Comments from the Overview and Scrutiny Committee on the KPMG Report on Westlift - Review of the Scrutiny Panel's investigations.

Approved Scrutiny 1 paper

Overview and Scrutiny Committee approved this item on Monday 31 March 2003. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Resolved - a) That the report be endorsed as highlighting the Committee’s issues and concerns on this matter arising from discussion with the Chief Executive and KPMG. b) That the report be approved for presentation to the Executive, together with the KPMG review, and that both reports also be submitted to the Borough Council for its consideration at the earliest opportunity.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Summary

At its meetings of 18 January and 20 February 2003 committee members considered the findings of KPMG’s review into the work of the Westlift Scrutiny Panel. At its meeting of 20 February, members requested that a commentary from the Overview and Scrutiny Committee accompany the review and should be presented to the Executive and Borough Council at the earliest opportunity. This report outlines the concerns of the Committee with regard to the process that commissioned this review from KPMG (the Council’s external auditors) on the work of the Westlift Scrutiny Panel. Secondly it provides a response to the issues and recommendations contained in KPMG’s review.

Recommendations

1.1Members are asked to consider the contents of this draft report and to satisfy themselves that it highlights issues and concerns raised in their discussions with the Chief Executive and KPMG. 1.2 That this draft report is agreed for presentation to the Executive (as amended by the meeting) together with the KPMG review, and that both reports then go to full Council for its consideration at the earliest opportunity.

Background

2.1The Westlift Scrutiny Panel was established in February 2001 at the request of the Council to:

• Consider what measures should be taken to assist the Council to achieve closure on the Westlift project;

• Identify, explore and comment on why the Council become involved in the project;

COM-FS • Explore where and how problems occurred and to comment on the action taken to resolve them; and

• Identify lessons to be learnt for the future.

2.2The Panel concluded its work in July 2001 and presented its report to the Executive, then Committee of the Council on 9 October 2001. A full and lengthy debate took place at Committee of the Council on the report and its recommendations. Committee of the Council agreed the report and its recommendations alongside the Executive’s response to the report. The Executive’s response strengthened some of scrutiny’s recommendations. These were welcomed and accepted by Scrutiny and full Council.

2.3One such recommendation that was strengthened was Recommendation 4 of the scrutiny report. The Executive response stated:

The Executive, whilst understanding that the Council’s external auditors be requested to carry out a preliminary review, felt the proposal was too broad. The Executive, therefore, AGREED that the recommendation be amended as follows:-

“We recommend that the Council’s external auditors be requested to carry out a preliminary review of the Borough Treasurer’s Department to identify which systems should be included in an audit plan for a further in-depth review.”

2.4Members expectations were that all recommendations would be implemented and that with regard to Recommendation 4 as amended, the Council’s auditors would be commissioned to carry out the above review.

2.5The process for commissioning KPMG

2.5.1 During October and November 2001 discussions took place between the Chief Executive and KPMG about the nature and the terms of reference for the review. The Chair of Overview and Scrutiny and the Head of Scrutiny and Performance were not involved in these early discussions with KPMG. The Review got underway and interviews with key individuals took place during March and April 2002. KPMG were assisted in the arrangements for interviews by the Head of Scrutiny and Performance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Comments from the Overview and Scrutiny Committee on the KPMG Report on Westlift: Review of the Scrutiny Panel's investigations.Report 118 KB DownloadRead as text

At this meeting

Whole meeting
14Comments from the Overview and Scrutiny Committee on the KPMG Report on Westlift - Review of the Scrutiny Panel's investigations.This decision
15Annual Report of the Overview and Scrutiny Committee.Noted 16Newsletter of Overview and Scrutiny Committee.Decided

More from Hounslow Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
26 Mar 2026 Joint Health Overview and Scrutiny Committee UpdateThat the update was noted. Noted Open
26 Mar 2026 Work Programme Review - suggestions for 2026/27That the suggested topics would be noted for consideration by the incoming Committee as part of its work programming ... Noted Open
26 Mar 2026 Forward Plan ReviewThat the forward plan was noted. Noted Open
26 Jan 2026 Forward Plan ReviewThat the Forward Plan was noted. Noted Open
26 Jan 2026 Work Programme ReviewThat the Work Programme was noted. Noted Open