Business Rates and Pooling update Quarter 4 - 2025/26

Noted Finance 1 paper

AI summaryHinckley and Bosworth scrutiny committee noted the Q4 2025/26 business rates update, showing £4,568,000 retained growth against a £4,557,000 budget. The Leicestershire business rates pool will close in 2026/27 due to the rates reset.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action required from committee
MoneyNot stated
What happens nextPool closes in 2026/27Business rates reset removes pooling basis
Who it affectsCouncil finances and pool partnersLoss of about £1m annual pool return

What was decided

The committee noted the Q4 2025/26 business rates and pooling report. Report 2.1

Why

The report updates members on business rates performance from 1 April 2025 to 31 March 2026, including outturn against budget. Report 1.1, 3.4

It covers the operation of the Leicestershire business rates pool and Hinckley and Bosworth BC's position within it. Report 3.7, 8.1

What happens next

The local business rates pool will be closed in 2026/27 because the rates reset removes the financial basis for pooling. Report 3.7

An estimated £1m of pool income previously returned to the council has been allowed for in the 2026/27 budget, adding to budget pressures. Report 3.7

The money

  • £3,974,000 Section 31 grant income received in 2025/26, compensating for reliefs granted Report 3.3, P9
  • £4,568,000 Retained business rates growth for 2025/26 at 31 March 2026 Report 3.5, P11
  • £4,557,000 Budgeted business rates growth for 2025/26 Report 3.5, P11
  • 7,422 Total retained income at year end 2025/26 (table values in thousands of pounds) Report P9, P10
  • 2,854 Baseline funding for 2025/26 (table values in thousands of pounds) Report P10, P11
  • £2.7m Levy budgeted for 2025/26 paid to the Leicestershire pool Report 3.7
  • £1m Estimated return from the pool to the council for 2025/26 Report 3.7

Options considered

  • Chosen: Note the report. Recommendation in the officer report Report 2.1

Implications

  • Financial: The pool closure in 2026/27 means the council loses an estimated £1m of returned levy income, adding to budget pressures. Report 3.7
  • Legal: Pooling is permitted under Section 59A of the Local Government Finance Act 1988 and is governed by a legal agreement between the Leicestershire councils. Report 6.1
  • Risk: Officers identified no significant risks associated with this report, though business rates remain volatile due to company closures, empty properties, reliefs and appeals. Report 3.6, 9.3
  • Equalities: Various reliefs are available for businesses and charities under business rate regulations. Report P28
  • Climate: No direct climate implications arise from this report. Report 11.1

Who and where

  • Hinckley and Bosworth Borough Council as billing authority Report 3.1, 3.3
  • Central Government, which receives 50% of collected business rates Report 3.1
  • Leicestershire County Council and the Fire Authority as precepting authorities Report 3.1
  • Members of the Leicestershire business rates pool Report 3.7, 8.1
  • Local businesses paying business rates, including those appealing their liabilities Report 3.6

Timeline

  • 1 April 2025, 31 March 2026: Business rates performance period covered by the report Report 1.1
  • 2026/27: Business rates reset takes effect and the local pool closes; prior year retained growth is removed Report 3.2, 3.7

Plain English for the jargon

  • NNDR: National Non-Domestic Rates, the business rates collected by billing authorities
  • Section 31 grant: Government grant compensating councils for business rates reliefs they have granted
  • Levy: 50% payment on business rates growth above a council's baseline, paid to government or to a pool
  • Safety net: Government payment triggered when a council loses 7.5% of its rates threshold
  • Tariff: Fixed amount of retained business rates paid to government, set in the Local Government Finance Settlement
  • Baseline funding: The guaranteed level of business rates income a council retains before growth or levy
  • Pooling: Arrangement under Section 59A of the Local Government Finance Act 1988 allowing councils to share business rates income
  • HBBC: Hinckley and Bosworth Borough Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item78

Resolved

RESOLVED – the report be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Finance & Performance Scrutiny

Purpose of report

1.1To inform the committee of business rates performance from 1st April 2025 – 31st March 2026.

Recommendation

2.1That the committee notes the contents of the report.

3. Background to the report

3.1Hinckley and Bosworth BC as a billing authorities pay 50% of collected business rates to government. The remaining 50% is split between the billing authority (40%) and the precepting authorities (10%).

3.2Following these payments, the retained business rates of billing authorities are subject to a tariff set out in the respective Local Government Finance Settlement. For 2025/26 any growth in business rates over the set baseline will be subject to a “levy” payment of 50%, with the remaining half retained by the host Council. Correspondingly, except for that element associated with the multiplier compensation cap. If a Council loses 7.5% of their set threshold, a “safety net” payment will be triggered to compensate for the loss. For 2026/27 the retained growth relating to prior years will be remove due to the business rates reset.

3.3The Council have received £3,974,000 of “section 31 grant” income. The allocated grant was based on the level of reliefs that were shown to have been granted in 2025/26, in the submitted business rates form (the NNDR3).

3.4The budgeted business rates performance for this council, along with outturn as at 31st March 2026 is summarised below.

06/16 Budget Table 1 Jun-25 Sep-25 Dec-25 Mar-26 2025/26

NNDR collected (net of reliefs) 45,939 45,939 45,939 45,939 45,939 Less: Central Government share (22,970) (22,970) (22,970) (22,970) (22,970) County Council share (4,135) (4,135) (4,135) (4,135) (4,135) Fire Authority Share (459) (459) (459) (459) (459) HBBC notional share 18,375 18,375 18,375 18,375 18,375 S31 Grant compensation 3,857 4,210 3,995 3,967 3,974 Total before tariff 22,232 22,585 22,370 22,342 22,349 Tariff charged on HBBC (12,069) (12,069) (12,069) (12,069) (12,069) Levy charged on growth (2,752) (3,029) (2,936) (2,896) (2,858) Retained income total 7,411 7,487 7,365 7,377 7,422

The retained income is made up of: Baseline funding 2,854 2,854 2,854 2,854 2,854 Total growth 7,309 7,662 7,447 7,419 7,426 Less Levy (2,752) (3,029) (2,936) (2,896) (2,858) Total 7,411 7,487 7,365 7,377 7,422 Movement- Gain/(loss) 0 76 (46) (34) 11

Retained income total 7,411 7,487 7,365 7,377 7,422 Baseline funding 2,854 2,854 2,854 2,854 2,854 Total Growth 4,557 4,633 4,511 4,523 4,568 Movement- Gain/(loss) 0 76 (46) (34) 11

3.5The above table shows that as at 31st March 2026, the council has £4,568,000 of retained growth for 2025/26 compared to the £4,557,000 growth that was budgeted for.

3.6It is important to acknowledge the volatility of business rates which can be impacted negatively by many factors including:  Companies going out of business or moving from the area,  Empty properties – The redevelopment of the town centre for instances may have an impact on the rates for the council whilst development takes place,  Awards of reliefs; most significantly charitable reliefs for schools which are awarded Academy status,  Results of appeals lodged by businesses against their liabilities.

06/16 The Business rates pooling scheme

3.7The changes to the business rates position across the local area due to the business rates reset introduced for 2026/27, will mean that the local business rate pool arrangement will not be financially viable and will be closed in 2026/27. In 2025/26, there was a levy of £2.7m budgeted for, which went to the Leicestershire pool to be used for local investment, of which £1m is estimated to be returned to HBBC. This has been allowed for in the 2026/27 budget and has added to the pressures faced by the Council.

4. Exemptions in accordance with the Access to Information procedure rules

4.1Report taken in open session.

5. Financial implications [AW]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Rates and Pooling update Quarter 4: 2025/26Report 634 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
MS
Councillor MJ SurteesChair, present
PW
Councillor P WilliamsVice-Chair, present
CA
Councillor CM AllenCommittee Member, apologies, sent representative
DC
Councillor DS CopeCommittee Member, absent
DG
Councillor DT GlenvilleCommittee Member, present
LM
Councillor LJ MullaneyCommittee Member, present
BS
Councillor BE SuttonCommittee Member, absent
BW
Councillor BR WalkerCommittee Member, absent
AW
Councillor A WeightmanCommittee Member, present
IB
Ilyas BhamOfficer, in attendance
DB
Daniel BrittonOfficer, in attendance
LH
Lois HodgkinsOfficer, in attendance

All 17 on the meeting page

On this subject at Hinckley and Bosworth

Search all
  1. Business Rates and Pooling update Quarter 4 - 2025/26This decision
  2. Business rates write offsDecided
  3. Business rates write offsApproved
  4. Business rates and Pooling update quarter 2 - 2024/25Noted
  5. Leicestershire Revenue & Benefits Partnership Council Tax & Business Rates 2021/22Noted
  6. Discretionary business rates relief - pop up shopsApproved

More from Hinckley and Bosworth Finance & Performance Scrutiny

All decisions
MeetingDecisionOutcome
24 Aug 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 6 July 2026 be confirmed as a correct record. Decided Open
6 Jul 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 11 May 2026 be confirmed as a correct record. Decided Open
6 Jul 2026 Hinckley and Bosworth UK Shared Prosperity Fund UpdateRESOLVED – the report be noted. Noted Open
6 Jul 2026 Performance and Risk Management Framework end of year summary for 2025/26RESOLVED – Members review the risks that posed the most threat to the council’s objectives and priorities and note th... Decided Open
6 Jul 2026 Housing Revenue Account - Rent performanceRESOLVED – that the current performance be noted along with the improvement in arrears performance Noted Open