Resolved - (a) That the highest bid received be accepted but if that tenderer is not able to complete within the 28 day period specified the land be offered to the second highest bidder. (b) That, should the second highest tenderer also not be able to complete within the specified timescale, the land be then offered to the third joint highest bidder as detailed in the report. (c) That if this third joint bidder is not in a position to proceed as set out in the report then the land be sold at public auction.