Resolved

RESOLVED – ( i ) The Chief Executive in consultation with the Leader be granted delegated authority to sign off the final contract arrangements for the RGF offer; (ii) The establishment of a budget of £19,474,000 for the RGF project to be spent over the next two years be approved.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Council, 3 pages

Purpose of report

1.1To seek Council approval to delegate authority to the Chief Executive in liaison with the Council Leader, for the sign off of the final contract letter for the Regional Grown Fund Bid (RGF).

1.2To establish a budget to administer the £19.5M RGF fund.

Recommendation

2.1That Council agree the delegation of authority to the Chief Executive in consultation with the Leader for the sign off of the final contract arrangements for the RGF offer of £19,474,000.

2.2That Council approve the establishment of a budget of £19,474,000 for the RGF project which will be profiled to be spent over the next two years.

3. BACKGROUND TO THE REPORT

3.1Members will be aware that following a successful bid to Government in the summer of 2011, the Department of Business, Innovation and Skills announced approval in principle to the partnership bid from Hinckley & Bosworth Borough Council and MIRA (supported by LLEP) for the funding for infrastructure to support the development of the £300M MIRA Technology Park. The Council resolved to grant planning consent for MIRA Technology Park in November 2011.

4. RGF OFFER

4.1The formal Conditional Offer from BiS dated 11 June 2012, confirms a grant of up to £19,474,000. This will provide for the following key infrastructure improvements:-

• Duelling of A5 adjacent to MIRA Technology Park and key junction improvements at Redgate and Dodwells/Longshoot.

• Construction of a new primary sub-station to serve the area.

• Sustainable transport improvements including provision of new cycle ways and employment bus facilities.

4.2BiS will require the Council to enter into a formal, legally binding contract for the delivery of the works. Officers have been working with MIRA and representatives of BiS, DCLG, the Highways Agency and Leicestershire and Warwickshire County Councils’ for a number of months to ensure a robust mechanism is established for the delivery of the improvements over the next two years. A draft delivery framework has been agreed and is undergoing due diligence to provide the Council and its Partners with confidence that works can be delivered effectively and that risks are mitigated. 4.3 Due to reporting timescales and the delivery programme, it is vital that Council delegate authority to the Chief Executive, in liaison with the Leader, to sign off final contract arrangements to allow detailed planning and delivery of the infrastructure improvements to take place as soon as possible.

4.4The Council are also required to formally establish a budget to enable the income received from BiS to be administered.

5. FINANCIAL IMPLICATIONS [CB]

5.1If approved both expenditure and income budgets will be created of £19,474,000 meaning no net change to HBBC’s budgetary requirement. As part of the project the Council has already incurred consultancy costs and forward funded the Highway Agency, both of which will be reclaimed from the RGF funding once received. An additional cost which H&BBC will need to bear though is the due diligence report referenced to above which will be between £8 – 10k. Under the terms of the grant funding this fee will not be recoverable.

5.2As this is a major project to be delivered within set timescales, and with significant sums of money involved, it is vitally important that the scheme is carefully managed and monitored. This is essential to avoid any overspend and to ensure all the requirements of the funding body are met. As noted above the robustness of the draft delivery framework is currently being assessed.

6. LEGAL IMPLICATIONS [AB]

6.1The contract with the department of business industry and skills will provide an agreement for them to provide the funding for the works detailed in 4.1 above. A secondary linked agreement between HBBC and MIRA will be entered into for MIRA to carry out the works and for HBBC to regulate the RGF funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RGF late reportReport 3 pages DownloadRead as text

More from Hinckley and Bosworth Council

All decisions
MeetingDecisionOutcome
27 Oct 2026 Minutes of the previous meetingRESOLVED – the minutes of the meeting held on 29 September be approved. Approved Open
27 Oct 2026 Review of the council's constitutionRESOLVED – the changes to the constitution be approved. Approved Open
27 Oct 2026 Community Governance Review - Witherley - final recommendationsRESOLVED – (i) The current parish of Witherley and Witherley Parish Council be abolished; (ii) Fenny Drayton parish a... Decided Open
29 Sep 2026 Minutes of the previous meetingsRESOLVED – the minutes of the meetings held on 23 July and 4 August 2026 be confirmed as a correct record. Decided Open
29 Sep 2026 Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies