Resolved
RESOLVED – the commencement of the procurement process be approved.
Executive approved this item on Wednesday 29 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the commencement of the procurement process be approved.
1.1To seek Executive’s approval to undertake a formal procurement exercise in relation to the operation of Hinckley Markets.
2.1That Executive approves the commencement of the procurement process as detailed within section 3.4 and following
3. BACKGROUND TO THE REPORT
3.1Following a report presented to Executive 9th March 2016, it was agreed that Officers explore all options for improvement/development of Hinckley’s Market, including undertaking soft market discussions, to understand what the private sector can potentially offer. Subsequent to that meeting, and on the basis of the ‘soft’ discussions (3.3 below), it is considered that the circumstances are appropriate for a formal procurement exercise to be undertaken.
3.2The outcome of the formal procurement process will allow the Authority to make an informed decision as to the future management and operational delivery arrangements. The following key aims will be promoted for achievement:
• Enhance the quantity of traders and stalls • Improve the overall ‘offer’ to the public • Increase the number of specialist markets • Assist in wider economic vitality of the town centre • Improve the financial position for the Authority • Investment into markets infra-structure • Focus on long-term sustainability of the markets • Develop a strong partnership with operator
06/16 3.3 During the last 3 months, Officers, Members and representatives from the Market Development Group have held productive discussions with Private sector representatives and have concluded it would be beneficial for the Authority to formally test the market.
3.4The specification will be developed on the basis that an external company would manage the market operation, including set up, day-to-day operations, staffing arrangements, promotions and income collection and would be responsible for the overall development of the market.
3.5The contract period would be 5 years with annual breakout clauses based on performance.
3.6As with other Council contracts, the principle of the contract will be to find a partner with whom the Local Authority, and its close stakeholders, can work effectively and openly, to enhance the markets.
3.7It is proposed that in accordance with financial and procurement procedures, Officers commence a formal tender process. Indicative timescales are as follows:
July –August 2016 Draft tender specification September 2016 Issue advert November 2016 Tender submission deadline Dec 2016 – Jan 2017 Review submissions Feb 2017 Confirm preferred bidder April 2017 Commencement of contract
3.8The well established Markets Development Group will be fully engaged throughout each stage of the procurement process.
4. EXEMPTIONS IN ACCORDANCE WITH THE ACCESS TO INFORMATION PROCEDURE RULES
4.1Not applicable
5. FINANCIAL IMPLICATIONS [DW]
5.1The full financial implications relating to any proposed contract would need to be considered before the contract is let to minimise any risk to the council and to demonstrate that value for money is being achieved. The award of any contract would be subject to the normal procurement rules and financial standing orders.
5.2An additional report will be needed, therefore, once the contract is awarded. This would set out in detail the potential financial impact. As a guide the direct costs associated with the market based on current year budget is £122,000 and primarily consist of staff wages, NNDR and contract cleaning. The total cost of the service currently, including support costs, is £158,000.
6. LEGAL IMPLICATIONS [AR]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Hinckley Markets ProcurementReport | 4 pages | DownloadRead as text |
Follow Executive at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... | Decided | Open |
| 23 Sep 2026 | Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... | Approved | Open |
| 23 Sep 2026 | Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. | Approved | Open |
| 29 Jul 2026 | Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... | Noted | Open |
| 29 Jul 2026 | Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.