Housing Repairs Update

Decided Finance 1 paper

Finance, Audit & Performance Committee decided this item on Monday 11 November 2013. Below is the council's own wording, with the papers it was decided on.

Item252

Resolved

RESOLVED – ( i ) the void standard be sent to members; (ii) ... view the full minutes text for item 252.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Finance, Audit & Performance Committee, 5 pages

Purpose of report

To provide members with an update on the progress made against the Action Plan produced in response to the review of the Housing Repairs Service.

Recommendation

That members:

• Note and endorse the progress made to date.

3. BACKGROUND TO THE REPORT

3.1In response to two independent reviews and a further internal financial review, an Action Plan was developed to address the issues identified within the Housing Repairs Service. Delivery against this Plan continues to be closely monitored.

3.2This Plan was reported to members at the previous meeting and it was agreed that updates and significant variations to the plan would be reported back. This report will therefore set out some of the key areas of progress made to date. Progress against the plan will also be assessed as part of the next Internal Audit Review of Housing Repairs, along with testing of the improved controls and procedures.

3.3There were 15 tasks within the Action Plan and all but four have been fully implemented. Updates against each action are provided below.

Key Task Comments

Clear historical backlog of There had been an issue identified where jobs were not jobs through the Orchard been completed in a prompt fashion with in the System and System. this was causing delays in the finance system also being updated. This has now been completed and the backlog has been cleared. Additional procedures were introduced to ensure this is now carried out regularly. This has resulted in more meaningful reporting of work in progress within the system

Complete Review structure and The budgets were fully reviewed and revised accordingly. allocation of budgets. This included a cleansing exercise for some erroneous codes and also new budget lines have been created to enable more detailed financial reporting.

A new methodology for budget monitoring was also developed between the service and the Finance Team which Key Task Comments

will include a more accurate forecast position. Specific targets have also being set, such as target cost per void property. Any variations from these are challenged accordingly.

Complete Work in Progress (WIP) This is now done routinely as part of the performance within the Orchard System management and budget monitoring process. is to be analysed and monitored. Complete

Map existing processes for These have been done for existing and new processes. responsive repairs. Complete Update Service Procedures Day to day procedures have been reviewed, updated and and Controls. implemented. These procedures require prompt delivery and closure of jobs on the system based upon new procedures adopted by the engineers. The review has also identified additional policies that were required, such as Acceptable Vehicle Usage and operational requirements regarding engineers availability.

Complete (however also under constant review). Review use of Schedule of A review of the existing rates is being procured and due to Rates and Job Cost Data. be completed by end November. Changes were made to how job cost data was captured to ensure more efficient use of resources.

Ongoing System Training. Training has been delivered on required systems / modules and this will remain under review as further systems and modules are implemented.

Complete Develop Procurement Plan. This has been produced and delivery against it will be monitored alongside delivery of the overall Housing Investment Plan.

Complete Review Invoicing There had been a delay of approximately 2 months for Procedures. invoices from materials suppliers which was having a negative impact on the accuracy of budget monitoring. This has now been resolved and invoices are now received on a timely basis weekly.

Complete Key Task Comments

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Repairs UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Housing Repairs UpdateThis decision
  2. Housing repairs policiesDecided
  3. Council Housing Repairs Decent Homes and Responsive Repairs Performance UpdateNoted
  4. Housing Repairs Internal AuditNoted
  5. Finance, Audit & Performance Update - Housing RepairsNoted
  6. Customer Complaints - Housing RepairsNoted

More from Hinckley and Bosworth Finance, Audit & Performance Committee

All decisions
MeetingDecisionOutcome
21 Mar 2016 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 8 February 2016 be confirmed and signed by the Chairman. Councillor Wal... Decided Open
8 Feb 2016 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 7 December 2015 be approved. Approved Open
8 Feb 2016 External Audit Grants Certification Report 2014/15RESOLVED – the report be noted. Noted Open
8 Feb 2016 Internal Audit Progress ReportRESOLVED – the report be noted. Noted Open
8 Feb 2016 Business Rates and Pooling UpdateRESOLVED – the report be noted. Noted Open