What was decided
The Council resolved that a letter be sent to Rugby Borough Council, Warwickshire County Council, Leicestershire County Council, National Highways and the Department for Transport.
The letter is to stress the importance of all infrastructure listed in the planning conditions as being required to be delivered prior to the development first being brought into use.
The conditions, particularly condition 13 covering the scheme of works for lowering the A5 carriageway under the railway bridge, should not be relaxed in any way.
Why
HGV strikes at the A5 railway bridge cause economic losses and major delays on local and national roads, costing residents time and money.
In 2023 the Council reluctantly approved a large warehouse development on adjoining Warwickshire land on the condition that the bridge, access road and Dodwells roundabout in its control would be improved.
The warehouse development is close to completion but the A5 carriageway design has only just been completed and still requires review, creating a risk the site could open before highway works are finished.
What happens next
A letter is to be sent to Rugby Borough Council, Warwickshire County Council, Leicestershire County Council, National Highways and the Department for Transport.
The letter will emphasise the need for all required infrastructure, especially condition 13 (lowering the A5 carriageway under the railway bridge), to be delivered before the development is brought into use.
Implications
- Legal: Existing planning conditions, including condition 13, should not be relaxed in any way.
- Risk: Without completed highway works, the warehouse could be brought into use while the A5 bridge and Dodwells roundabout remain congested and liable to HGV strikes.
- Other: National Highways has flagged fundamental concerns over the A5 carriageway design, and full approval is not yet in place.
Who and where
- Residents and road users affected by delays and congestion at the A5 railway bridge and Dodwells roundabout
- The developer of the adjoining Warwickshire warehouse site
- National Highways as the responsible authority for the A5
- Rugby Borough Council, Warwickshire County Council, Leicestershire County Council and the Department for Transport as the recipients of the letter
Timeline
- 2023: Council reluctantly approved the Warwickshire warehouse development subject to highway improvement conditions.
- Within six months of presenting plans: Work on the bridge was originally expected to begin, but has not progressed as planned.
- At the time of the motion: The A5 carriageway design has only just been completed and is still being reviewed by National Highways.
- 2025-11-18: Council agreed to write to the other parties stressing the need to deliver the required infrastructure before the development opens.
Plain English for the jargon
- HBBC: Hinckley and Bosworth Borough Council.
- HGV: Heavy goods vehicle, a large lorry.
- Condition 13: The planning condition requiring the scheme of works for lowering the A5 carriageway under the railway bridge.
- Dodwells roundabout: A roundabout in Hinckley that lies within the Council's control and is part of the access road to the development site.