Resolved
That the recommendations of report for the release of S106 funds be agreed.
Chiswick Area Committee (Planning) agreed this item on Tuesday 14 January 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
That the recommendations of report for the release of S106 funds be agreed.
To advise Members of current unallocated S106 monies that may be used for environmental improvement schemes within the Chiswick Area and proposed use of some of those funds.
THAT THE CONTENTS OF THE REPORT BE NOTED
THAT MEMBERS AGREE TO THE ALLOCATION OF £28K FROM S106 RESOURCES TO FUND THE ENVIRONMENTAL IMPROVEMENTS TO AREA A OF THE RIVERSIDE WALK ON STRAND ON THE GREEN 3.0 Background
3.1The Council is due to carry out the remedial works to the River Wall on Strand on the Green at Strand End early in the new year and in response to concerns raised by Strand on the Green Residents Association about the intended structural works to the river wall and the implementation of the proposed environmental improvement scheme at this location, Members requested further details of the proposed project and any information on unallocated S016 monies that relate to environmental improvements for the Chiswick Area.
3.2At the Monitoring meeting on the 11 December 2002 Members of the Committee discussed and agreed in principle to the co-ordinated approach to the two projects subject to this report.
4.0Current Position
4.1The Council is undertaking remedial works to the river wall along Strand on the Green to meet the requirements of a Court Order set out in Nov 2000. The cost of undertaking these remedial works is considerable, and this year the Council has allocated a total of £80,000 to undertake the structural repairs to the section of wall between chainage 815 & chainage 850 in accordance with the Court order.
4.2It is estimated that the cost of the proposed environmental improvement scheme to restore the degraded footway environment behind the river wall is £28,000. ( see appendix 1 ) currently there are no resources identified for these works.
5.0Proposed Funding
5.1.1 Funding for the proposed environmental improvements to the riverside walk at Area A is available from S106 monies received from the development at 532- 546 Chiswick High Road ( Scheme 208 ).
6.1THAT THE CONTENTS OF THE REPORT BE NOTED
6.2THAT MEMBERS AGREE TO THE ALLOCATION OF £28K FROM S106 RESOURCES TO FUND THE ENVIRONMENTAL IMPROVEMENTS TO AREA A OF THE RIVERSIDE WALK ON STRAND ON THE GREEN (SEE APPENDIX 2)
7.0Head of Finance Comments
Funding is available as outlined in para 5.1 of the report.
8.0Environmental Implications 8.1 The proposed works to the riverside walk would enhance the quality of the environment in this part of the Conservation Area and improve access to the river frontage.
Contact: Andy Clements………….. Telephone: 020 8583 4980 Background Papers:
This report is relevant to the following wards/areas: Strand on the Green
APPENDIX 1. STRAND ON THE GREEN
Strand End @ Thames Road Environmental Improvement works.
The proposed environmental works to the footway at this location behind the river wall have been calculated for a new finished level for the river wall of 5.40metres above O.S. datum. This would create a large accessible amenity area that would have public seating and lighting, traditional style railings and suitable soft landscaping.
Area A covers approximately 120 sq metres between chainage 815m and 850m and consists of works over and above those that would be carried out as part of the contracted works for the reconstruction of the wall at this point.
The estimated cost of carrying out these works for budgetary purpose is £28k; this has been calculated as shown below
Proposed works. Est cost £ Total Cost Remove existing guard railing from central wall 750
Fill area with suitable sub-base material average of 5,500 depth approx 750 mm
Construct new footway surface with Dense Bitumen 4,000 Macadam,
Break out and reconstruct existing footway to Thames Rd and to chainage 815m with Dense Bitumen Macadam to marry 3,000 in to new levels
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
S106 Funds for Strand-on-the-Green Environmental ImprovementsReport | 106 KB | DownloadRead as text |
PDF |
S106 strand on the green planReport | 598 KB | Download |
Follow Chiswick Area Committee (Planning) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Mar 2011 | Apologies for absence, declarations of interest or any other communications from MembersApologies had been received from Councillor Lynch. Councillor Lee had been delayed but would be attending. In respect... | Decided | Open |
| 15 Mar 2011 | Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed. There were no matters arising. | Decided | Open |
| 15 Mar 2011 | Items on which there are speakersThere were no speakers. | Decided | Open |
| 15 Mar 2011 | Chiswick Community School Car Boot Sale- Traffic ManagementMembers approved the recommendations of the report as follows: Members noted the outcome of the meeting between repre... | Approved | Open |
| 15 Mar 2011 | 5 Burnaby CrescentApproved, subject to the conditions in the report and with the additional condition to meet Good Neighbour constructi... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.