RESOLVED – (i) Permission be granted subject to: a. The completion within six months of this resolution of a S106 agreement to secure the following obligations: · Safeguarding of land for highways purposes · Footpath connections contribution b. The conditions contained in the officer’s report and late items. (ii) The Head of Planning be granted delegated powers to determine the final detail of planning conditions; (iii) The Head of Planning be granted delegated powers to determine the final terms of the S106 agreement including trigger points and clawback periods.
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
Site: Land South Of The A5 Padge Hall Farm Hinckley
Proposal: Hybrid planning application comprising: Outline application (all matters reserved except for site access from the A5) for the demolition of existing structures and the erection of distribution and industrial buildings (Use Class B2 and B8) including ancillary offices and associated earthworks, infrastructure and landscaping; a Full application for the development of a distribution building (Use Class B8), including ancillary offices with associated access, hard standing, parking, earthworks and landscaping. The proposals include improvements to increase the height clearance of the existing railway bridge on the A5 Watling Street. A cross boundary application with Rugby Borough Council and Nuneaton and Bedworth Borough Council (EIA development)
1. Recommendations 1.1. Grant planning permission subject to: The completion within 6 months of this resolution of a S106 agreement to secure the following obligations: Safeguarding of land for highways purposes Footpath connections contribution Planning conditions outlined at the end of this report. 1.2. That the Head of Planning be given powers to determine the final detail of planning conditions.
1.3That the Head of Planning be given delegated powers to determine the final terms of the S106 agreement including trigger points and claw back periods on the basis of the Committee`s resolution. 2. Planning application description 2.1. This application seeks outline planning permission for one part and full planning permission for another part of the same site. This is a cross boundary application with Rugby Borough Council (RBC) and Nuneaton and Bedworth Borough Council (NBBC).
2.2RBC and NBBC have resolved to determine their elements of the application at the with both Local Planning Authorities approving the application subject to conditions and completion of a S106 agreement. Although HBBC cannot grant or refuse planning permission for the parts of the scheme in RBC and NBBC, they are a significant material consideration within the determination of this application.
2.3The plan below identifies the appropriate Borough boundaries for each Local Authority adjoining the application site. It is important to note that the Local Plan policies only apply to the area of the site within Hinckley & Bosworth Borough Council’s administrative area; however, the whole planning application is a material planning consideration.
Outline Planning Permission 2.4. The outline permission sought is for the demolition of existing structures and the erection of distribution and industrial buildings falling within Use Classes B2 and B8 including ancillary offices and associated earthworks, infrastructure and landscaping. The main considerations in this application are the principle of development and access to be taken from the A5. Layout, landscaping, scale and appearance are all reserved matters to be considered in detail at a later stage. Parameters of the outline area to be considered are: Finished floor level to 91.00m AOD +/- 300mm Maximum height of buildings (from FFL to highest ridge point) – 18 metres Up to 136,350 square metres of floorspace (including unit 1 – detailed)
Full Planning Permission 2.5. Full planning permission is being sought for the development of a distribution building within Use Class B8, including ancillary offices with associated access, hard standing, parking, earthworks and landscaping. The proposals also include improvements to increase the height clearance of the existing railway bridge on the A5 Watling Street by lowering the road under the bridge.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.