Council house repairs backlog and pay challenges

Approved Committee 1 paper

Council approved this item on Tuesday 18 July 2023. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

RESOLVED – (i) The application of market supplements to repairs operative salaries and the recruitment of two additional temporary operatives be approved; (ii) A supplementary budget of £149,999 in year one and £75,947 thereafter, funded through the housing revenue account, be approved. Councillors Boothby, Smith and Stead-Davis returned to the meeting.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Council, 8 pages

Purpose of report

1.1To update Council on the position in relation to the responsive repairs backlog.

1.2To highlight continuing challenges in respect to the retention and recruitment of housing repair trade personnel due to below market pay levels.

1.3To advise Council of the additional salary requirements needed to match market levels and propose action to respond to the pressure on service delivery and associated service risks due to these resourcing difficulties.

Recommendation

Council:

2.1Notes the report and pressures faced within the repairs service,

2.2Approves the proposed action detailed in section 4 of the report – the application of market supplements to repair operative salaries and the recruitment of two additional temporary operatives to address the service issues.

2.3Approves a supplementary budget of £149,999 in year one, £75,947 thereafter funded through the HRA, as detailed in section 5. 3. Background to the report

3.1Staffing Challenges

The housing repair service is continuing to face ongoing challenges in respect to the morale of existing trade operatives due to the perception and evidence base that HBBC is not competitive with pay levels when compared to other local authority housing providers and challenges of recruitment and retention due to these issues. These challenges are likely to undermine our legislative and regulatory responsibilities, ultimately increasing risks to tenants by failing to carry out works in a timely way, further creating risks to HBBC for failing to meet its landlords’ responsibilities.

Whist there have been some success in recruiting to vacancies within the service, there have been multiple attempts to recruit to posts such as multi trade plumber and senior multi trade carpenters and plasterers which have proved difficult and costly.

Work into the recruitment and retention situation has highlighted:

 We are seeing active resignations, due to operatives finding alternative employment at much better rates of pay.  Other operatives are actively seeking new employment due to pay.  Two operatives are due to retire within 12 months and the service is concerned about recruiting to those posts.  Over the last 12 months, take up of overtime has been extremely poor as overtime rates of pay are also not competitive.  Agencies have declined to recruit to permanent posts on HBBC’s behalf due to the lower-than-average rates of pay.  Repairs have struggled to backfill vacancies with agency staff, and where we have been successful there is contention, due to paying agency workers a higher rate of pay that do not necessarily hold the same level of skills as our employed operatives.

We are finding it increasingly difficult to attract and retain talent, especially operatives skilled at the right level that we would expect to be able to carry out the works within the remit of the In-House contractor.

3.2Backlog of Responsive Repairs

In addition to these challenges the housing repairs service still faces a backlog of works due to its inability to carry out routine and planned responsive works during the pandemic.

The number of outstanding jobs is not reducing significantly month by month and at best remains stable. This is due to a large part to not having a full workforce due to the above-mentioned difficulties recruiting. The backlog will continue to increase, albeit more slowly than during the pandemic. The below table shows the total number of live jobs per month. We would expect figures to rise in Autumn/Winter.

Table A number of jobs raised each month

Month Number of Live Jobs Jun-22 1100 Jul-22 1088 Aug-22 1021 Sep-22 1030 Oct-22 1081 Nov-22 1071 Dec-22 784 Jan-23 925 Feb-23 875 Mar-23 803 Apr-23 783

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council house repairs backlog and pay challengesReport 8 pages DownloadRead as text

More from Hinckley and Bosworth Council

All decisions
MeetingDecisionOutcome
27 Oct 2026 Minutes of the previous meetingRESOLVED – the minutes of the meeting held on 29 September be approved. Approved Open
27 Oct 2026 Review of the council's constitutionRESOLVED – the changes to the constitution be approved. Approved Open
27 Oct 2026 Community Governance Review - Witherley - final recommendationsRESOLVED – (i) The current parish of Witherley and Witherley Parish Council be abolished; (ii) Fenny Drayton parish a... Decided Open
29 Sep 2026 Minutes of the previous meetingsRESOLVED – the minutes of the meetings held on 23 July and 4 August 2026 be confirmed as a correct record. Decided Open
29 Sep 2026 Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies