Resolved
RESOLVED – (i) The funding allocations of £82,990 as outlined in the report be endorsed; (ii) The proposed amendments to the community equipment grant be supported.
Scrutiny Commission decided this item on Thursday 13 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – (i) The funding allocations of £82,990 as outlined in the report be endorsed; (ii) The proposed amendments to the community equipment grant be supported.
1.1To request that the Scrutiny Commission endorses the allocation of the Parish and Community Initiative Fund (PCIF) 2025/26.
1.2To request that the Scrutiny Commission note the list of schemes approved under this year’s Community Equipment Grant and support the proposed amendments to the grant scheme for 2025/26.
2.1That the Scrutiny Commission endorses the funding allocations of £82,990 for 14 schemes as detailed in section 3.3.
2.2That the Scrutiny Commission support the proposed amendments to the Community Equipment Grant as detailed in section 3.4
3. Background to the report
3.1Since 2005 the Parish Community Initiative Fund and Hinckley Community Initiative Fund have distributed £1,922,841 towards 469 local parishes or voluntary organisation schemes.
3.2In 2024/25 the scheme received 13 applications from across the Borough and a total of £91,892 was awarded to 13 schemes.
06/16 3.3 Applications for 2025/26:
The table in Appendix 1 of this report provides an objective scoring summary from the assessments made of all the applications by the following Officers: Ian Pinfold – Green Space Manager, Paul Scragg – Senior Green Space Officer and Ben Pipe Green Space Officer.
The assessment panel then determined which applications they felt should be awarded grant funding. This panel consisted of Caroline Roffey Head of Street Scene Services, Ian Pinfold – Green Space Manager, Paul Scragg – Senior Green Space Officer and Ben Pipe Green Space Officer. The grant will fund a maximum of 50% of the project costs. Each applicant must seek support from their Parish Council and Borough Councillor. Only capital items over £5,000 in value are funded and the lowest submitted quote has been used to calculate the maximum eligible grant, unless a good reason has been provided for using a higher quote. Each application has been scored individually against the criteria by 2 officers and an average score given.
To reflect the scale and cost of some climate change projects, it was agreed after a review in 2023 that the maximum grant award will be increased to £20,000 / 50% of project costs. This increased grant size would overrule the £12,000 per parish limit and would only be applied for significant carbon reduction projects.
We have received 14 applications this year requesting a total of £82,990, all schemes scored over 50 out of hundred against the scoring criteria and the panel therefore recommends funding all of the projects as detailed below:
1. Solar Panels– Barlestone Parish Council (Barlestone). Outline: The installation of solar panels at Barlestone Community Centre £6,500.
2. Replacement Mower – Market Bosworth Bowling Club (Market Bosworth) Outline: The purchase of a new mower to ensure quality maintenance of the greens. £3,597.
3. Footpath improvements – Burbage Parish Council (Burbage) Outline: The installation of a new section of footpath and footpath improvements at Sketchley Hill Recreation Ground. £7,975
4. Dadlington Village Hall Carbon reduction scheme – Dadlington Village Hall Committee (Dadlington) Outline: The installation of external Wall insulation at the Village Hall to improve energy efficiency. £6,475
5. St Martin’s Church renovation – St Martin’s Parochial Church Council (Desford). Outline: The installation of 3 new windows to the Church Hall and improvements to the church walls. £3,632
6. New flooring – Sport in Desford (Desford) Outline: The installation of new flooring in the gym. £2,580
06/16 7. New Slide for play area – Peckleton Parish Council (Peckleton) Outline: The installation of a new slide at Kirkby Mallory recreation ground. £2,623
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Parish & Community Initiative FundReport | 9 pages | DownloadRead as text |
Follow Scrutiny Commission at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... | Approved | Open |
| 22 Oct 2026 | Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. | Approved | Open |
| 22 Oct 2026 | Budget planRESOLVED - members noted the Budget Plan for 2027/2028. | Noted | Open |
| 22 Oct 2026 | Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... | Noted | Open |
| 22 Oct 2026 | Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.