Hinckley and Bosworth Borough Council
Planning Committee, Tuesday 25 September 2012 at 6.30pm

Renegotiation of Section 106 Planning Obligations

Noted Planning 1 paper

Planning Committee noted this item on Tuesday 25 September 2012. Below is the council's own wording, with the papers it was decided on.

Item187

Resolved

RESOLVED – ( i ) the report be noted; (ii) the proposed responses to the questions be endorsed. (Councillors [name removed] and Hodgkins were absent during voting on the application).
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Planning Committee, 4 pages

Purpose of report

1.1To advise Members of, and to seek Members agreement on the consultation response on proposed changes to the time period during which the local planning authority can be formally requested to renegotiate the terms of signed Section 106 agreements.

Recommendation

2.1That Members:

(i) note the content of the report; and

(ii) agree the responses to the questions raised as detailed within this report.

3. BACKGROUND TO THE REPORT

3.1Section 106 of the Town and Country Planning Act 1990 allows a local planning authority to enter into a legally-binding agreement or planning obligation with a landowner, or persons who intend to develop that land, in association with the granting of planning permission. These planning obligations are intended to deliver or address matters that are necessary to make a development acceptable in planning terms. The Borough Council uses such provisions to secure necessary developer contributions in respect of play and open space, affordable housing, education etc.

3.2The Government’s Housing Strategy “Laying the Foundations: A Housing Strategy for England” published on 21 November 2011 set out a number of proposals to help unlock stalled development. There are currently around 1400 housing schemes of over 10 housing units with planning permission that are stalled. 62% of stalled units predate April 2010.

3.3The Government is concerned about the high number of stalled schemes and the lost economic benefit they represent. Some planning obligations negotiated in different economic conditions now make sites economically unfeasible – resulting in no development, no regeneration or community benefits.

3.4The Government want to ensure that effective renegotiation of planning obligations can be achieved to make them more reflective of the current market and help unlock stalled development, whilst continuing to ensure through the use of obligations that development is acceptable to communities and local authorities in line with local plans. Wherever possible, such renegotiation should be agreed on a voluntary basis. It is important to note that HBBC has, when requested, reconsidered the terms of planning obligations to ensure development is delivered.

3.5The intent of the change is to assist in bringing forward stalled development. It will not mean that obligations should be reduced arbitrarily or the terms altered automatically. Nor should it be a reason to permit unsustainable development. It remains that there must be a strong justification for any change, and the resultant obligation must still be sufficient to make the development acceptable in planning terms. The principles for modifying planning obligations are given in section 106A of the Town and Country Planning Act 1990. This requires that an obligation must “no longer serve a useful purpose” or that it “continues to serve a useful purposeequally well” if it is to be modified. These principles will be important considerations during negotiations.

3.6The Proposed Changes

3.7Section 106A of the Town and Country Planning Act 1990 allows voluntary renegotiation of a planning obligation at any time. Where voluntary agreement cannot be reached there may be a formal request to reconsider an obligation when that obligation is 5 years old. The local authority must take a decision on such a request. If the local authority decision is not to renegotiate terms then there is a right to appeal to the Planning Inspectorate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Renegotiation of Section 106 Planning ObligationsReport 4 pages DownloadRead as text

At this meeting

Whole meeting

More from Hinckley and Bosworth Planning Committee

All decisions
MeetingDecisionOutcome
17 Nov 2026 24/00610/OUT - Cadent, Brick Kiln Street, HinckleyRESOLVED – the application be deferred. Deferred Open
20 Oct 2026 26/00096/FUL - Clares Barn Farm, 26 Sheepy Road, TwycrossRESOLVED - Planning permission be granted, with the Assistant Director Planning and Regeneration given powers to dete... Decided Open
20 Oct 2026 25/01157/OUT - Land east of the Industrial Estate, Hill Lane, MarkfieldRESOLVED - Permission be granted, subject to: (i) The planning conditions detailed at the end of the report; (ii) The... Agreed Open
20 Oct 2026 25/01192/FUL - EMEB Sports and Social Club, Nutts Lane, HinckleyRESOLVED – Planning permission be granted subject to: (i) The conditions set out in section 11; (ii) The completion o... Agreed Open
20 Oct 2026 25/01231/FUL - Land off Church Road, WitherleyRESOLVED – the application be deferred. At this stage, Councillor C Gibbens exited the meeting having declared a regi... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies