CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hinckley and Bosworth Borough Council
Audit Committee, Wednesday 11 November 2026 at 6.30pm

Corporate Risk Register review

Noted Finance 1 paper

AI summaryHinckley and Bosworth Borough Council’s Audit Committee noted its Corporate Risk Register. The officer report covers the end of October 2026. The register records a £4.6m deficit risk for 2028/29, although the 2027/28 budget is still expected to be balanced. [D] [1.1] [P34]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe officer report covers the end of October 2026 [1.1]
Money£4.6m deficit risk [P34]Possible deficit in 2028/29 [P34]
What happens nextBudget risk under review [P34]External Audit will review the financial position [P34]
Who it affectsCommunity service delivery [10.1]Unmanaged risks can affect everyone [10.1]

What was decided

The Audit Committee noted the Corporate Risk Register. [D]

Why

The Risk Management Policy gives the council a consistent method based on likelihood and impact. [3.1] It requires proportionate mitigating actions, with risks prioritised, escalated and monitored. [3.1] Report 3.1

The Audit Committee provides independent oversight of risk management and reviews policy effectiveness. [3.2] The committee was asked to assess the register and consider whether further risks should be added or deleted. [2.1] Report 3.2, 2.1

Significant risks that may prevent delivery of business objectives are proactively identified and managed. [9.1] The review supports every Corporate Plan element and the council's ability to deliver it. [7.1] Report 9.1, 7.1

What happens next

Funding and cost reduction options are being considered for 2027/28. [P34] Report P34

The financial position of the MTFS will be reviewed in the VFM review by External Audit. [P34] Report P34

The council awaits the government's further reorganisation decision, expected by March 2027. [P34] Report P34

The money

  • £4.6m Deficit risk taken forward into 2028/29 based on the MTFS agreed by Council. [P34] Report P34

Implications

  • Financial: No direct financial implications arise from the report. [5.1] The register records a £4.6m deficit risk for 2028/29, while the 2027/28 budget is expected to remain balanced at a lower general fund performance position. [P34] Report 5.1, P34
  • Legal: No direct legal implications arise from the report. [6.1] Effective risk management supports statutory obligations and reduces exposure to legal challenge, regulatory action and financial liability. [6.1] Report 6.1
  • Equalities: No equality or rural implications arise directly. [10.1] Failure to manage risks effectively can affect service delivery across the community. [10.1] Report 10.1
  • Climate: No direct climate implications arise from the report. [11.1] Report 11.1
  • Risk: No immediate risk to the Council from the report is missing from the risk register. [9.3] Report 9.3
  • Risk: Business continuity arrangements for Critical Services have been collated and are due for review by SLT. [P32] ICT continuity work continues, and dependencies for implementing alternative resilience options still need review. [P34] Report P32, P34
  • Staffing: Cyber security training is mandatory for all staff, and managers have been trained to manage absence. [P34] [P33] Report P34, P33
  • Risk: Social housing capacity concerns include damp and mould reports under Awaab's Law, and planning appeal risks remain. [P35] Report P35

Who and where

  • Residents and businesses Report P31
  • All members of the community Report 10.1
  • All Council staff Report P34
  • The 10 authorities in reorganisation governance Report P34
  • Critical Services Report P32
  • Social housing tenants Report P35
  • Parish councils Report P35
  • Building Control partnership Report P37

Timeline

  • 29 July 2026: The Executive approved the latest Risk Management Policy. [3.1] Report 3.1
  • end of October 2026: The report covered the Corporate Risk Register. [1.1] Report 1.1
  • 29 October 2026: Ministerial statements and briefings followed withdrawal of the reorganisation decision. [P34] Report P34
  • 14th July: The Full Council Local Plan meeting was put back from 3rd June. [P35] Report P35
  • March 2027: A further government decision on reorganisation is expected. [P34] Report P34
  • 2027/28: Savings and new income will be required because of unfunded cost pressures. [P34] Report P34
  • 2028/29: There is a risk of a £4.6m deficit being taken forward. [P34] Report P34
  • end March: Current welfare support funding is in place, while other funding streams remain under review. [P34] Report P34

Plain English for the jargon

  • Risk matrix: A 3 by 3 table that multiplies likelihood and consequence scores. [P8]
  • RAG: The status column used for each register risk review. [P31]
  • Business continuity: Shared arrangements intended to maintain Critical Services. [P32]
  • SLT: The forum receiving business continuity, safety and financial monitoring reports. [P32] [P33] [P34]
  • MTFS: The agreed financial basis for the 2027/28 budget and 2028/29 deficit risk. [P34]
  • VFM: The External Audit review that will examine the council's financial position. [P34]
  • LGR: Local government reorganisation, with a further decision expected by March 2027. [P34]
  • Awaab's Law: Housing regulation linked to concern about damp and mould reports. [P35]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item243

Resolved

RESOLVED – the risk register be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Audit Committee

Purpose of report

1.1To provide an update to the Audit Committee on the Council’s Corporate Risk Register as at the end of October 2026.

Recommendation

2.1That the Audit Committee: • Review and consider the corporate risk register (attached as appendix 1) including assessment of risk, • Consider if any further risks need to be deleted or added to the corporate risk register.

3. Background to the report

3.1The latest Risk Management Policy was approved by the Executive on the 29 July 2026. This policy ensures that risks are assessed using a consistent methodology based on likelihood and impact, recorded on appropriate risk registers, and managed through proportionate mitigating actions. This ensures that risks are prioritised, escalated and monitored in a structured and transparent way.

3.2The current role of the Audit Committee is (extract from the policy):  To maintain an independent oversight of risk management issues  To undertake reviews of specific areas of risk management activity or initiatives  where required  To consider the effectiveness of the implementation of the risk management policy  To review the Council’s Annual Governance Statement

3.3Assessing risks involves estimating the levels of likelihood and impact of the risks and opportunities and assessing which of the risks pose the greatest threat and what would be the benefits of exploiting or taking up an opportunity. To assess a risk, we have adopted the risk matrix set out below:

Risk Matrix

The Risk Matrix is a three-by-three table showing the likelihood and consequence of all risks. The consequence of the risk which can be either low, medium or high, is multiplied by the likelihood of the risk, which is also low, medium or high; low is scored as 1, medium is scored as 2 and high is scored as 3. So, if a risk has a low consequence but a high likelihood, the score is 1 multiplied by 3 giving a risk score of 3.

Table 1 Risk Matrix

3 3 6 9 Likelihood

2 2 4 6

1 1 2 3 1 2 4 Consequence

4. Exemptions in accordance with the Access to Information procedure rules

4.1Report is taken in an open session.

5. Financial implications [IB]

5.1None directly from this report

6. Legal implications [SLS]

6.1There are no direct legal implications arising from this report. However, effective management of the risks within the Corporate Risk Register supports the Council in meeting its statutory obligations and minimising exposure to legal challenge, regulatory action and financial liability.

7. Corporate Plan implications

7.1Contributes to all elements of the Corporate Plan and ability to deliver.

Consultation

8.1None

Risk implications

9.1It is the council’s policy to proactively identify and manage significant risks which may prevent delivery of business objectives.

9.3There is no immediate risk to the Council from this report that is not captured in the risk register.

10. Knowing your community – equality and rural implications

10.1None arising specially from this report although failure to manage risks effectively can impact upon service delivery for all of the community . 11. Climate implications

11.1None directly from this report.

12. Corporate implications

12.1By submitting this report, the report author has taken the following into account:

- Community safety - Procurement implications implications - Human resources - Environmental implications implications - ICT implications - Planning implications - Asset management - Data protection implications implications - Voluntary sector

Background papers: None Contact Officer: Julie Kenny Executive Member: Councillor S Bray Appendix 1: Corporate Risk Register

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register reviewReport 754 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 11 attended
DC
Councillor DS CopeChair, expected
DR
Councillor Dr R Webber-JonesVice-Chair, expected
CA
Councillor CM AllenCommittee Member, expected
RF
Councillor REH FlemmingCommittee Member, expected
SG
Councillor SM GibbensCommittee Member, expected
EH
Councillor E HollickCommittee Member, expected
CL
Councillor C LambertCommittee Member, expected
AP
Councillor A PendleburyCommittee Member, expected
MS
Councillor MJ SurteesCommittee Member, expected
BS
Councillor BE SuttonCommittee Member, expected
PW
Councillor P WilliamsCommittee Member, expected

On this subject at Hinckley and Bosworth

Search all
  1. Corporate Risk Register reviewThis decision
  2. Audit Committee corporate risk register review 2024/25Decided

More from Hinckley and Bosworth Audit Committee

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 16 September be confirmed as a correct record. Decided Open
11 Nov 2026 Car Parks 2026/27 - Internal Audit Final ReportRESOLVED – the internal audit final report for car parks be approved. Approved Open
11 Nov 2026 Internal Audit progress reportRESOLVED – (i) The internal audit progress report be noted; (ii) Further discussion take place between the chairs of ... Noted Open
11 Nov 2026 Progress Report on the National Fraud Initiative (NFI) and any other Fraud issuesRESOLVED – the report be noted and the national report be circulated to members when available. Noted Open
11 Nov 2026 Audit Committee Forward PlanRESOLVED – the forward plan be approved. Approved Open