Resolved
RESOLVED – the appropriation of the land shown on the plan appended to the report in accordance with Section 122 of the Local Government Act 1972 from commercial to planning purposes be approved.
Council approved this item on Tuesday 21 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the appropriation of the land shown on the plan appended to the report in accordance with Section 122 of the Local Government Act 1972 from commercial to planning purposes be approved.
1.1To seek approval to appropriate land under section 122 of the Local Government Act 1972 so that it is held for planning purpose to support the redevelopment of Hinckley town centre and to enable section 237 of the Town and Country Planning Act 1990 to be relied upon. This is being timed to coincide with the handover (upon practical completion) of Block C from the Developer to the Council.
2.1That Council approves the appropriation of the land (shown on plan 1 appended to this report) in accordance with Section 122 of the Local Government Act 1972 from commercial purposes to planning purposes.
3. BACKGROUND TO THE REPORT
3.1Outline planning permission was granted on 18 January 2011 for a mixed-use development comprising retail (A1-A3 uses), leisure (D2 uses) and offices (B1a uses), together with all associated infrastructure and plant, public realm, landscaping and servicing, including the provision of a part undercroft/part surface public car parking area and a new bus station (known as the “Crescent development scheme”).
3.2A compulsory purchase order was made by the Council on 11 May 2011 for the purposes of a mixed use development scheme including a new bus station, retail, leisure and office facilities, car parking and other development with associated public realm enhancement works (“the CPO”). These purposes would include the Crescent regeneration scheme. The CPO was confirmed by the Secretary of State on 2 April 2012.
3.3Land was acquired pursuant to the CPO and the Developer started on site in 2014. Some of the land has been retained by the Council and other parts of the land have been transferred to the developer, Tin Hat Regeneration Partnership. This report concerns the land retained by the Council known as Block C, which is shown on the plan appended to this report.
3.4As would be expected for a redevelopment of this nature, there is a small number of rights and restrictions on the title that are historic in nature and for the benefit of unknown beneficiaries. Whilst the CPO has enabled the Council to acquire freehold and leasehold interests in the land, it does not have the effect of acquiring third party interests in, or easements or rights over, the land which has been acquired. In these circumstances, Section 237 of the Town and Country Planning Act 1990 (“TCPA”) can be relied on, which states at that:
“the erection, construction or carrying out or maintenance of any building or work on land which has been acquired or appropriated by a local authority for planning purposes (whether done by a local authority or by a person deriving title under them) is authorised by virtue of this section if it is done in accordance with planning permission notwithstanding that it involves … an interference with a right or interest to which this section applies”.
3.5Section 237 also provides that the subsequent use of land which has been acquired or appropriated for planning purposes is authorised notwithstanding that it involves an interference with an interest or right or a breach of a restriction as to user of land arising by virtue of contract.
3.6Section 122 of the Local Government Act 1722 (“LGA”) permits a Council to appropriate land for any purpose which it is authorised to acquire land by agreement and which belongs to the Council and is no longer required for the purpose for which it is held immediately before the appropriation.
3.7To engage Section 237, it is therefore necessary to demonstrate that:
3.7.1 the land is no longer needed for its current purposes; 3.7.2 the development is carried out in accordance with a planning permission; 3.7.3 the work is done by the Council or a person deriving title under them; and 3.7.4 the land has been acquired or appropriated by the local authority for planning purposes.
Each of these elements is considered in turn below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appropriation of land at the former Hinckley Bus StationReport | 4 pages | DownloadRead as text |
PDF |
Crescent Block C Landholding appendixAppendix | 1 pages | Download |
Follow Council at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Minutes of the previous meetingRESOLVED – the minutes of the meeting held on 29 September be approved. | Approved | Open |
| 27 Oct 2026 | Review of the council's constitutionRESOLVED – the changes to the constitution be approved. | Approved | Open |
| 27 Oct 2026 | Community Governance Review - Witherley - final recommendationsRESOLVED – (i) The current parish of Witherley and Witherley Parish Council be abolished; (ii) Fenny Drayton parish a... | Decided | Open |
| 29 Sep 2026 | Minutes of the previous meetingsRESOLVED – the minutes of the meetings held on 23 July and 4 August 2026 be confirmed as a correct record. | Decided | Open |
| 29 Sep 2026 | Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.