Resolved
It was agreed that a progress report be brought to the Scrutiny Commission in twelve months.
Scrutiny Commission agreed this item on Thursday 12 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that a progress report be brought to the Scrutiny Commission in twelve months.
1.1The purpose of this report is to update members of progress to date in regard to the council’s Channel Shift project.
2.1That members of the committee note the work achieved to date.
3. BACKGROUND TO THE REPORT
Channel Strategy
3.1The Channel Strategy was approved by the Strategic Leadership and Corporate Operation Board in February 2014 and is attached at Appendix A. The strategy sets out the Council's plans in regard to what channels it will use to deliver its services and how it will interact with its customers in the future.
3.2The strategy sets out how current Council services will be redesigned around four key principles, this being:
Avoidable contact – to ensure right first time Digital inclusion –targeting hard to reach groups and those likely to have the greatest needs for our services Accessibility of contact – enhancing service provision so that customers facing barriers can access services via electronic means i.e. if facing difficulty over the phone, preferred method is via email Channel shift – to provide the public with greater access to services 24/7 by utilising modern technology i.e. the internet as opposed to face to face and over the telephone
Channel shift, known as digital by default, sets out how the council encourages customers to move towards accessing services online, as their first channel of choice, and is the main focus for this report. In terms of the broader channel strategy it is acknowledged that an online service is not a panacea for all of the council’s customers as some customers will need support either face to face or over the phones, particularly if they are vulnerable. Work carried out in regards to other areas of the strategy, such as digital inclusion which focuses upon vulnerable customers will be reported separately.
Channel Shift Project
3.3A project group was established in February 2014. The remit of the group was to refresh the web strategy and to review the current systems and processes used by the Customer Services Team. A fundamental weakness of the existing customer services platform is that services and systems are built around the CRM system (customer relationship management). Customer advisers follow scripts and input forms that need constant updating. Running alongside this, customers use different web based form forms via the internet which are not integrated with back office systems. This causes duplication of processes and a lack of joined up systems. Furthermore, the current CRM system is outdated, costly and unsupported.
Four main areas were identified in order to deliver a transition to online services.
1) Enabling technology 2) Process and services
4) Assisted customer 3) The Website services
3.4Enabling technology
The group was tasked to implement new technologies to enable channel shift to take place. The current Customer Services infrastructure includes: website, e-forms, CRM, email and telephone. This needs to be replaced, merged and integrated to provide greater visibility for customers. In order for this to be realised, the first step involved is to procure a system that will effectively ‘wrap around’ current back office systems and provide a link to customer services via the website.
A business case was produced and signed off in May 2014. As part of the Business Case an options appraisal was carried out to identify the most cost effective and appropriate technology moving forward. The option preferred by the group was to replace the CRM system with a new web based customer service portal using the concept of ‘MyAccount’ and engage a MyAccount Partner. The table below shows the expected savings of £222,150 based upon a 10% channel shift over a five year period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Channel Shift strategyReport | 4 pages | DownloadRead as text |
PDF |
channel shift appendixAppendix | 15 pages | Download |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.