Resolved

RESOLVED – the report be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Scrutiny Commission, 7 pages

Purpose of report

1.1To update Scrutiny on the procurement of the council’s fleet following report to Council in July 2017

Recommendation

2.1Scrutiny note the report

3. BACKGROUND TO THE REPORT

3.1The report to Council in July 2017 identified that the replacement of the council’s fleet of vehicles for the streetscene, environmental health and housing repairs services was due in April 2018 with the expiry of the existing Specialist Fleet Services (SFS) lease. In addition the fleet was to increase from the bringing in-house of the dry recycling service, additional refuse rounds from increasing housing numbers and additional trade refuse rounds. It advised that the Council’s financial advisors had suggested reviewing if purchase of the vehicles offered a better financial return due to the council’s low interest rates for capital borrowing. Estimated values were reported to Council to obtain agreement for the allocation of capital.

Council agreed:

(i) Procurement of the vehicle fleet and the associated supplementary budgets as follows, be approved:

(a) A supplementary capital budget of £3,855,500 for fleet and equipment procurement;

06/16 (b) A supplementary capital budget of £82,100 for the procurement of retained vehicles which is to be funded from the grounds machinery reserve;

(c) A supplementary revenue budget of £609,004 for the annual financing cost which will replace the current revenue budget of £396,000;

(d) An increase in the council’s capital financing requirement of £3,855,500 to allow the purchase.

(ii) The decision on purchase and/or lease of fleet and equipment be delegated to the relevant officer in consultation with the Executive Member for Neighbourhood Services

3.2Link Asset Services, our financial advisors, were engaged to carry the evaluation of these options. A thorough review by officers of their requirements and identification of any suitable vehicles to be retained through purchase was carried out. Link then carried out two OJU compliant tenders for the “Heavies” –Refuse Collection Vehicles, HGVs and the “Lights” - vans, box vans and pick ups etc. From the returned tenders it calculated from knowledge of manufacturer prices and discounts the likely purchase prices and costs of maintenance, sundries and fleet supervision.

3.3The procurement costs of the vehicles, and notes on some of the pressures are included in tables below. These tables give the comparison to the budgets as agreed in July 2017. The procurement of the fleet also assumes the services remain in house, along with the bringing in house of the dry recycling service and trade waste, which requires 5 additional refuse collection vehicles. The report in July noted that it did not include the costs of maintenance.

3.3.1 The capital costs associated with the purchase and contract hire options are:

Vehicles Grounds Total Machinery Capital cost £3,826,136 £202,345 £4,028,481 Less residual value -£304,795 -£10,000 -£314,795 Total capital costs £3,521,341 £192,345 £3,713,686 *internal estimate

This is £141,814 (3.68%) below the approved capital budget of £3,855,500 agreed by full July council.

3.3.2 The revenue costs associated with the purchase and contract hire options are:

Total annual Final Position Capital Costs Maintenance cost Contract Hire £ £ £ HGV/Specialist 432,054 231,632 663,686 LCV/Grounds 179,538 46,596 226,134 Total 611,592 278,228 889,820 Purchase £ £ £

06/16 HGV/Specialist 450,423 358,047 808,470 LCV/Grounds 187,613 155,098 342,711 Total 638,036 513,145 1,151,181

Savings to the GF using hire purchase compared -26,443 -234,917 -261,361 to Purchase

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FleetProcurementAppendixAppendix 1 pages Download
PDF
Procurement of Council FleetReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Procurement of Council FleetThis decision
  2. Procurement of HGV fleetApproved
  3. Procurement of fleetApproved

More from Hinckley and Bosworth Scrutiny Commission

All decisions
MeetingDecisionOutcome
22 Oct 2026 Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... Approved Open
22 Oct 2026 Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. Approved Open
22 Oct 2026 Budget planRESOLVED - members noted the Budget Plan for 2027/2028. Noted Open
22 Oct 2026 Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... Noted Open
22 Oct 2026 Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies