Scrutiny Commission, Thursday 6 November 2025 at 6.30pm

Scrutiny review: adoption of infrastructure associated with housing development - final report

Decided Scrutiny 5 papers

AI summaryHinckley and Bosworth scrutiny commission forwards final report and 13 recommendations on adoption of housing development infrastructure to the Executive.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedScrutiny commission agreed to forward task and finish group report
Moneynull20 years maintenance sum usually required from developer
What happens nextExecutive to consider the reportAction to be decided by the Executive
Who it affectsNot stated

What was decided

The commission agreed that the task and finish group's final report and its 13 recommendations be presented to the Executive. Report P1

Why

The review found a growing tendency for new open space, play equipment and public highways in the borough to remain in the hands of commercial management companies rather than being adopted by public bodies, leading to concerns about service standards and unclear maintenance responsibilities. Report 2.1, 2.2, 2.3

The 2024 Competition and Markets Authority report reached similar conclusions nationally, identifying that consumers on privately managed estates were experiencing poor outcomes driven by falling levels of adoption by local authorities. Report P24, P26, P27, P31

What happens next

The Executive is asked to write to the appropriate minister urging action on recommendations 1 and 2 of the CMA report and to encourage mandating of stewardship schemes, and to raise concerns about public adoption of roads with Leicestershire County Council highways. Report 7.1, 7.2

Officers are to incorporate model standardised wording in S106 agreements, covering open space, transfers, 20-year maintenance sums and options appraisals, and to make sure open space is offered to town, parish or borough council in the first instance. Report 7.3, 7.4, P92

The new local plan is to make provision for stewardship approaches at both large and small scales, the council website is to be updated with developer expectations, and a briefing pack is to be prepared for parish and town councils to support them in adopting open space. Report 7.5, 7.6, 7.7, 7.8, 7.12, 7.13

The money

  • 20 years Maintenance sum paid by developer and used by the adopting council after transfer Report P53
  • 12-month Maintenance period on open space before final certificate issued Report P48, P49

Options considered

  • Supported: Public adoption by borough, town or parish council of new open space and infrastructure. Seen as the preferred long-term outcome for residents, supported by CMA findings and task group conclusions Report 6.1, 6.3, 7.1, 7.3
  • Rejected as default: Management by a private management company funded by service charges. Linked to poor outcomes and lack of consumer protection; group wants this replaced as the default presumption in new applications Report P47, 6.1
  • Supported: Long-term stewardship scheme as an alternative management model. Considered an effective approach, including for Sustainable Urban Extensions, to be encouraged through the new local plan Report 5.3, P40, P41, 7.5, 7.6, 7.7, 7.9

Implications

  • Legal: Model S106 wording changes to require open space to be offered to the relevant council first, to set timeframes for transfers, to require an options appraisal, and to guarantee 20 years' maintenance funding regardless of who manages the site. Report 7.3, 7.4, P92
  • Other: Waste collection on private roads is becoming more common as more roads remain unadopted, leaving some residents without a kerbside service; officers are asked to review the council's waste strategy. Report P67, 7.11
  • Risk: Underground and pumped Sustainable Urban Drainage Systems pose medium to long term financial risk if they fail, making adoption unlikely where pumping stations are included. Report P70
  • Equalities: Residents on privately managed estates may pay both a parish precept and a management company service charge for open space that other residents can also use, creating an unfair cost burden. Report P76
  • Other: Lobbying of national government is recommended, as the task group concluded that the power to resolve the underlying issues lies with government rather than locally. Report 6.2, 7.1

Who and where

  • Residents of new housing estates in the borough, including those on unadopted roads and those paying service charges to management companies Report 2.2, P67, P76
  • Borough, town and parish councils asked to consider adopting new infrastructure Report 2.4, P78, 7.12
  • Housebuilders and developers of new housing, including Sustainable Urban Extension developers Report P43, 7.9
  • Leicestershire County Council as Local Highway Authority for roads and related assets Report P61, 7.2
  • The Planning Manager, Democratic Services Manager and Compliance and Monitoring Officer who supported the task and finish group Report 4.7

Timeline

  • 20 January 2025: First meeting of the task and finish group, agreeing approach and information required Report 4.9
  • 10 April 2025: Second meeting of the task and finish group Report 4.9
  • 10 June 2025: Third meeting of the task and finish group Report 4.9
  • 2 July 2025: Fourth meeting of the task and finish group Report 4.9
  • 12 August 2025: Final meeting of the task and finish group, where the report was drafted Report 4.5, 4.9
  • 6 November 2025: Scrutiny commission considered the final report and resolved to send it to the Executive
  • Within 12 months of completion: Open space maintenance period after which a final certificate may be issued Report P48, P49
  • 20 years: Period the maintenance sum from the developer is typically expected to cover after adoption Report P53

Plain English for the jargon

  • S106 agreement: A legal agreement under section 106 of the Town and Country Planning Act used to secure planning obligations, including provision and maintenance of open space.
  • S38 agreement: An agreement under section 38 of the Highways Act used to secure the adoption of new roads by the Local Highway Authority.
  • S278 agreement: An agreement under section 278 of the Highways Act used to secure highway works outside the development site.
  • SuDS: Sustainable Urban Drainage Systems, features such as attenuation ponds that manage surface water runoff.
  • BNG: Biodiversity Net Gain, a requirement for development to deliver a measured improvement in biodiversity.
  • CMA: Competition and Markets Authority, which published a 2024 report on the housebuilding market.
  • HBBC: Hinckley and Bosworth Borough Council.
  • LCC: Leicestershire County Council, the Local Highway Authority for the borough.
  • LHDG: The Leicestershire Highways Design Guide, written by Leicestershire County Council, setting out when roads will be adopted.
  • SUE: Sustainable Urban Extension, a large scale housing development on the edge of an existing settlement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item223

Resolved

RESOLVED – the report and its recommendations be presented to the Executive.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Scrutiny Commission, 13 pages

Scrutiny review of adoption of infrastructure associated with housing development Report of the Task & Finish Group 1. Purpose of the review

1.1The purpose of the review was to consider how items of infrastructure (such as public open space or roads) associated with housing development projects were adopted and by what bodies, ensuring the management of the infrastructure was balanced in the long-term interests of both the public and residents associated with new developments, within reasonable timeframes.

2. Background to the subject of the review

2.1Within the Borough over the last few years there had been a growing tendency for new open space, play equipment and public highways to not be adopted by public bodies and this infrastructure was therefore managed by commercial companies.

2.2Members had received concerns relating to difficulties associated with services not being delivered to the necessary standard, and also many cases of uncertainty as to the responsibilities for maintenance of some assets (for example streetlights).

2.3Concerns had been raised with members about the speed of the adoption of assets where an agreement to adopt assets had been made, however, in all cases this would require the developer to demonstrate that the infrastructure had been delivered/built to an acceptable standard or in accordance with approved plans for transfer. In some cases, this period had been over twenty years and issues of responsibility always arose during the period between occupation and adoption.

2.4Members of the borough, town and parish councils were driven to ensure developers’ contributions were appropriate amounts for public bodies to take on the responsibility for maintenance of open spaces in perpetuity. 3. Key points for the review

3.1It was agreed that the review would explore;

 the process for the adoption of infrastructure associated with large developments  the powers the council had at its disposal through the planning process to mandate outcomes and understand what decisions were ultimately in the gift of the developer  what the long-term issues were in respect of infrastructure managed by commercial management companies  how decision making on the adoption of infrastructure by the borough, town & parish councils could be made more transparent, less intimidating and could be taken with full knowledge of the consequences  benefits that could be achieved from the concept of stewardship schemes and how they might be promoted  how infrastructure adoption timescales could be reduced once development had been completed.

3.2Outcomes expected from the review included;

 a working understanding of the planning process for infrastructure  an understanding of the long-term impacts of the management of infrastructure  recommendations relating to a stewardship style of management  recommendations for new guidance/briefing information for Town & Parish Councils  recommendations for matters that could be addressed in the new Local Plan  recommendations to the government relating to outcomes of the review. 4. Process for the review

4.1The group agreed that the first stage of the review would be to ask planning officers to outline the process by which infrastructure was progressed through the planning process and outline their understanding of the options available to them to influence the options presented by developers.

4.2Building on this initial position and learning from case studies, it was agreed that witnesses would be requested from key stakeholders to inform the groups review of drivers, implementation and outcomes. Witnesses attended on behalf of a developer, a management company and a stewardship scheme.

4.3A glossary of terms would be prepared to aid members’ understanding and support the final recommendations.

4.4The group would consider the potential updates in the revised open spaces study being prepared as part of the Local Plan and consider how this would modify the current consideration and adoption process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GlossaryAppendix 1 5 pages Download
PDF
Adoption of Open Space Flow ChartAppendix 2 1 pages Download
PDF
Section 38-process-chartAppendix 3 1 pages Download
PDF
Planning Contributions Process Flow Chart 12.5.25Appendix 4 7 pages Download
PDF
Scrutiny review: adoption of infrastructure associated with housing development: final reportReport 13 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 18 attended
CL
Councillor C LambertChair, present
MS
Councillor MJ SurteesVice-Chair, apologies
PW
Councillor P WilliamsVice-Chair, present
DC
Councillor DS CopeCommittee Member, present
MC
Councillor MJ CrooksCommittee Member, present
CH
Councillor C HarrisCommittee Member, present
JM
Councillor JR MooreCommittee Member, apologies
AP
Councillor A PendleburyCommittee Member, present
MS
Councillor M SimmonsCommittee Member, apologies
RW
Councillor R Webber-JonesCommittee Member, apologies
AW
Councillor A WeightmanCommittee Member, absent
CB
Chris BrownOfficer, in attendance

All 18 on the meeting page

On this subject at Hinckley and Bosworth

Search all
  1. Scrutiny review: adoption of infrastructure associated with housing development - final reportThis decision
  2. Scrutiny review: digital povertyNoted
  3. Scrutiny review: adoption of infrastructure associated with housing development - final reportApproved
  4. Scrutiny review: HousingDecided
  5. Scrutiny review: housingDecided
  6. Scrutiny review: utility companiesDecided

More from Hinckley and Bosworth Scrutiny Commission

All decisions
MeetingDecisionOutcome
22 Oct 2026 Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... Approved Open
22 Oct 2026 Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. Approved Open
22 Oct 2026 Budget planRESOLVED - members noted the Budget Plan for 2027/2028. Noted Open
22 Oct 2026 Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... Noted Open
22 Oct 2026 Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies