Resolved
RESOLVED – (i) The report be noted and officers thanked for their hard work; (ii) A report be brought to the next meeting on the five year land supply and progress on the local plan.
Scrutiny Commission noted this item on Thursday 25 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – (i) The report be noted and officers thanked for their hard work; (ii) A report be brought to the next meeting on the five year land supply and progress on the local plan.
1.1To inform Members of the delivery of affordable housing in the Borough, as requested by the Scrutiny Commission as an annual position update.
2.1For Scrutiny to note the contents of this report.
3. Background to the report
3.1This report is the latest report presented annually in response to a Scrutiny Commission meeting of 20 December 2012, which requested that Members are informed on an annual basis on the delivery of affordable housing in the Borough.
3.2The targets and thresholds for affordable housing in the Borough are set out in Policy 15 of the Core Strategy. These differ for the urban and rural settlements and are as follows:
Location Site size threshold Target Urban (Hinckley, Barwell, 15 dwellings or more, or 20% affordable Burbage and Earl Shilton sites of 0.5 ha or more housing but not the SUEs) Sustainable Urban 15 dwellings or more, or 20% affordable Extensions – Barwell and sites of 0.5 ha or more housing Earl Shilton Rural areas (all sites not in 4 dwellings or more, or 40% affordable the above categories) sites of 0.13 ha or more. housing
06/16 3.3 However, local policy has been superseded by national policy, and as set out in the 2019 revised version of the National Planning Policy Framework (NPPF), the provisions are as follows;
Provision of affordable housing should only be sought for residential developments that are major developments which are defined in the NPPF as developments where 10 or more homes will be provided, or the site has an area of 0.5 hectares or more In designated rural areas LPAs may instead choose to set their own lower threshold in plans and seek affordable housing contributions from developments above that threshold
3.4The Core Strategy also sets out the minimum numbers of affordable housing to be delivered in the Core Strategy period 2006 – 2026. This sets out a target of 2,090 affordable dwellings to be delivered over the policy period, 480 of which should be in rural areas.
4. AFFORDABLE HOUSING COMPLETIONS AND PERMISSIONS TO 31 MARCH 2020
4.1The total number of affordable housing completions and the percentage of affordable housing delivered since the start of the Local Plan period (2006 – 2026) is shown in the table below. This table has been updated from the Residential Land Availability monitoring statement for 2019/20, and makes a minor correction to the number of affordable homes completed in 2015 – 16 to 97 units. Percentage of Affordable affordable Completions housing (net) Total Total Open delivery by Affordable Market Total Percentage of location (%) Housing Housing Housing housing Completions Completions Completions delivery that is Rural Urban Year Rural Urban (net) (net) (net) affordable (%) 3.42 14.84 2006/07 15 65 80 358 438 18.26 0.75 10.31 2007/08 3 41 44 354 398 11.06 1.9 16.88 2008/09 9 80 89 385 474 18.78 0 30.31 2009/10 0 107 107 246 353 30.31 0 2.2 2010/11 0 5 5 222 227 2.20 0 35.92 2011/12 0 134 134 239 373 35.92 2.66 4.88 2012/13 6 11 17 208 225 7.55 12.5 8.96 2013/14 60 43 103 377 480 21.46 12.36 8.12 2014/15 93 61 154 598 752 20.48 4.53 11.76 2015/16 27 70 97 498 595 16.30 10.36 14.41 2016/17 59 82 141 428 569 24.78 4.96 19.15 2017/18 21 81 102 321 423 24.11 12.71 8.62 2018/19 59 40 99 365 464 21.33 18.6 22.1 2019/20 53 63 116 169 285 40.7 1288 6.69 14.58 Totals: 405 883 4768 6056 21.26
06/16 4.2 This table shows that since the beginning of the plan period (2006) a total of 1,288 affordable dwellings have been completed against the 2,090 affordable dwelling requirement set out in the Core Strategy Policy 15.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Affordable housing deliveryReport | 7 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.