Resolved
RESOLVED – the schemes programmed for 2014/15 be endorsed.
Scrutiny Commission decided this item on Thursday 3 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the schemes programmed for 2014/15 be endorsed.
1.1This report outlines the Environmental Improvement Programme for 2014/15.
2.1That Scrutiny agrees the enhancement schemes (Appendix 1) to be implemented in the financial year 2014/15 as the Environmental Improvement Programme.
3. BACKGROUND TO THE REPORT
3.1ENVIRONMENTAL IMPROVEMENT PROGRAMME 20013/14
3.1For 2014/15 Council agreed in February capital expenditure of £50,000 of which £15,000 was funded from contributions. If the Borough Council's applications for grant aid are successful and landowners agree to make financial contributions towards projects, as anticipated, it will be possible to finance the 20 schemes identified in Appendix 1 which will result in projects costing £59,647 being implemented at a net cost to this Authority of £34,704.
3.2This year’s programme aims to continue the practice to implement schemes identified in the Authority’s Conservation Area Management Plan Reviews and provide a good distribution of projects throughout the borough, both in the urban and rural areas. All of the conservation areas have now been reviewed and plaques have been displayed throughout the conservation areas.
Appendix 2 outlines the progress made on the projects included in the 2013/14 programme.
GUIDELINES FOR PRIORITISING SCHEMES
3.4The agreed guidelines approved by members for prioritising schemes are set out below:
(a) Implement schemes identified in the Authority’s Conservation Area Management Plan Reviews,
(b) Schemes that generate significant amounts of external funding, or be supported by partnerships involving private sector funding,
(c) Complete or complement schemes undertaken in previous years' programmes
(d) Contribute to the Strategic objectives of the Local Authority to provide an attractive environment. (e) Be implemented on publicly-owned or private accessible land
(f) Be in areas which have not yet benefited significantly in previous years' programmes
(g) Voluntary organisations are given priority for undertaking appropriate projects providing the work meets the selection guidelines outlined in sub paragraphs (a) to (f).
4. FINANCIAL IMPLICATIONS (SJE)
4.1The council approved a net budget of £35,000 for 2014/2015 (Expenditure of £50,000 of which £15,000 is to be externally funded). However, the attached appendix 1 outlines the cost of the implementation of the schemes at £59,647 and £24,944 to be externally funded. The net cost to HBBC is £34,704 which is within the approved budget of £35,000. The additional £9,944 expenditure budget and £9,944 income budget will need to be approved in accordance with the council financial procedure rules.
5. LEGAL IMPLICATIONS (MR)
5.1The Council has power under the Local Government Act 2000 to promote or improve the environmental well being of its area.
6. CORPORATE PLAN IMPLICATIONS
6.1This report contributes to the following Strategic Aims of the Council
Strategic Aim - Creating a vibrant place to work and live
Strategic Aim – Empowering communities
7.1Consultations will take place on each project on an individual officer basis with parish councils and other interested parties.
8.1Management of significant (Net Red) Risks Risk Description Mitigating actions Owner None identified
9. KNOWING YOUR COMMUNITY – EQUALITY AND RURAL IMPLICATIONS
9.1Projects put forward in the Environmental Improvement Programme are generally spread over the whole of the Borough and includes the rural area.
10. CORPORATE IMPLICATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EIP 2014-15 Appendix 1Appendix | 2 pages | Download |
PDF |
EIP Appendix 2 Progress Report 2013-14Appendix | 4 pages | Download |
PDF |
Environmental Improvement ProgrammeReport | 3 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.