Resolved
It was agreed to have a further update on section 106 contributions in six months, but to have another report in the meantime, should any progress be made with regard to the Montgomery Road contributions.
Scrutiny Commission agreed this item on Thursday 14 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed to have a further update on section 106 contributions in six months, but to have another report in the meantime, should any progress be made with regard to the Montgomery Road contributions.
1.1To inform members of the Scrutiny Commission of the position in respect of the Section 106 contributions that have not been spent within the 5 year period that contain a 5 year claw back clause and therefore are at risk of being clawed back by the developer, and those that are over 4 years old but not beyond the 5 years threshold.
2.1That the report be noted.
3. BACKGROUND TO THE REPORT
3.1Developers/applicants can be requested to make financial contributions to make a planning application acceptable, where it would otherwise be refused, towards infrastructure needed as a consequence of their development, i.e. towards play and open space, libraries, education facilities etc. The contribution request has to be in accordance with the Community Infrastructure Levy Regulations 2010. In addition, any contribution requested prior to the 27 March 2012 had to be in accordance with Circular 05/2005 Planning Obligations.
3.2This can be done through entering into a Section 106 agreement or the acceptance of a Unilateral Undertaking both of which identify the amount of contribution and when the contributions need to be paid, i.e. on the commencement of development or first occupation.
3.3The latter option has no claw-back period. However, the money must be used for the purposes identified otherwise the developer may be entitled to claw the money back. Section 106 agreements have a claw-back period normally of 5 years, on the basis that if the infrastructure improvements are not in place by then, there is no need for the facility.
3.4The contributions are closely monitored through a database set-up on a parish basis and are available to the parish councils on request as well as being circulated to all on a quarterly basis. This enables parish councils to clearly see what funds may come forward to help them plan for improvements in their area. Open invitations have been sent to all parish council clerks with regard to receiving a presentation on understanding the full s.106 process.
3.5Notwithstanding the current measures, a report will be produced for the Strategic and Community Planning Officer to discuss with the Parish Council’s at the bi-annual Parish Forum. The report will further highlight the s.106 contributions available to the Parish Council’s and give further opportunity for discussions to be held.
3.6Whilst the database is complex, owing to the amount of information held, it helps to identify what money the development may bring in, when development has commenced, and monies outstanding. It also indicates where money has been committed through the Green Space Strategy. 3.7 The Section 106 Forum was set up 5 years ago and also monitors the database.
3.8The database shows two s.106 agreements where the 5 year claw-back period has expired. These agreements are for development at 44 Westfield Road, Hinckley and Montgomery Road, Earl Shilton and total £17,980.00 and £150,000.00 respectively.
44 Westfield Road, Hinckley
3.9The off-site open space contribution comprises £7,930.80 in respect of the provision and/or improvement of open space in lieu of the provision of open space within the Development and £9,169.20 in respect of maintenance of such open space.
3.10Payment was received 20.12.2007 and a written request to return any sums not utilised in accordance with the s.106 agreement was received from the Developer on 24.01.2013.
3.11Investigations are ongoing in an attempt to satisfactorily resolve the situation.
Montgomery Road, Earl Shilton
3.12The community facilities contribution comprised £80,000.00 towards either the provision of leisure facilities or of a NEAP in the locality of the Development and £70,000.00 towards the maintenance of such provision. Payment was received 22.01.2008 and a written request has been received from the Developer (David Wilson Homes) for the refund of any unexpended sums.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Section 106 Developer ContributionsReport | 4 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.