Resolved
RESOLVED – the report be noted.
Scrutiny Commission noted this item on Thursday 16 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the report be noted.
1.1To update and inform members of the Scrutiny Commission of the position in respect of the monies towards play and open space that have been received and spent over the last 10 years via planning condition and Section 106 Agreement or Unilateral Undertaking.
2.1The report is noted.
3. BACKGROUND TO THE REPORT
3.1Developers / applicants can be requested to make financial contributions to make a planning application acceptable, where it would otherwise be refused, towards infrastructure needed as a consequence of their development, e.g. towards play and open space, libraries, education facilities etc. The contribution request has to meet the three statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010. In addition, any contribution requested prior to the 27 March 2010 had to meet the tests in Circular 05/2005: Planning Obligations.
3.2This can be done through entering into an agreement or the acceptance of a Unilateral Undertaking pursuant to Section 106 of the Town and Country Planning Act 1990 both of which identify the amount of contribution and when the contributions need to be paid, e.g. on the commencement of development or first occupation. Historically, monies were also secured through the imposition of a planning condition. This has secured over £0.5m in S106 receipts as detailed below. However, legal advice regarding the imposition of the condition considered that its imposition may be challengeable. There are some instances where developments have been commenced and monies requested by planning condition have not been recovered. This has been only a small proportion against the level of funding secured by this method (see below).
3.3Over the last 10 years (since December 2003) the Local Authority has received £552,150.75 towards play and open space across the Borough through the imposition of a planning condition; of these monies a total of £345,274.75 has been spent on play and open space by the parish councils and the Borough Council. This should be read in the context of the amount that the Local Authority has not been able to recover due to the developers challenging the use of the condition, this totals £18,642.00.
3.4The total amount secured towards play and open space by way of Section 106 agreement or Unilateral Undertaken is significantly higher, with the amount received over the last 10 years totalling £4,219,039.91 across the Borough; of these monies a total of £2,137,601.47 has been spent on play and open space by the Parishes and the Borough Council, the remaining money is held by the Borough Council for expenditure by either the Parish or Town Councils or the Green Spaces Team of the Borough Council. 3.5 The use of either a Unilateral Undertaking or planning condition has no claw-back period. Section 106 agreements have a claw-back period normally of 5 years, on the basis that if the infrastructure improvements are not in place by then, there is no need for the facility. The period for claw-back is currently under review.
3.6The contributions are monitored through a database set up on a parish basis and are available to the parish councils on request as well as being available on-line and being circulated to all parishes on a quarterly basis. This enables parish councils to clearly see what funds may come forward to help them plan for improvements in their area.
3.7The database is complex, owing to the amount of information held. Over recent months the Planning and Finance Services have been working together to ensure the records align. This process has highlighted a few anomalies which are currently being investigated. Work is also underway to bring the Finance and Planning database together into one database.
3.8The database shows 3 payments that are nearing the 5 year claw-back, these are as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Contributions towards Play and Open SpaceReport | 3 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.