Resolved
RESOLVED – the report be noted.
Planning Committee noted this item on Tuesday 4 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the report be noted.
To inform Members of appeals lodged and determined since the last report.
That the report be noted.
3. BACKGROUND TO THE REPORT
Appeals Lodged
3.1Appeal by Alexander Bruce Estates Ltd. against refusal for the erection of 49 dwellings, landscaped public open space and creation of a formal wetland habitat with access at land off Spinney Drive and south of Brookside, Barlestone.
Amended Format: Public Inquiry – (3 days) dates to be confirmed.
Appeals Determined
3.2Appeal by Bellway Homes against the refusal to grant planning permission for the demolition of an existing residential dwelling and erection of 35 residential units, associated highway and engineering operations on land off Workhouse Lane, Burbage.
The application was refused by Members following an officer recommendation to approve on the grounds that the applicant had failed to demonstrate that there is a housing need in Burbage that justifies the development of this Greenfield site that does not reflect the spatial vision for the Borough and that the proposed scheme by virtue of its location to the south of Burbage is an unsustainable location outside the settlement boundary of Burbage within the countryside contrary to Policy 4 of the adopted Core Strategy.
The Inspector considered the main issues of the appeal to be the effect that the development would have on landscape character and on the setting of Burbage and whether the adverse impacts of allowing the proposal significantly and demonstrably outweigh the benefits, when assessed against the policies of the NPPF as a whole.
In the view of the Inspector the protection and preservation accorded to the landscape to the east of Burbage under Policy 4 of the Core Strategy does not apply to the appeal site which abuts the southern edge of the village. The site is not protected by any special landscape designation but forms part of the open (undeveloped) area of land extending to the M69. The built up edge of Burbage has recently been extended southwards by residential development off Britannia Road. The development would no more extend towards the M69 than the schemes already granted planning permission and the remaining length of Workhouse Lane would retain its rural character. While the development would lead to a loss of open land its impact on the wider landscaper would be limited due to the site’s containment on three sides and the relationship of Burbage and the countryside beyond would be largely maintained by virtue of the remaining area between the motorway and the developments.
In balancing any landscape harm against the potential benefits of the scheme the Inspector considered that the principle advantage is the contribution towards addressing the under-delivery in the Borough’s housing supply and meeting numbers in Policy 4 of the Core Strategy, particularly as the lack of brownfield sites means that recourse to greenfield sites is inevitable.
The Inspector considered that the site is easily accessible to a range of local services and facilities by means other than private vehicles and that the layout, scale and design generally were acceptable and concerns regarding poor relationship to existing dwellings are unfounded.
The mix of size and tenure, including 7 affordable houses for which there is a demand, would diversify the housing stock in the village. The proposal would trigger the new Homes Bonus payment to the Borough and County Councils. The development would contribute to the economic and social dimensions of sustainability and whilst some harm to the areas landscape character and to Burbage’s setting would occur, the scale of environmental harm would not be so extensive as to override the clear planning benefits. The NPPF presumption in favour of sustainable development applies.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appeals lodged and determinedReport | 4 pages | DownloadRead as text |
Follow Planning Committee at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | 24/00610/OUT - Cadent, Brick Kiln Street, HinckleyRESOLVED – the application be deferred. | Deferred | Open |
| 20 Oct 2026 | 26/00096/FUL - Clares Barn Farm, 26 Sheepy Road, TwycrossRESOLVED - Planning permission be granted, with the Assistant Director Planning and Regeneration given powers to dete... | Decided | Open |
| 20 Oct 2026 | 25/01157/OUT - Land east of the Industrial Estate, Hill Lane, MarkfieldRESOLVED - Permission be granted, subject to: (i) The planning conditions detailed at the end of the report; (ii) The... | Agreed | Open |
| 20 Oct 2026 | 25/01192/FUL - EMEB Sports and Social Club, Nutts Lane, HinckleyRESOLVED – Planning permission be granted subject to: (i) The conditions set out in section 11; (ii) The completion o... | Agreed | Open |
| 20 Oct 2026 | 25/01231/FUL - Land off Church Road, WitherleyRESOLVED – the application be deferred. At this stage, Councillor C Gibbens exited the meeting having declared a regi... | Deferred | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.