Government Consultation on Statutory Consultee Performance and Award of Costs

Noted Planning 2 papers

Planning Committee noted this item on Tuesday 21 August 2012. Below is the council's own wording, with the papers it was decided on.

Item119

Resolved

RESOLVED – the report be noted and the consultation response be agreed with the abovementioned inclusion.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Planning Committee, 9 pages

Purpose of report

1.1To advise Members of, and to seek Members agreement on the appended consultation response on the proposed changes to the Statutory Consultee Performance and Award of Costs consultation, issued by the Department of Communities and Local Government in July 2012.

Recommendation

2.1That Members:

(i) note the content of the report; and (ii) agree the appended consultation response.

3. BACKGROUND TO THE REPORT

3.1The Government is committed to ensuring local authorities deliver an efficient planning service. It expects all those involved in the planning system to play their part. Statutory consultees are organisations and bodies, defined by statute, who must be consulted on relevant planning applications. The Government recognises that Local Planning Authorities can give significant weight to the advice of statutory consultees to such an extent that their comments can lead to the imposition of planning conditions or in some cases the refusal of planning permission. Whilst Local Planning Authorities remain ultimately responsible for planning decisions, statutory consultees should take responsibility for the advice they give.

3.2The Government is keen to promote good practice and ensure advice continues to be of high quality, appropriate to each particular case and provided within the statutory time frame of 21 days. It is consulting on amending guidance in the Award of Costs Circular to promote a proportionate response on the part of statutory consultees when they are advising on planning applications and their subsequent responsibility for that advice at appeal. Together these measures should result in clearer, stronger advice from statutory consultees to Local Planning Authorities and applicants which should then result in quicker, more efficient and fully justified decisions from local authorities.

3.3The scope of this consultation document includes:

• The Government’s proposals to amend guidance in Circular 03/09: Costs Awards in Appeals and Other Planning Proceedings in relation to statutory consultees and their advice at appeal.

• The Government is also announcing clarifications to the guidance in Circular 03/09 in relation to local councils and their development plan, and in relation to ensuring evidence submitted at appeal is manifestly accurate and truthful. • The Government is also proposing to require the five main statutory consultees to report on, and be accountable for, their performance on dealing with planning applications as part of their individual Improvement Plans.

3.4The Policy Context

Statutory consultees are organisations and bodies who must be consulted on relevant planning applications. In November 2011, the Government committed to improving the performance of the key statutory consultees in responding swiftly to applications, the focus of this work is on the five main statutory bodies (English Heritage, Natural England, Environment Agency, Highways Agency and Health & Safety Executive). The Government also announced in November 2011, that it will ensure that there is a more effective mechanism for applicants to obtain an award of costs, if there is an appeal against refusal of a planning permission, where a statutory consultee has acted unreasonably. In 2011, there were no awards of costs against statutory consultees.

During the passage of the Localism Act, the Government committed to revising its guidance on the award of costs regime so that there should be no grounds for an award of costs against a local planning authority if it refuses a planning application that is clearly contrary to a development plan and where no material considerations including national policy indicate that planning permission should have been granted.

3.5The Legal Context

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of costs appendixAppendix 31 pages Download
PDF
Government Consultation on Statutory Consultee Performance and Award of CostsReport 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Government Consultation on Statutory Consultee Performance and Award of CostsThis decision
  2. Government Consultation on streamlining information requirements for planning applicationsNoted

More from Hinckley and Bosworth Planning Committee

All decisions
MeetingDecisionOutcome
17 Nov 2026 24/00610/OUT - Cadent, Brick Kiln Street, HinckleyRESOLVED – the application be deferred. Deferred Open
20 Oct 2026 26/00096/FUL - Clares Barn Farm, 26 Sheepy Road, TwycrossRESOLVED - Planning permission be granted, with the Assistant Director Planning and Regeneration given powers to dete... Decided Open
20 Oct 2026 25/01157/OUT - Land east of the Industrial Estate, Hill Lane, MarkfieldRESOLVED - Permission be granted, subject to: (i) The planning conditions detailed at the end of the report; (ii) The... Agreed Open
20 Oct 2026 25/01192/FUL - EMEB Sports and Social Club, Nutts Lane, HinckleyRESOLVED – Planning permission be granted subject to: (i) The conditions set out in section 11; (ii) The completion o... Agreed Open
20 Oct 2026 25/01231/FUL - Land off Church Road, WitherleyRESOLVED – the application be deferred. At this stage, Councillor C Gibbens exited the meeting having declared a regi... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies