Resolved
RESOLVED – the report be noted and RECOMMENDED to Council. Councillor Sheppard-Bools entered the meeting at 6.45pm.
Scrutiny Commission noted this item on Thursday 20 August 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the report be noted and RECOMMENDED to Council. Councillor Sheppard-Bools entered the meeting at 6.45pm.
1.1This report provides an update on the Ambion Court sheltered Scheme redevelopment.
Council
2.1Notes the progress with the project.
2.2Notes the estimated tender sum of £3,068,200.00 for a 54 week programme and approves a revised budget of £3,769,668.00 for delivery of the scheme.
2.2Notes the ongoing discussions with Homes England regarding their funding allocation.
3. BACKGROUND TO THE REPORT
3.1The Ambion Court redevelopment includes the demolition of the existing sheltered scheme and the development of a 24 unit one bedroomed self- contained apartment development providing a fit for purpose modern sheltered accommodation for the over 60s.
06/16 3.2 Homes England funding for the Ambion Court redevelopment project was secured in March 2019, providing a capital sum of £1.2m phased over the delivery of the project.
3.3Planning approval was awarded in October 2019 for the demolition of the existing sheltered housing scheme and the development of the 24 bed scheme, including communal lounge/dining/library area, kitchen, hair dressing, laundry, offices and storage spaces. Permission was also granted for the development of 3 one bedroom bungalows within the footprint of the previous sheltered scheme. The option to develop out the bungalows will be considered at a later date once the redevelopment project is completed.
3.4Cawarden were appointed as the preferred demolition contractor through the EEM procurement framework through the direct award route. Following consultation with residents surrounding the site, work commenced on site with the removal of asbestos on 16th March 2020.
3.5On Friday 27th March 2020 Cawarden advised that following recent government updates and advice from the Demolition Industry Body the Ambion Court site would be required to close due to the Covid19 pandemic. The site was then closed for a period of 8 weeks before remobilisation could take place on the 11th May 2020.
3.6The demolition contract is now completed with the site being made available to hand over on the 31st July. It should be noted that the Council have received no financial claims from Cawarden during the closure of the site and no complaints from residents during the demolition programme.
3.7It was considered that the appointment of a main contractor to commence work immediately following the demolition of Ambion Court was essential both in order to comply with the requirements of the Homes England funding (March 2021 completion date) whilst also achieving a project programme which delivered the project as quickly as possible minimising any negative impact on local residents.
3.8On this basis, during the demolition period, Officers, supported by Pelham Architects, have been in direct negotiation with Geda (development contractor) who were selected off the Blue Skies Framework to provide a tender for negotiation and if acceptable to enter into contract to procure the new build works
3.9The resulting detailed negotiations with Geda have now reached a point where a cost plan and programme have been provided to officers. Geda have confirmed that they are able to take on responsibility of the site from 31st July 2020 and mobilise a workforce within 4 weeks of reaching a contractual agreement with a contract period of 54 weeks for an estimated construction value of £ 3,068,200.00.
06/16 3.10 The cost plan when compared to an independent cost estimate falls within 6 %, reassuring the Council the project deliver values for money for a development of this type.
3.11An overall cost summary based on expenditure incurred and remaining costs is summarised in the table below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ambion Court redevelopmentReport | 5 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.