Resolved
RESOLVED – the budget strategy, as amended, be approved.
Executive approved this item on Wednesday 4 November 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the budget strategy, as amended, be approved.
1.1To approve the Budget Strategy for 2016/2017.
2.1That Executive approve the Budget Strategy for 2016/2017.
3. BACKGROUND TO THE REPORT
3.1This Budget Strategy (the Strategy) is presented within an overall national scene of reduced central government funding and the drive towards greater financial localism. The ongoing impact of austerity measures enacted by Government means that local government budgets have been and will continue to be radically reduced due to cuts in central government funding and local reductions in traditional income streams. For this Council, the key pressures in 2016/2017 can be summarised as follows:
• An expected reduction in funding provided by Government. The level of reduction is however unknown as no provisional Settlement has been provided for the forthcoming year. For the purposes of this strategy an assumption will be made that Revenue Support Grant (RSG) will reduce by 16.4% from the 2014/15 allocation.
• Although additional New Homes Bonus and Business Rates Uplift bridged the funding gap in 2015/16, this is not a reliable and sustainable funding stream. New Homes Bonus is dependent upon additional housing development that is complete, occupied and taxable by October of each year. The Strategy will initially assume 75% of the levels of trajectory predicted by the Planning service at an average Band C. This is a prudent estimate and will provide a contingency against any adverse variance due to slippages in development or delays in occupation. It will also provide towards any changes in the local split between this Borough Council and the other major preceptors. The actual allocation of New Homes Bonus is expected from Government in November 2015.
• Pressure from Government to avoid large levels of council tax increases. It should be noted that this Council has at present the joint 8th lowest Council Tax level nationally and has accepted the freeze grant from government for the last 5 years. This has effectively created a loss of income by 31 March 2016 of £691,009 (or £1,142,693 if a £5 increase had been taken in year 1); thereby exasperating the Council’s financial position. The assumption for this strategy is that the increase for 2016/17 will be limited by government to a 2% increase at average Band D. This, at current 2015/16 base equates to 36,311.59 Band D equivalents. Fluctuations in the level of Business Rates that will be retainable by the Council in light of high levels of appeals and, more locally, negotiations on rates received from the MIRA Enterprise Zone.
• The pressure in 2015/16 arising from the removal of green waste recycling credits (£345,792). In 2015/2016, this pressure was funded from reserves as a one off solution. The pressure will therefore be included in the base budget for 2016/17. • The increase in the Council’s dry waste recycling contract in 2015/2016 (£298,890). In 2015/2016, this pressure was funded from reserves as a one off solution. The pressure will therefore be included in the base budget for 2016/17.
• Fluctuations in fees and charges income including planning fees, car parking and rental income.
3.2When members set the council tax for 2016/2017, the Deputy Chief Executive (Corporate Direction), as the Council’s section 151 officer will have a duty under Part II of the Local Government Act to report on the robustness of the Budget and the adequacy of reserves in providing quality services. This Strategy aims to provide a framework that will provide for this robustness but at the same time allows the flexibility to react to changes and opportunities should they arise.
3.3An abbreviated MTFS covering the period 2014/15 to 2017/18 was approved by Council on 17th March 2015. This MTFS detailed three financial scenarios; a best case, worst case and forecast position. The assumptions that underpinned these three scenarios were as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Strategy 2016-17Report | 10 pages | DownloadRead as text |
Follow Executive at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... | Decided | Open |
| 23 Sep 2026 | Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... | Approved | Open |
| 23 Sep 2026 | Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. | Approved | Open |
| 29 Jul 2026 | Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... | Noted | Open |
| 29 Jul 2026 | Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.