RESOLVED – (i) Option B, which included demolition of existing flats and further work to draw up a detailed scheme, be supported; (ii) The capital budget be increased by £1,181,073 to ensure maximum flexibility in determining the mix of property types / scheme design; (iii) The issuing of a demolition notice be approved; (iv) The associated one-off home loss and disturbance payments of £200,000 be approved.
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
1.1To inform members of the proposals for regeneration of the flats at Peggs Close, Earl Shilton, and the progression of the project.
Recommendation
That Council
2.1Support progression of option B to demolish all the existing flats and to carry out further work to draw up a detailed scheme.
2.2Increase the capital budget by £1,181,073 to ensure maximum flexibility in determining the mix of property types/scheme design (this is based on pre- tender estimates of indicative schemes).
2.3Approve the issue of a demolition notice as the first stage of the regeneration groundwork, to progress to demolition of the buildings when they are vacated.
2.4Approve the associated one-off home loss and disturbance payments of £200,000.
3. Background to the report
3.1The Peggs Close development in Earl Shilton comprises three blocks of 3 storey residential accommodation. Constructed in 1977 the scheme comprises the following mix of properties:
06/16 Accommodation type Block A Block B Block C Total 1 bed rented flats 4 3 6 13 2 bed rented flats 3 6 6 15 2 bed leasehold flat 1 1 Community Hub (1 bed flat) 2 2 Community Hub (2 bed flat) 2 2 Total 12 9 12 33
3.2Throughout the history of Peggs Close there have been issues with anti-social behaviour in the neighbourhood. Previous work carried out at the flats has failed to resolve these issues and community safety remains an ongoing challenge.
3.3In addition, although the buildings are safe, there is a requirement to carry out essential work at all the blocks of flats which has financial implications. In 2019 this was costed at £500,000, and would require all residents to be decanted, with an additional cost for the Council to assist residents with the move.
3.4The flats are a mixture of 1 and 2 bedroomed flats, and whilst there is a need for 1 bedroomed flats across the whole of the Borough, 2 bedrooms are unpopular and hard to let as families prefer houses and childless couples / single people would be subject to housing benefit restrictions.
3.5Due to the requirement to carry out essential work on the buildings, and the historic underperformance in terms of housing management and void costs, Ark Consultancy carried out an all options appraisal on the blocks.
3.6The original options were assessed, and 2 options were considered the best fit for reasons of cost and to meet strategic objectives for the council’s housing stock. These 2 options were therefore put out for consultation to residents of the 3 blocks of flats.
3.7These options are: Option A: Partial redevelopment and retention This option would demolish 2 of the blocks of flats and leave 1 block standing.
Option B: Complete redevelopment - This option demolishes all 3 blocks and a new development in its place.
3.8Currently 19 of the flats are occupied, 4 flats form the community house and 1 flat has been sold. The property which is privately owned is currently let to a tenant. There are 9 voids. Letters were hand delivered to all occupants of the flats, setting out the 2 options and inviting them to a drop-in session to discuss the options. Two drop-in sessions were held in the on-site community house. Residents were invited to submit their response to the consultation either online or by letter during the month of February 2023.
3.9Due to local elections taking place, consultation was paused until the end of the election period. Officers made one to one visits in June 2023 to engage with
06/16 residents who had not responded to the questionnaire and to discuss options individually with those who had requested a private meeting. Consultation results
3.10Thirteen consultation responses were returned. The majority of these responses support the regeneration of the site and option B, to demolish all of the flats, was the narrowly supported preferred approach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.