RESOLVED – (i) The concerns of members be noted; (ii) The Scrutiny Commission seeks regular reports on performance of assets and looks to consider alternative uses and strategies; (iii) The risk management profile be reviewed regularly; (iv) The use of the Developing Communities Fund as a mechanism to support the development of the crematorium be not supported.
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
1.1To inform members of the potential impact of the decision to retain block C at the Crescent site.
Recommendation
2.1To note impact and potential savings or extra income needed
2.2To consider the potential use of capital receipts and reserves use to off set the impact of the decision to retain Block C.
3. BACKGROUND TO THE REPORT
3.1The Council in 2013 agreed to back an £80m regeneration scheme as part of its vision to redevelop the former bus station site. This included entering into a development agreement with Tin Hat Partnership to secure the completion of the whole scheme, including supermarket, shops, car park, bus station, cinema and family restaurants and public realm improvements. To ensure this development went ahead the Council invested £4.5m in the purchase of Block C, a multiple unit retail site. In addition, the business rate gain in ensuring development of the whole site was considered at the time as generating an additional £377,000 of business rate growth to the Council.
3.2To this end the Council has achieved its primary aim of redevelopment and regeneration of this former rundown area of the town centre. The Crescent is a major shopping and leisure scheme that formed part of a comprehensive regeneration plan to transform the former rundown bus station site. Since its completion in October 2015 it has proved a major success transforming the town centre and introducing a range of family entertainment uses including a new cinema and family-orientated restaurants, new retail units including a major Sainsbury’s superstore, over 500 car-parking spaces
06/16 and a new bus station facility. Further information on the original purchase costs and current rental performance is given in appendix 3.
3.3On the 21 May 2019, the decision to retain Block C was agreed at Council via a Member proposed motion. The key basis and rationale for retaining block C in Council ownership by the current Administration are as follows:
The units in ‘Block C’ currently continue to bring an income in to the Council of over £336,000 per annum, with a net return before interest of £117,691
This will signal the Council’s unequivocal commitment to Hinckley town centre as a key retail and leisure destination for local residents and visitors
3.4It has been widely reported that since 2015 local authorities have spent an estimated £800m on acquiring shopping centres in a bid to safeguard and take control of prime commercial assets to underpin confidence in town centres. Therefore, HBBC is not alone in having such assets. As well as bringing benefits to these areas, there are also ongoing risks for councils associated with such investments. These are included in section 9 below.
3.5This report considers the impact of that decision on the MTFS and the potential mitigating strategy to address that impact.
3.6The affect on the General Fund Balance, before any mitigating actions are taken, over the life of the MTFS is noted in table 1 and accompanying graph below. The cause of the change is due to having to fund the crematorium project from a £4m loan as opposed to the capital receipt from the sale of Block C and the impact of slippage by 4 months on the delivery start time for the crematorium to become operational. As the sale is not happening, this slippage only makes about £20,000-£25,000 difference in 2020/21 post the decision to keep, but £125,000 difference on the previous MTFS agreed in February. Therefore £100,000 of pressure now faced is due to slippage on the operational start date and not the decision to retain Block C.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.