AI summaryHinckley and Bosworth planners approve conversion of a traditional barn at Holywell Farm, Ratby into a three bedroom home, subject to conditions on materials, ecology, archaeology and drainage.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedConversion of Barn A into one dwelling approved
MoneyNot stated
What happens nextCommence within three yearsAssistant Director to finalise conditions
Who it affectsApplicant, parish, ecology, heritageNeighbours, public rights of way users
What was decided
Planning permission was granted for conversion of the traditional barn, known as Barn A, at Holywell Farm, Desford Lane, Ratby, into a single three bedroom dwelling, subject to the conditions and notes to applicant set out in the officer's report. Report P6, P8, P16
The Assistant Director of Planning and Regeneration was given authority to determine the final detail of the planning conditions. Report P7
The proposal mirrors two earlier consents for the site from 2015 and 2019 which were not implemented, and includes raising the roof on one side of the barn, new window openings, and demolition of the Dutch barns to the rear. Report P8
Why
The council cannot demonstrate a five year housing land supply, so the tilted balance in paragraph 11(d) of the National Planning Policy Framework applies, weighing the benefits of the scheme against any adverse impacts. Report P14
The barn is a redundant agricultural building of historic merit, in a structurally sound condition and capable of conversion without significant rebuild, so the proposal is supported by policies DM4(b) and DM15 of the Site Allocations and Development Management Policies document. Report P14
Officers found no material harm to highway safety, neighbouring amenity, ecology and biodiversity, archaeology, drainage, waste or heritage assets subject to conditions, and the reuse of the redundant building outweighed the harm from the unsustainable countryside location. Report P14, P16
What happens next
The development must begin before the expiration of three years from the date of the permission. Report P17, P18
Several pre commencement or pre occupation conditions must be discharged, including submission and approval of material samples, boundary treatment details, written schemes of investigation for historic building recording and archaeology, and a Biodiversity Gain Plan. Report P19, P20, P24, P26, P28
A Natural England bat licence will be required for the works, with mitigation measures to be implemented as set out in the Preliminary Roost Assessment and the Preliminary Ecological Appraisal for Barn A. Report P14, P28
Options considered
Chosen: Grant planning permission subject to conditions and notes, with delegated authority to finalise conditions. Officers concluded the scheme complies with the development plan and the tilted balance in the NPPF, with no material harm subject to conditions. Report P6, P7, P16
Implications
Ecological: Bat mitigation required, including a Natural England licence, pre commencement bat box, integrated bat box in the new dwelling, swallow nest cups, and a Biodiversity Net Gain of plus 14.47% in Habitat Units to be secured for 30 years. Report P14
Legal: Section 66 of the Planning (Listed Buildings and Conservation Areas) Act 1990 duty considered, and Section 149 of the Equality Act 2010 public sector equality duty considered with no known equality implications arising. Report P14, P15
Climate: The site is in an unsustainable and isolated countryside location with poor transport sustainability, meaning future occupiers are highly likely to be dependent on private motorised travel, contrary to the sustainability aims of the NPPF. Report P14
Other: Ratby Parish Council objected on grounds of inappropriate countryside development, urbanising effect, biodiversity impacts and precedent, but officers concluded the proposal is supported by policy and conditions. Report P12, P14
Who and where
The applicant, owner of Holywell Farm Report P2, P8
Future occupiers of the three bedroom dwelling Report P14
Occupants of the existing farmhouse on the same farmstead Report P14
Common pipistrelle bats using two day roosts in the barn Report P14
Nesting swallows and wren using the site Report P14
Users of public bridleway R42 and public footpath R43 Report P9, P14
Ratby Parish Council, as objector Report P12
Timeline
16 March 2026: Application details and site location, block and layout plans received by the Local Planning Authority Report P19
21 April 2026: Amended proposed details plan received following case officer request to change window materials to aluminium Report P19, P14
Within three years of permission: Development must be begun Report P17, P18
2 June 2026: Planning Committee resolves to grant permission subject to conditions Report P1
Plain English for the jargon
Tilted balance: The presumption in favour of sustainable development in paragraph 11(d) of the National Planning Policy Framework, engaged where a council cannot show a five year supply of deliverable housing sites.
Biodiversity Net Gain: A measurable improvement in biodiversity value of a site after development, with a statutory minimum of 10% under the Environment Act framework.
Scheduled Monument: A nationally important archaeological site given legal protection under the Ancient Monuments and Archaeological Areas Act 1979, in this case the Iron Age hillfort Bury Camp.
Designated open countryside: Land outside defined settlement boundaries where the council's planning policies generally restrict new development to protect landscape character and prevent settlement coalescence.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30
Resolved
RESOLVED – (i) Permission be granted subject to the conditions and notes to applicant outlined in the officer’s report; (ii) The Assistant Director Planning and Regeneration be granted authority to determine the final detail of planning conditions.
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
1. Recommendations 1.1. Grant planning permission subject to: Planning conditions and notes to applicant outlined at the end of this report
That the Assistant Director Planning and Regeneration be given powers to determine the final detail of planning conditions.
2. Planning application description 2.1. The application seeks full planning permission for the conversion of a traditional barn into a dwelling (specifically Barn A) at Holywell Farm, Desford Lane, Ratby. 2.2. As part of the conversion the roof on the left-hand side of the barn is to be raised and additional window openings would be created. The Dutch barns to the rear of the site are also proposed to be demolished. A full breakdown of works are enclosed within the submitted Building Condition Statement. The proposed plans mirror those granted planning permission in 2015 and 2019 under application reference: 14/00206/FUL and 19/01239/FUL.
3. Description of the site and surrounding area 3.1. The application site is located within the designated open countryside to the west of the settlement boundary of Ratby, within the National Forest and Charnwood Forest. Ratby is a Key Rural Centre located on the periphery of Leicester. 3.2. The application site consists of the existing Holywell Farm farmhouse alongside a number of outbuildings and a number of agricultural fields. The outbuilding subject to the application is situated immediately to the north-west of the access track. 3.3. The Holywell Farm site contains the Scheduled Monument, Bury Camp, an Iron Age hillfort which is located approximately 160 metres north-west of the application site. The historic farm complex is likewise a non-designated heritage asset in its own right. 3.4. The existing access from Desford Lane, an adopted and classified ‘C’ road subject to a 60mph speed limit is hard surfaced at the point of entrance with passing room for vehicles traveling in either direction. The remainder of the access is via a long and narrow farm track. A public bridleway (R42) follows most of the access drive and passes to the south of the application building. To the east of the application site public footpath (R43) crosses the access drive and meets with the public bridleway. 3.5. The application site is immediately surrounded by land within the designated open countryside. To the east of the site (approximately 821.00 metres away) beyond other farms is Ratby Medical Centre and the Ratby Sports Club, which mark the western entry to Ratby along Desford Lane.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.