Resolved
RESOLVED – (i) The report be noted; (ii) The supplementary budget of £50,000 be approved to enable adaptation works to continue to be carried out through to 31 March 2023.
Executive noted this item on Wednesday 1 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – (i) The report be noted; (ii) The supplementary budget of £50,000 be approved to enable adaptation works to continue to be carried out through to 31 March 2023.
1.1To inform the Executive of the current financial position, impacting on the ability of Housing Repairs Service to carry out Social Service Adaptations in council-owned properties
2.1That the Executive notes the report
2.2That the Executive approves a supplementary budget of £50,000, to enable adaptation works to continue to be carried out, through to the 31st March 2023.
3. Background to the report
3.1The volume of social service recommendations received by Housing Repairs during 2022/23 has exceeded the level of budget ring-fenced to carry out adaptation works. The volume of recommendations received during financial years 2020/21 & 2021/22 was significantly lower than anticipated due to Covid restrictions imposed by Occupational Health. Face-to-face assessments were not carried out during this time. A £100,000.00 underspend from 2021/22 was carried forward to 2022/23 in anticipation of an increase in recommendations being received due to an expected backlog of referrals
06/16 3.2 In anticipation of an increase in the volume of works needing to be carried out, 2 external contractors were procured by Housing Repairs to effectively double output
3.3The baseline budget of £455,393.00 including the £100,000.00 carry forward from 2021/22 will be fully spent by the 31st January 2023.
3.4Virements totalling £50,000.00 and a supplementary budget of £25,000.00 agreed by the Chief Executive & Section 151 Officer, will also be spent by the 31st January 2023
3.5It is anticipated that adaptation works will have to cease from the end of January 2023, until 2023/24 budgets become available in April despite Housing Repairs being in receipt of Social Service adaptation requests with an estimated value of £320,000.00 as of the 30th November 2022. Further recommendations will continue to be received for the remainder of the financial year.
3.6An increased budget for 2023/24 has been requested to take into account the current backlog of adaptation works
4. Exemptions in accordance with the Access to Information procedure rules
4.1open Session
5. Financial implications [AW]
5.1The supplementary will lead to £50,000 additional expenditure for adaptations that will fall on the revenue account. Without the increase in budget, adaptations will be delayed for individuals in need.
6. Legal implications [MR]
6.1None
7. Corporate Plan implications
7.1The proposals align with the following corporate objective Place- Improve the quality of existing homes, enable the delivery of affordable housing.
7.2Ensuring residents are able to remain living independently in their homes.
8.1None
06/16 9. Risk implications
9.1Management of significant (Net Red) risks Risk description Mitigating actions Owner Adaptation works are not carried out A further G Upton st st between 31 January & 1 April 2023 supplementary budget will enable adaption Potential for tenants to not be able to works to continue to be remain in their homes living carried out until 1st independently April 2023
Backlog of work will grow increasing Backlog of works does the pressure on the 2023/24 budget not increase further
Increase in complaints due to works Continuity of workload not being carried out within set for contractors timescales maintained
10. Knowing your community – equality and rural implications
10.1The proposal outlined will enable the service to continue delivering services effectively across the borough
11.1The Housing Service is committed to delivering it services in line with climate change objectives
12. Corporate implications
12.1By submitting this report, the report author has taken the following into account:
- Community safety implications - Environmental implications - ICT implications - Asset management implications - Procurement implications - Human resources implications - Planning implications - Data protection implications - Voluntary sector
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Additional supplementary budget request for social service adaptation worksSupplementary | 3 pages | DownloadRead as text |
Follow Executive at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... | Decided | Open |
| 23 Sep 2026 | Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... | Approved | Open |
| 23 Sep 2026 | Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. | Approved | Open |
| 29 Jul 2026 | Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... | Noted | Open |
| 29 Jul 2026 | Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.