1.1The purpose of this Report is to provide an update to Planning Committee on a number of major schemes in the Borough that are currently being proposed or implemented.
2.1That Planning Committee notes the content of this report.
3. BACKGROUND TO THE REPORT
3.1This report provides an update of progress with regard to the delivery of major development projects. The following sections provide the latest update:
Strategic Planned Housing Sites
Barwell Sustainable Urban Extension (SUE) 3.2 The Barwell SUE is allocated in the adopted Earl Shilton and Barwell Area Action Plan (AAP) for the development of 2,500 new homes and a minimum of 6.2ha of employment land plus open space, a new primary school, shops and leisure facilities. The draft Section 106 document has been broadly agreed subject to several minor outstanding points that is awaiting the developer’s response. Most of these discussions are now complete and once the final details are agreed, detailed designs will be drawn up for the first phases. The final sign off is scheduled for the summer of 2017.
Earl Shilton Sustainable Urban Extension (SUE) 3.3 The Earl Shilton SUE is allocated in the adopted Earl Shilton and Barwell Area Action Plan (AAP) for the development of 1,600 new homes and a minimum of 4.5ha of employment land.
06/16 3.4 The developer consortium is working with their consultant and the Council to commence pre-application discussions. The Council has had the developer’s viability appraisal independently assessed, which will inform the eventual S106 package. The council is waiting for the developer consortium to consider the independent assessment. Officers are in regular contact with the developers to seek to make sure that progress is made at the earliest opportunity.
Land West of Hinckley
3.5The development site covers an area of 44.04 hectares. The site is allocated in the Site Allocations and Development Management Policies DPD for 850 dwellings, including 20% affordable housing, a local shop, a primary school, pedestrian access links across Normandy Way and appropriate provision of play and open space.
3.6An outline planning application for the development of 850 homes including 20% affordable housing, 500m2 of retail units, a primary school, community facilities including sport pitches, parkland, children’s play areas, allotments, sustainable urban drainage systems, a new access from Normandy Way and associated infrastructure. on the site was submitted to the Council on 27 February 2015.
3.7A full application for an element of the allocated site, phases 1 and 2 has been submitted. This application is for 260 dwellings, formal and informal public open space, a new access from Normandy Way and associated infrastructure including a sustainable urban drainage system. Both this and the outline applications were approved by Planning Committee 16th August 2016 subject to conditions and the completion of a Section 106. The final decision on the terms of the S106 agreement has been delegated to a group of six members. Work is at an advanced stage with concluding the Section 106 negotiations and a decision is due to be made in summer 2017.
Other Strategic Planning and Economic Development updates
Town centre regeneration
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Major projects updateReport | 4 pages | DownloadRead as text |
Follow Planning Committee at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | 26/00096/FUL - Clares Barn Farm, 26 Sheepy Road, TwycrossRESOLVED - Planning permission be granted, with the Assistant Director Planning and Regeneration given powers to dete... | Decided | Open |
| 20 Oct 2026 | 25/01157/OUT - Land east of the Industrial Estate, Hill Lane, MarkfieldRESOLVED - Permission be granted, subject to: (i) The planning conditions detailed at the end of the report; (ii) The... | Agreed | Open |
| 20 Oct 2026 | 25/01192/FUL - EMEB Sports and Social Club, Nutts Lane, HinckleyRESOLVED – Planning permission be granted subject to: (i) The conditions set out in section 11; (ii) The completion o... | Agreed | Open |
| 20 Oct 2026 | 25/01231/FUL - Land off Church Road, WitherleyRESOLVED – the application be deferred. At this stage, Councillor C Gibbens exited the meeting having declared a regi... | Deferred | Open |
| 20 Oct 2026 | 26/00700/FUL - Concordia Theatre, Stockwell Head, HinckleyRESOLVED – Planning permission be granted, subject to: (i) The planning conditions detailed at the end of this report... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.