Resolved
RESOLVED – the virement of £30,000 from the minor works to major works budgets be approved.
Executive approved this item on Wednesday 9 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the virement of £30,000 from the minor works to major works budgets be approved.
1.1To seek Member approval to Vire £30,000 from the Private Sector Housing minor works budget to the major works budget.
2.1Executive approves the virement of £30,000 from the minor works to major works budgets.
3. BACKGROUND TO THE REPORT
3.1The private sector housing team identify and work with vulnerable households within the borough to remove category one hazards in their properties. Households can apply for financial assistance to remedy issues with their properties when they do not have the means to pay for the works themselves. Applications can be made for minor works grants (up to £5000) or major works grants (up to £20,000).
3.2There has been an increase in applications for assistance and the building costs for works required have been increasing. Very few properties can now be fully remedied for less that £5,000 which is the current threshold for minor works assistance. All current applications for financial assistance, with only one exception, fall within the criteria for major works assistance.
3.3The major works financial assistance is fully repayable upon disposal of the property with a lifetime condition being applied in each case.
3.4The major works financial assistance has been able to help twelve home owners this year who are on a low household income to carry out essential work to their home in order for it to be safe for them to live in. The type of work includes injection of a damp proof course, thermal insulation, electrical rewiring and re-roofing. This work is typically carried out in the older and cheaper housing stock within the borough for households where there is no or little disposable income available to carry out these repairs.
3.5The programme helps ease the demand for health services by reducing the number of accidents within the home and by reducing the incidents of illnesses caused by poor housing. In addition the programme helps the local economy by using local contractors to carryout the work.
3.6An additional budget of £30,000 is required to enable the works that are due to be completed by the 31 March 2016 to be processed. The current major works budget for 2015/16 is £162,172, the £30,000 virement will increase the available budget to £192,172 for 2015/16.
3.7As at the 26 January 2016 £105,463.28 of major works had been completed and £98,748.72 had been approved as a formal commitment. From the total commitment of £204,212 it is anticipated that there will be slippage. A budget of £192,712 is therefore required. 3.8 In summary the major works programme is lengthy in nature including the production of schedules, drawings, tendering and resolving social and health implications all prior to the formal approval. The process takes months of careful and sometimes delicate preparation. Once approved, arranging respite care or managing decant into alternative accommodation for the occupiers and arranging start dates with contractors, in addition to external factors such as weather and customer wellbeing affect completion times which are beyond the control of the council.
4. FINANCIAL IMPLICATIONS [TF]
4.1Currently the following budgets are available:
Grants Budget for the year Spend to date Budget remaining Major 162,712 74,891 87,820 Minor 80,000 3,057 76,942
4.2The virement will reduce the minor grants budget by £30,000 and increase the majors grants by £30,000.
4.3If endorsed the revised budget for major works will be £192,712. This will mean that the current estimated demand in 2015/16 can be met.
4.4Changes for future year’s budgets will be reflected in the revised capital programme which will be presented to Council in February 2016.
5. LEGAL IMPLICATIONS [JB]
5.1None.
6. CORPORATE PLAN IMPLICATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Private Sector Housing: Virement RequestReport | 3 pages | DownloadRead as text |
Follow Executive at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... | Decided | Open |
| 23 Sep 2026 | Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... | Approved | Open |
| 23 Sep 2026 | Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. | Approved | Open |
| 29 Jul 2026 | Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... | Noted | Open |
| 29 Jul 2026 | Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.