CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hinckley and Bosworth Borough Council
Scrutiny Commission, Thursday 8 November 2018 at 6.30pm

Review of the Developing Communities Fund

Decided Scrutiny 2 papers

Scrutiny Commission decided this item on Thursday 8 November 2018. Below is the council's own wording, with the papers it was decided on.

Item242

Resolved

RESOLVED – Council be RECOMMENDED to consider the following: (i) Officer support for project management is required, but the fine line between enabling and project managing be addressed; (ii) Expansion of the Parish & Community Initiative Fund rather than reducing the lower limit of the Developing Communities Fund; (iii) Changes to the challenging timescales; (iv) Creation of a toolkit to support parishes through the application and project management processes.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Scrutiny Commission, 6 pages

Purpose of report

1.1To review the operation of the Developing Communities Fund, the eligibility of projects, the evaluation criteria and process, governance and the allocation of funding to be made available for the future.

Recommendation

2.1That Scrutiny Commission consider the review of the progress of the Developing Communities Fund, suggested modifications for eligibility of projects, the evaluation criteria and process, and the amount of funding to be made available and recommend their approval to Council

3. BACKGROUND TO THE REPORT

3.1The outline of the new Developing Communities Fund was approved by Council on 6 September 2016. This Fund was introduced to:-  support parishes and rural communities wanting to deliver locally important and ambitious schemes,  to build on the success of the Parish and Community Initiative Fund, and  to provide support for larger projects in areas where there is (or is anticipated to be) considerable population and/or employment growth.

3.2The Council wrote to all Parishes on 7 September 2016, inviting expressions of interest (EOI) for funding to be submitted by 9 December 2016. From this 13 projects were submitted and 7 ultimately approved by Scrutiny and Council to received funding.

3.3This decreased to 6 following one not being able to progress due to ownership issues. The remaining 6 have progressed at different speeds to the current position as summarised:

06/16 Project Comment DCF DCF Total Grant Approved Barlestone New Village Completed and now £139,000 £139,000 Hall open Sheepy Church Floor To be completed £57,000 £57,000 replacement Oct 18 Burbage Millennium Hall Site Investigation £350,000 £350,000 extension and changing commenced – build rooms- start Jan 19 Market Bosworth Feasibility study in £26,900 £26,900 Marketplace progress. Phase 2 Redevelopment Phase 1 to be determined Status dependent on feasibility study results. Markfield Community Starting Oct 19, £178,000 £178,000 Park MUGA and completion Dec 19 landscaping– Sport In Desford Starting Oct £234,000 £234,000 multiuse courts 18completion Dec 18 Total £196,000 £788,900 £984,900

3.4The project team reviewed the experiences from the first phase and identified a number of lessons leaned which were then discussed with Executive. These can be summarised as:

 The ability/competence of applicants to deliver large projects was limited  Much higher input by assessors than anticipated was required  High workload on officers with varying experience therefore a reliance on an external consultant  Decision making process with the Projects Board, SLT and Scrutiny extended and delayed project timetables.  Choice of consultants/contractors in some instances was not robust which increased project risks.  VAT implications for applicant- highlighted need to resolve before project application as significant impact on project cost  Early briefing of applicants to ensure good submissions was identified.  Expression Of Interest in Sept 2016 were sought before full criteria developed- only PC/Groups with schemes already developed applied- Fund was therefore allocated to schemes which were already identified rather than where greatest need was identified.-  6 schemes £57k to £350k – Should there be a smaller number of larger schemes?  Legal agreements- required to protect public funds but perceived as bureaucratic by applicants.  Cost estimates were guestimates for some  Degree of council risk in seeking to deliver projects against adverse publicity should schemes not deliver on cost or to timetable  PCIF £12k per parish Max 50% contribution Minimum DCF £30k

3.5When considered by Executive on 26 June 2018 to review criteria it was agreed:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DCF appendix in colourAppendix 1 pages Download
PDF
Review of the Developing Communities FundReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Review of the Developing Communities FundThis decision
  2. Review of the Developing Communities FundApproved

More from Hinckley and Bosworth Scrutiny Commission

All decisions
MeetingDecisionOutcome
22 Oct 2026 Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... Approved Open
22 Oct 2026 Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. Approved Open
22 Oct 2026 Budget planRESOLVED - members noted the Budget Plan for 2027/2028. Noted Open
22 Oct 2026 Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... Noted Open
22 Oct 2026 Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies