Resolved
That the report be noted. 2. That members receive regular reports on all aspects of the Key Site 1 development. Members agreed to suspend standing orders for a further 10 minutes beyond 10.00 p.m. in order to take further agenda items.
Central Hounslow Area Committee (monitoring) noted this item on Thursday 2 October 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted. 2. That members receive regular reports on all aspects of the Key Site 1 development. Members agreed to suspend standing orders for a further 10 minutes beyond 10.00 p.m. in order to take further agenda items.
1. That Members note the contents of this report. 2.0 Background
2.1Key Site 1 (also known as the Blenheim Centre) is a large mixed use development located in Hounslow town centre. The project will be built in two phases: the first phase will include a foodstore and health centre, residential units together with the supporting vehicular, cycling and pedestrian access, while the second phase will consist mainly of retail and leisure units.
2.2Currently, residents and businesses are being invited to comment on the latest stages of the development of Key Site 1. This includes the proposed details on the phases of development and construction, proposed car parking, construction routes for traffic, proposed Alexandra Road closure and minor amendments to plans. It is expected that substantial work on the site will begin in April 2004.
3.0Proposed Bus routes through Key Site 1
3.1Since the last update of this issue to the Central Hounslow Area Monitoring Committee on 8 May 2003 a meeting has been held on 16 May 2003 between the bus companies, the developers and London Borough of Hounslow officers. This meeting focused on a technical report presented by the developer’s consultants on a bus re-route scenario through Key Site 1.
3.2The technical report is based on the preferred scenario identified by developers, bus companies and Council officers and provides good coverage to Key Site 1 while retaining simplicity in the network. Details are as follows: • High Street to remain available only for westbound buses; • Staines Road services (currently westbound in High Street and eastbound on Hanworth Road) to transfer to Key Site 1 Link Road; • Bath Road services to transfer to High Street; • All other services to use Hanworth Road, except: - Route 120 since this could be routed via Lampton Road – Balfour Road – Link Road – Bus Station; - Route H22 to be routed through Key Site 1; • H37 to be extended from Hounslow Bus Garage to Key Site 1. This scenario was discussed in detail at the Central Hounslow Area Monitoring Committee on 8 May 2003.
3.3The report seeks to address the following three main issues in regards to the above scenario which had been raised by LB Hounslow officers and bus operators: • Impact on traffic capacity throughout the network; • Increase in bus journey time; • Capacity and movement through the Douglas Road / High Street junction.
3.4Traffic Impacts In terms of traffic impact, the report found that the introduction of the Link Road would help further prevent the occurrence of queues or capacity problems. It concluded that the above scenario works well throughout the network and is therefore considered to be an acceptable bus routing strategy to serve the development in terms of traffic capacity. 3.5 Bus Journey Time The technical report sought to clarify the issue of journey time for buses running via Key Site 1. The report found that travelling in an eastbound direction would take 114 seconds longer via Key Site 1 rather than via Hanworth Road. In a westbound direction it would take 114 seconds longer via Key Site 1 rather than Hanworth Road and 37 seconds longer than the High Street. It concluded that whilst significant, this had to be considered over the total journey time of the route and the fact that travelling via Key Site 1 will attract significantly more patronage.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Key Site 1: Public Transport updateReport | 4 pages | DownloadRead as text |
Follow Central Hounslow Area Committee (monitoring) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2011 | S.106 Funding for Environmental Improvement SchemesThat the allocation of the sums available for the proposed works, totalling £308,155.19 as set out in Appendix 1 of t... | Approved | Open |
| 20 Jan 2011 | Appointment of Co-opted MembersThat [name removed], [name removed] and [name removed] be appointed at Co-opted Members to Central Hounslow Area Comm... | Decided | Open |
| 18 Mar 2010 | Declarations of Interest and any other Communication from MembersCouncillor Sharma presented a petition in objection to the red bus route opposite Hounslow West Tube station. Action:... | Decided | Open |
| 18 Mar 2010 | Minutes of the meeting held on 3 December 2009Agreed. | Agreed | Open |
| 18 Mar 2010 | Minutes of the meeting held on 21 January 2010Agreed, with the following addition: Councillor L. Davies asked the Area Committee for funding to support the Wii Oly... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.