Resolved - a) That Officers be authorised, under Section 106 of the Town and Country Planning Act 1990 or other appropriate legislation, to secure:- i) Public transport improvements to offer alternative means for employees to get to the site, other than reliance on use of the car, including improvements to pedestrian access to the site and improved street lighting. ii) A Green Commuter Plan, giving options as to how people travel to work. iii) That the business recovery facility only be used within defined emergency situations. iv) The business recovery facility is only to be occupied for a temporary period of six months, unless otherwise agreed by the Planning Authority. b) That, subject to the satisfactory completion of the above legal agreement, the Borough Planning Officer be authorised to grant planning permission to change the use of part of Unit D, Prologis Park, from use as a warehouse to B1 offices (business recovery area) for use in an emergency, subject to the conditions set out in the report.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
00507/AC/P2 SUSTAINABLE DEVELOPMENT P/2002/3555 COMMITTEE 11/03/03 [SB]
1.0SITE
1.1UNIT D, PROLOGIS PARK, GREEN LANE, HOUNSLOW (CRANFORD)(21/11/02)
2.0PROPOSAL
2.1CHANGE OF USE OF PART OF UNIT D FROM USE AS A WAREHOUSE TO B1 OFFICES (BUSINESS RECOVERY AREA) FOR USE IN AN EMERGENCY DWG. NOS. MO20368.09/OFF, 10/OFF RECEIVED 21/11/02
3.0SITE DESCRIPTION
3.1This application relates to Unit D which is part of a mixed warehousing, industrial and light industrial development on the north western part of the former Beavers Lane Army camp.
3.2Unit D is situated to the south of the development with frontage to Green Lane. It is accessed via a central access serving the whole development site from Green Lane.
3.3The southern elevation of the building faces residential development in Cavalry Crescent and Beavers Crescent (Beavers Lane Camp).
4.0HISTORY
4.1An outline application to develop the western part of the army camp for 7 industrial units with access off Green Lane was approved in January 1994. Reserved matters including design and appearance and reducing the number of units to 5 were approved in February 1997.It was subject to a Section 106 agreement whereby the developers agreed to make a financial contribution towards improvements at the junctions of Green Lane and The Causeway (P3).
4.2In January 1999 permission was granted for the erection of a building of 15181sq.m for industrial and warehousing purposes with ancillary offices and 152 parking spaces. This Phase 1 development has now been completed together with the junction improvements (P7).
D:\moderngov\data\published\Intranet\C00000212\M00001090\AI00002906\UnitDProlo gisPark0.doc 4.3 Planning permission for the erection of 34280 sq.m warehousing and industrial floorspace to be laid out as two large units and 10 starter industrial units, car parking and service courts was granted in December 1999 (Phase 2) and this has now been implemented. A Section 106 agreement required the developer to make a financial contribution towards additional junction improvements at either end of Green Lane, public transport, on-street parking controls, off-street residents parking on Green Lane and environmental improvements (P8).
4.4In February 2001, permission was granted for the construction of a mezzanine floor in Unit B and an energy centre in the service yard, the fitting out of ground floor offices and conversion of first floor offices.
4.5In 2002 permission was granted for the construction of a mezzanine floor and external stair enclosures to Unit D and the erection of a plant area in the service yard incorporating alterations to the existing car park and the proposed use of the unit as a data centre.
5.0DETAILS
5.1Permission is now sought for the change of use of part of the unit from use as a data centre to use as B1 offices (business recovery area) for use in an emergency. The proposed use would occupy an area of 13,473 sq.m of existing ground floor and mezzanine floorspace that would be fitted out for use by a city based financial organisation. The proposed use would provide a back up office maintained for the displacement of staff in the event of any unforeseen interruption to critical business operations (i.e. in the event of a disaster including acts of terrorism).
5.2The submitted layout shows the floorspace laid out to accommodate 2,200 employees at any time. It is anticipated that approx. 50% of the applicant’s current workforce totalling approx. 6,000 would work from home. The proposed business recovery facility is intended to be temporary and would function for an approximate maximum period of 6 months. After an anticipated period of 6 months, employees would be transferred to a temporary office facility in the city for approx. 2 to 3 years until their offices had been re-established. The remainder of the building would be used as a data centre, but the business area recovery facility would remain fully equipped for future use if required. However, it is feasible that the facility may never be used.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Garage Block, Lateward Road, Brentforda) That planning permission for planning application 00681/ADJ12/P1 for the demolition of existing garage blocks and ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.