CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hinckley and Bosworth Borough Council
Scrutiny Commission, Thursday 2 July 2026 at 6.30pm

General fund temporary accommodation programme - phase 3

Approved Scrutiny 1 paper

AI summaryScrutiny Commission backs phase 3 plan to buy one-bedroom properties and repurpose John Nichols Street Hostel as supported accommodation, using up to £2.5million from existing capital funds.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedScrutiny Commission endorsed phase 3 of the temporary accommodation programme
MoneyUp to £2.5million capitalPlus £384,250 revenue, funded by PWLB borrowing
What happens nextCouncil and Executive to approveCouncil to set revenue budget, Executive to approve partnership
Who it affectsSingle homeless householdsPeople placed in nightly paid temporary accommodation

What was decided

Members backed the use of up to £2.5million from the approved capital programme to acquire one-bedroom properties. Report 2.1, 5.1

Members agreed to recommend that Council approves a revenue budget of £384,250 with a matching income budget for the scheme. Report 2.3, 5.1

Members agreed to recommend that the Executive approves a partnership with Falcon Support Services to operate supported accommodation at John Nichols Street Hostel, and endorsed delegation to the Director of Place Services to implement the proposals. Report 2.4, P26

Why

Single households now make up a large share of nightly paid placements, which is described as the most volatile and costly area of homelessness spending. Report 3.1, 3.2

Earlier phases focused on family accommodation, but demand from single people has continued to rise. Report 3.3

John Nichols Street Hostel is a Council owned HRA asset that is underused in its current family configuration, while there is no dedicated supported accommodation for single homeless people in the borough. Report P18

What happens next

Full Council to be asked to approve the £384,250 revenue budget and matching income budget. Report 2.3

The Executive to be asked to approve entering a partnership with Falcon Support Services, subject to procurement requirements, and to finalise lease terms that keep the HRA compliant. Report 2.4

The Director of Place Services, with the Section 151 Officer and relevant Executive member, to implement the acquisitions and the hostel repurposing, monitoring property market and scheme affordability. Report P58

The money

  • £2.5million Capital for acquiring up to 15 one-bedroom properties, funded by PWLB borrowing Report 2.1, 5.1
  • £384,250 Annual revenue cost and matching income budget for 15 units Report 2.3, 5.1, P36
  • £340,000 Annual revenue cost and income if 10 units are bought Report P36
  • £151,500 Annual interest at 6.06% on PWLB borrowing Report P36, 5.1
  • £100,000 Annual Minimum Revenue Provision based on 25 year annuity Report P36
  • £88,500 Other running costs for 10 units Report P36
  • £132,750 Other running costs for 15 units Report P36
  • £250,000 Prudent estimate of cost per unit including purchase, fees and refurbishment
  • £167,000 Possible average per property if 15 units bought within £2.5m, described as possibly optimistic
  • -£219,000 Estimated annual temporary accommodation saving from 10 units Report 5.1, P36
  • -£273,750 Estimated annual temporary accommodation saving from 15 units Report 5.1, P36
  • £1,825 Per unit per month temporary accommodation saving Report P36
  • £328,000 Current annual cost of equivalent temporary accommodation for John Nichols Street Report P38, 5.2
  • £179,995 Estimated annual cost of the proposed supported accommodation model at John Nichols Street Report P39, 5.2
  • £148,000 Estimated annual saving from the John Nichols Street model Report P40, P52, 5.2
  • £367,000 Combined estimated annual saving if 10 units are purchased Report 5.3
  • £421,750 Combined estimated annual saving if 15 units can be purchased Report 5.3
  • £251,500 Annual financing costs (interest and MRP) on the £2.5m PWLB borrowing Report 5.1

Implications

  • Financial: £2.5m funded by PWLB borrowing, with annual financing and running costs up to £384,250 and combined estimated annual savings of £367,000 to £421,750. Savings are not guaranteed if homelessness demand continues to rise. Report 5.1, 5.3, 5.4
  • Legal: Any John Nichols Street arrangement must satisfy Council procurement rules and keep the HRA compliant, with detailed terms to be finalised by Legal and Finance. Report 6.1
  • Risk: Risks include delays in acquiring suitable one-bedroom properties, buying fewer than expected, and the John Nichols Street partnership not progressing at the intended pace or terms, all to be monitored on the project risk register. Report P58
  • Equalities: Proposals expected to have a positive impact for single homeless households, including those with support needs; an Equality Impact Assessment is not considered necessary at this approval in principle stage. Report 10.1, 10.2
  • Climate: Acquisitions and refurbishments will need to consider energy performance and sustainability where practical and affordable, but climate implications are not seen as outweighing the need to act. Report 11.1, 11.2
  • Other: Phase 3 uses a mixed model: self-contained one-bedroom properties and supported accommodation at John Nichols Street Hostel for up to 15 single homeless individuals, with Falcon Support Services leasing the building and providing 24/7 housing management and support. Report 3.4, P26

Who and where

  • Single homeless households in the borough Report 1.1, 3.1
  • Single homeless individuals with more complex support needs Report 3.4
  • Current residents of John Nichols Street Hostel, as the building is repurposed from family use Report P18
  • Council tenants in the HRA, as the hostel arrangement must keep the HRA compliant

Timeline

  • February 2026: Acquisition and Development Scheme capital budget of £2.5m approved Report 5.1
  • 2026-07-02: Scrutiny Commission considered phase 3 proposals
  • Not specified: Wider temporary accommodation solutions will continue to be explored beyond this report Report 3.5, P44

Plain English for the jargon

  • TA: Temporary accommodation, often paid for nightly at high cost
  • HRA: Housing Revenue Account, the ringfenced account for council housing
  • PWLB: Public Works Loan Board, a government body that lends to local authorities
  • MRP: Minimum Revenue Provision, the annual repayment of borrowing principal
  • CFR: Capital Financing Requirement, the council's underlying borrowing need
  • MTFS: Medium Term Financial Strategy, the council's multi-year budget plan
  • Section 151 Officer: The council's chief finance officer, with statutory responsibility for financial affairs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66

Resolved

RESOLVED – (i) The use of up to £2.5million from the approved capital programme be approved to acquire one-bedroom properties; (ii) Council be RECOMMENDED to approve a revenue expenditure budget of £384,250 together with a matching income budget to support the operation of the acquisition scheme; (iii) The Executive be RECOMMENDED to approve the entering into of a partnership with Falcon Support Services to operate supported accommodation at Joh Nichols Street hostel; (iv) The delegation of authority to the Director of Place Services, in consultation with the Section 151 Officer and relevant Executive member to implement the proposals be endorsed.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Scrutiny Commission

Purpose of report

1.1To outline Phase 3 of the Council’s programme to reduce reliance on costly nightly paid temporary accommodation (TA) for single homeless household.

1.2To seek support for utilisation of existing capital provision to acquire one- bedroom properties for use as Council owned temporary accommodation.

1.3To seek support for repurposing John Nichols Street Hostel as supported accommodation through a partnership arrangement.

1.4To set out the financial implications and expected impact in reducing General Fund pressures and improving accommodation outcomes.

Recommendation

2.1That members support the use of up to £2.5 million from the approved capital programme to acquire one-bedroom properties.

2.3That members support Council approval of a revenue expenditure budget of £384,250, together with a matching income budget, to support the operation of the acquisition scheme.

2.4That members recommend Executive approval to enter into a partnership with Falcon Support Services, subject to satisfying procurement requirements, to operate supported accommodation at John Nichols Street Hostel. 2.5 That Members note and endorse delegation of authority to the Director of Place Services, in consultation with the Section 151 Officer and Portfolio Holder, to implement these proposals.

3. Background to the report

3.1The Council continues to experience sustained pressure in temporary accommodation, particularly for single households. This cohort now represents a significant proportion of nightly paid placements and is the most volatile and costly area of homelessness expenditure.

3.2The current model of relying on nightly paid accommodation provides limited stability and support, contributing to poorer outcomes and ongoing cost pressures.

3.3Earlier phases of the acquisition programme focused on family accommodation and have improved quality and reduced reliance on high-cost placements. However, demand from single people has continued to increase.

3.4Phase 3 therefore adopts a mixed model approach, combining:  self-contained accommodation; and  supported accommodation for those with more complex needs

3.5Given current homelessness demands, wider solutions around temporary accommodation provisions will continue to be sought, beyond those outlined within this report.

3.6John Nichols Street Hostel

3.6.1 John Nichols Street Hostel is a Council-owned Housing Revenue Account (HRA) asset currently used for small families but is not well suited to that purpose due to the size and configuration of rooms, resulting in underutilisation.

3.6.2 As a result, the asset is underperforming and does not represent best value in its current form. At the same time, demand for accommodation for single people remains high, with many placed in unsuitable nightly paid accommodation.

3.6.3 There is currently no dedicated supported accommodation provision within the borough for single homeless individuals, and the absence of this contributes to repeat homelessness and ongoing reliance on costly TA.

3.6.4 The Council has therefore considered how existing assets can be better utilised. John Nichols Street presents an opportunity to:  bring an underperforming asset back into effective use  align provision with current demand  introduce a supported housing offer locally 3.6.5 Repurposing the building as supported accommodation supports a more sustainable pathway for individuals, improving outcomes and reducing repeat use of temporary accommodation.

4. Proposal- Acquisition of one-bedroom properties and John Nichols Street Hostel

4.1.1 It is recommended that the Council acquire up to 10-15 one-bedroom properties to provide self-contained temporary accommodation.

4.1.2 These properties will reduce reliance on nightly paid accommodation, improve standards and provide long-term asset value.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General fund temporary accommodation programme: phase 3Report 458 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 17 attended
PW
Councillor P WilliamsVice-Chair, in the Chair, present
CL
Councillor C LambertChair, apologies
MS
Councillor MJ SurteesVice-Chair, present
RA
Councillor RG AllenCommittee Member, apologies
DC
Councillor DS CopeCommittee Member, present
MC
Councillor MJ CrooksCommittee Member, apologies
CH
Councillor C HarrisCommittee Member, apologies
DJ
Councillor Dr JR MooreCommittee Member, absent
AP
Councillor A PendleburyCommittee Member, present
DR
Councillor Dr R Webber-JonesCommittee Member, present
AW
Councillor A WeightmanCommittee Member, absent
DB
Daniel BrittonOfficer, in attendance

All 17 on the meeting page

On this subject at Hinckley and Bosworth

Search all
  1. General fund temporary accommodation programme - phase 3This decision
  2. General fund temporary accommodation programmeApproved
  3. General fund budgetApproved
  4. General fund budget 2025/26Approved
  5. General fund budget 2024/25Approved
  6. General fund budget 2024/25Noted

More from Hinckley and Bosworth Scrutiny Commission

All decisions
MeetingDecisionOutcome
22 Oct 2026 Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... Approved Open
22 Oct 2026 Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. Approved Open
22 Oct 2026 Budget planRESOLVED - members noted the Budget Plan for 2027/2028. Noted Open
22 Oct 2026 Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... Noted Open
22 Oct 2026 Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... Approved Open