Resolved
RESOLVED – the report be endorsed.
Scrutiny Commission decided this item on Thursday 10 August 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the report be endorsed.
1.1This report outlines the Environmental Improvement Programme for 2017/18.
2.1That Director’s Briefing agrees the enhancement schemes (Appendix 1) to be implemented in the financial year 2017/18 as the Environmental Improvement Programme. Please note due to timing of meetings SLT have endorsed the programme spend so projects can commence.
3. BACKGROUND TO THE REPORT
BOROUGH IMPROVEMENT PROGRAMME 2017/18
3.1If partners agree to make financial contributions towards projects, as anticipated, it will be possible to finance the 12 schemes identified in Appendix 1. The 12 schemes have an overall estimated cost of £56,749, with a gross cost to Hinckley and Bosworth Borough Council of £38,111.50. After taking account of external contributions the net cost to this Authority will be £32,911.50.
3.2This year’s programme aims to continue the practice to implement schemes identified in the Authority’s Conservation Area Management Plan Reviews and provide a good distribution of projects throughout the borough, both in the urban and rural areas.
3.3Only one proposed project has not been supported through Environmental Improvement Programme 2017/18. The project submitted by Market Bosworth Parish Council involved works to a grassed area on Warwick Lane which is out of the conservation area and deemed to be general maintenance. The Parish Council has been informed and understands the decision.
06/16 3.4 Appendix 2 outlines the progress made on the projects included in the 2016/17 programme.
3.5GUIDELINES FOR PRIORITISING SCHEMES
The agreed guidelines approved by members for prioritising schemes are set out below:
(a) Implement schemes identified in the Authority’s Conservation Area Management Plan Reviews, (b) Schemes that generate significant amounts of external funding, or be supported by partnerships involving private sector funding, (c) Complete or complement schemes undertaken in previous years' programmes (d) Contribute to the Strategic objectives of the Local Authority to provide an attractive environment. (e) Be implemented on publicly-owned or private accessible land (f) Be in areas which have not yet benefited significantly in previous years' programmes (g) Voluntary organisations are given priority for undertaking appropriate projects providing the work meets the selection guidelines outlined in sub paragraphs (a) to (f).
4. EXEMPTIONS IN ACCORDANCE WITH THE ACCESS TO INFORMATION PROCEDURE RULES
4.1This report is to be taken in open session.
5. FINANCIAL IMPLICATIONS [TF]
5.1Details of schemes and associated costs and income are attached in Appendix 1. The estimated cost for 2017/18 schemes is £38,111.50. The estimated income is £5,200. The net cost is therefore estimated to be £32,911.50. This compares to an approved expenditure budget of £50,000 and an income budget of £15,000 a net budget of £35,000.
5.2The reduction of anticipated spend of £11,888.50 and contributions received of £9,800 will be monitored throughout the remaining parts of the year and any savings will be reviewed and reported through the budget monitoring process.
6. LEGAL IMPLICATIONS [MR]
6.1The Council has power under the Local Government Act 2000 to promote or improve the environmental well being of its area.
7. CORPORATE PLAN IMPLICATIONS
7.1This report contributes to the following priorities of the Council; Places - Creating clean and attractive places to live and work Prosperity- Encouraging growth, attracting businesses, improving skills and supporting regeneration.
06/16 8. CONSULTATION
8.1Consultations will take place on each project on an individual officer basis with parish councils and other interested parties.
9.1The following significant risks associated with this report / decisions were identified from this assessment:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Environmental Improvement ProgrammeReport | 3 pages | DownloadRead as text |
PDF |
Environmental Improvement app1Report | 1 pages | Download |
PDF |
Environmental Improvement app2Report | 1 pages | Download |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.