CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow

Budget - Current Year Spend

Decided Committee 3 papers

Gunnersbury Park Joint Committee - final meeting April 2007. Disbanded April 2007. decided this item on Friday 19 March 2004. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Resolved – That the proposal in the report to secure the £44,000 budget reduction in 2003/04 through a reduction in the contingency provision for National Lottery Fund bids, after taking account of underspends following finalisation of the 2003-04 accounts, be endorsed.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Gunnersbury Park Joint Committee - final meeting April 2007. Disbanded April 2007.

Summary

This report provides the expenditure for the current financial year April 2003 to February 2004. In addition actual expenditure for 2002 –2003 is shown as well as the budget estimate for the current year.

Purpose of the report

1.1The Joint Committee asked for regular quarterly budget monitoring reports to be produced showing spend to date against budget. The first report was produced in respect of the June quarter (April to June 2003), and submitted to the Joint Committee on 26th September 2003. Joint Committee however felt that reports should not be produced on a strict quarterly basis, but in line with Committee meetings thereby showing the most up to date financial position.

1.2The attached budgetary control report is in respect of the third quarter, April 2003 to December 2003, however has been produced for the period April 2003 to February 2004 in order to incorporate the latest available financial information.

2 COMMENTARY – CLIENT SIDE

2.1The tables attached (Appendix 1 – pages 1 to 3) show the actual client side expenditure for last year (2002-03), the estimate for the whole of 2003/04, spending profile, the actual client side expenditure up until 29th February 2004 and projected client side outturn for the year to 31 March 2004.

2.2In order to facilitate comparison of expenditure to date against budget, a budget profile column has been introduced, which takes into account differences of timing in the payment of certain expenditure items. For some items (e.g. building maintenance) that currently have no predictable pattern of spend, the annual budget has initially been calendarised (e.g. profiled at 11 months of annual budget). This is an area which will be require to be refined for future reports in the coming financial year. Other areas of spend (e.g.

1 capital charges) are shown as a year-end charge, and are dealt with as year- end closing of accounts transactions.

2.3As advised previously the £20,000 catering commission income has been introduced into the financial report.

2.4The 2003-04 year-end projected outturn has been used as the base in the formulation of the revised estimate for 2003-04 and 2004-05 estimate as detailed within Client Side revenue Budget 2004-05. This is covered in more detail within the 2004-05 budget report.

3. CIP BUDGET COMMENTARY

3.1There is a separate report attached, (Appendix 2 – summary and Appendix 3 – detail) showing the providers (CIP) actual expenditure for the third quarter of the financial year. The following narratives comment on the attached financial reports.

3.2These figures represent actual expenditure and income by CIP for Gunnersbury Park and Gunnersbury Park Museum to the end of the 3rd quarter of the financial year 2003-04. In general the budget is on course to balance but within the report figures there are a few issues or points to highlight.

3.3The high level of spend on water charges has previously been commented on in the 2nd quarter report (December 2003). Some of these costs are recouped from commercial tenants, such as Greenscene. However, both the Actual 2002/2003 and the projected Year End spend for 2003/2004 in this area show spend over the estimated amount. In this year’s budget the over spend is balanced by increased income, however, an increased sum will require to be added to the budget allocation for 2004/2005 to better reflect needs.

3.4The lower than expected spend on Salaries and Wages in the park is due to the loss of Mike Rowan’s time and assistance during the year. A new staffing structure is currently being put in place that will provide dedicated parks expertise within the Gunnersbury Park Estate team from 2004/2005.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget: Current Year SpendReport 68 KB DownloadRead as text
PDF
Gunnersbury2003-4 to Jan04-CIP file 15-3-04Report 102 KB Download
PDF
Quarterly Report 3rd Quarter 2003-04-Ver1: 2-3-04Report 60 KB Download

More from Hounslow Gunnersbury Park Joint Committee - final meeting April 2007. Disbanded April 2007.

All decisions
MeetingDecisionOutcome
16 Mar 2007 Consultation on Events in the ParkResolved – a) That the following approach be adopted for events: Community events, carnivals and small-scale events (... Approved Open
16 Mar 2007 Sporting HubsResolved – That the report be noted. Noted Open
16 Mar 2007 Budget Monitoring ReportResolved – a) That the income and expenditure of the Estate for the period to 28 February 2007 be noted. b) That the ... Noted Open
17 Mar 2006 Options: A Way ForwardResolved – That the Cabinet at Ealing Council and the Executive at Hounslow Council be advised that the Committee sup... Decided Open
17 Mar 2006 The De Rothchild CovenantsIt was agreed that the meeting should proceed on an informal basis. Resolved – That the London Borough of Hounslow Di... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies