their help and support during their contract with the Council. The Chairman echoed these remarks.
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
Report to Finance, Audit & Performance Committee, 49 pages
HINCKLEY AND BOSWORTH BOROUGH COUNCIL
Internal Audit Progress Report
Finance and Audit Select Committee Meeting – 26th March 2012 HINCKLEY AND BOSWORTH BOROUGH COUNCIL Internal Audit Progress Report – 26th March 2012
CONTENTS SECTION Page 1 Introduction 1 2 Final reports issued 1 3 Key Findings from Internal Audit Work 2 4 Work in Progress or Planned 3 5 Liaison with Management and External Audit 4 6 Changes to our Plan 4 Appendix A Hinckley and Bosworth Borough Council – Operational Plan Performance 2011/12 5 Appendix B Hinckley and Bosworth Borough Council – Executive Summaries and Action Plans: 9 Leicestershire Partnership (LP) (Revenues and Benefits) – Housing Public Consultations Benefits Housing Repairs LP (Revs & Bens) – Council Tax VAT LP (Revs & Bens) – NNDR Sheltered Accommodation (Tenants’ Data protection 1998 Compliance Funds)
The matters raised in this report are only those which came to our attention during our internal audit work and are not necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required. Whilst every care has been taken to ensure that the information provided in this report is as accurate as possible, based on the information provided and documentation reviewed, no complete guarantee or warranty can be given with regard to the advice and information contained herein. Our work does not provide absolute assurance that material errors, loss or fraud do not exist.
This report is prepared solely for the use of Board and senior management of Hinckley and Bosworth Borough Council. Details may be made available to specified external agencies, including external auditors, but otherwise the report should not be quoted or referred to in whole or in part without prior consent. No responsibility to any third party is accepted as the report has not been prepared, and is not intended for any other purpose.
1 HINCKLEY AND BOSWORTH BOROUGH COUNCIL Internal Audit Progress Report – 26th March 2012
1. INTRODUCTION th 1.1 The periodic internal audit plan for 2011/12 was approved by the Finance and Audit Select Committee on 14 February 2011. This report summarises the outcome of work completed to date against that plan, and Appendix A provides cumulative data in support of internal audit performance.
2. FINAL REPORTS ISSUED 2.1 We have finalised 8 reports since the last Committee meeting; these are in the areas of:
Leicestershire Partnership (Revenues and Benefits) – Housing Benefits; Leicestershire Partnership (Revenues and Benefits) – Council Tax;
Leicestershire Partnership (Revenues and Benefits) – NNDR;
Data Protection Compliance 1998;
Public Consultations;
Housing Repairs;
VAT; and
Sheltered Accommodation – Tenants’ Funds.
2.2The executive summaries and agreed action plans for recommendations classified as ‘High’ and ‘Medium’ risk are included at Appendix B. Full reports of all recommendations including ‘Low’ risk can be provided upon request. The ‘Low’ risk recommendations are not included in this report, as it is felt that time and attention should be focused on the more significant risks facing the Authority (i.e. ‘High’ and ‘Medium’ recommendations).
1 HINCKLEY AND BOSWORTH BOROUGH COUNCIL Internal Audit Progress Report – 26th March 2012
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Audit & Performance Committee at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.