Planning Committee, Tuesday 10 December 2013 at 6.30pm

MIRA Enterprise Zone - delegated arrangements

Decided Planning 1 paper

Planning Committee decided this item on Tuesday 10 December 2013. Below is the council's own wording, with the papers it was decided on.

Item315

Resolved

RESOLVED – determination of all planning applications within the defined enterprise zone in line with the current scheme of delegation be authorised. Councillor Taylor left the meeting at 9.12pm.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Planning Committee, 3 pages

Purpose of report

To obtain Members’ approval for the determination of all planning applications within the defined enterprise zone to be delegated to officers

Recommendation

To delegate the determination of all planning applications within the defined enterprise zone (as shown on the attached Plan 1) in accordance with the current scheme of delegation.

3. BACKGROUND TO THE REPORT

Members will be aware of the outline planning permission reference 11/0360/OUT granted in 2012 for the MIRA Technology Park. At the meeting of the Planning Committee on 15 October delegated authority was given to officers to determine all subsequent reserved matters applications associated with 11/00360/OUT.

The defined boundary of the enterprise zone (EZ) is larger than the area to which the Technology Park masterplan refers.

Under current arrangements there is no delegated arrangement for the determination of applications where they are major applications. The Constitution requires all such applications to be determined by Planning Committee.

A key objective of EZs is to encourage development and economic growth and to provide where necessary a simplified planning regime (SPR) to ensure that once investors are lined up to deliver development, the ‘normal’ planning system does not pose delays to the delivery of development. To achieve this end, where EZs are designated, DCLG are keen to encourage and support the necessary LPAs to develop their SPR.

The Council’s constitution does however pose a significant delay and amount of uncertainty to the delivery of development, but only through the need for applications to be timetabled and determined by Planning Committee.

The MIRA Enterprise Zone and business as a whole is growing and MIRA needs to remain very agile and responsive to demand for space on the site. The forecast investment of circa £300m and 2000 direct and up to 5,000 including indirect jobs being created on site further supports the demand for space and timely delivery of such space. MIRA are also in the process of securing further Government funding for new buildings and infrastructure (as supported by the Borough Council and the LLEP) which require detailed planning permissions to be in place to stand any chance of securing the available funds.

It is therefore proposed to seek delegated authority to determine all planning applications associated within the enterprise zone. It is hoped that this will allow for decisions to be issued in a timelier manner. The overall timescale for decision making will be controlled by either a Planning Performance Agreement or an extension of time agreement where necessary.

It is still proposed that the Enterprise Zone is to be subject to a Local Development Order (LDO) which will in turn provide an accompanying SPR. The LDO is currently under development and will be reported to Planning Committee in due course.

The extent of consultation will remain unchanged, and the current delegation exemptions as specified in the consultation will still apply.

4. FINANCIAL IMPLICATIONS [KP]

The internal costs associated with considering and processing planning applications for the Enterprise Zone will be reviewed to consider whether they can be reclaimed through the Council’s Regional Growth Funding allocation of £19.4million. Costs will be calculated on the basis of the hourly rate of those officers involved. Depending on the level claimed, this will release a saving in the General Fund budget for the amount reimbursed.

5 LEGAL IMPLICATIONS [MR]

Section 101 of the Local Government Act 1972 empowers the Planning Committee to delegate to officers the power to determine planning applications.

6. CORPORATE PLAN IMPLICATIONS

This document contributes to Strategic Aim 1 of the Corporate Plan

• Creating a vibrant place to work and live.

Consultation

None

Risk implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MIRA Enterprise Zone: delegated arrangementsReport 3 pages DownloadRead as text

At this meeting

Whole meeting

More from Hinckley and Bosworth Planning Committee

All decisions
MeetingDecisionOutcome
17 Nov 2026 24/00610/OUT - Cadent, Brick Kiln Street, HinckleyRESOLVED – the application be deferred. Deferred Open
20 Oct 2026 26/00096/FUL - Clares Barn Farm, 26 Sheepy Road, TwycrossRESOLVED - Planning permission be granted, with the Assistant Director Planning and Regeneration given powers to dete... Decided Open
20 Oct 2026 25/01157/OUT - Land east of the Industrial Estate, Hill Lane, MarkfieldRESOLVED - Permission be granted, subject to: (i) The planning conditions detailed at the end of the report; (ii) The... Agreed Open
20 Oct 2026 25/01192/FUL - EMEB Sports and Social Club, Nutts Lane, HinckleyRESOLVED – Planning permission be granted subject to: (i) The conditions set out in section 11; (ii) The completion o... Agreed Open
20 Oct 2026 25/01231/FUL - Land off Church Road, WitherleyRESOLVED – the application be deferred. At this stage, Councillor C Gibbens exited the meeting having declared a regi... Deferred Open