Energy Efficiency Measures - Report A: Heatstreets Projects

Agreed Executive 1 paper

Executive agreed this item on Tuesday 4 January 2005. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

- (i) That Hounslow Council act as the lead authority for the West London “Heatstreets” Energy Efficiency Scheme (ii) That a retrospective exception to the Council’s Tenders and Contracts Regulations be authorised in order to obtain competitive quotations (iii) That authority be delegated to the Head of Housing Strategy and Services in consultation with ACE (Legal) and ACE (Finance) to: · Negotiate and enter into a contract with Powergen Retail Ltd on behalf of the seven participating West London Authorities to deliver the scheme · To agree terms for participation with six other Local Authorities in an inter-borough legal agreement
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Executive

Summary

1.1The Cross-Borough Energy Efficiency Scheme (‘Heatstreets’) is a two-year scheme covering seven London boroughs and it is funded by the Government Office for London (GOL). This report seeks authorisation to proceed with this project, with Hounslow as the lead authority for this West London Partnership, ensuring compliance with the terms of the Grant determination letter from GOL.

1.2Authority is also sought to delegate to the Head of Housing Strategy and Services, responsibility for :

• Entering into a contract with PowerGen Retail Limited, to deliver the Heatstreets scheme across the 7 participating West London Authorities.

• Entering into an inter-borough legal agreement with West London Local Authorities partners to define Local Authorities’ accountability and responsibility.

Recommendations

2.1To agree that Hounslow Council act as the lead authority for the West London ‘Heatstreets’ Energy Efficiency scheme.

2.2To authorize a retrospective exception to the Council's Tenders and Contracts Regulations to obtain competitive quotations.

2.3To delegate authority to the Head of Housing Strategy and Services in consultation with ACE (Legal) and ACE (Finance) to:

• Negotiate and enter into a contract with Powergen Retail Limited on behalf of the seven participating West London Authorities to deliver the scheme.

• To agree terms for participation with six other Local Authorities in an inter- borough legal agreement.

HeatStreetExecReportver9112040.doc 2.

Background

3.1In December 2003, the London Housing Board invited bids for cross-borough regeneration projects. After dialogue LBH, together with several other West London Boroughs, submitted a successful bid (as the “The West London Sub-Region” consortium)for £3.6m to fund a two-year ‘Heatstreets’ Energy Efficiency Project. It is estimated that Powergen, the principal supplier under the Heatstreets project, together with private customers will contribute a further £9m in match funding.

3.2Following research of the market it has been ascertained that there are a limited number of providers who can deliver the Heatstreets Project. In view of the limited number of providers and time constraints and the fact that Powergen is uniquely suited to deliver the goals of the Heatstreets Project, the Council’s standing orders for tendering could not be fully complied with and retrospective authorization to waive such compliance is requested.

3.3The selection procedure was not based on price alone but on the ability to deliver the quality expected from private sector households, customer service expectations and volume of work. To deliver overall Best Value Powergen was considered to be by far the most outstanding, useful and relevant scheme, offering external leverage and flexibility, and it is a copyrighted scheme.

3.4Why is Heatstreets Unique?

3.4.1 Heatstreets is the only energy efficiency scheme that offers a fully-managed solution to alleviate fuel poverty and improve the energy efficiency of the owner-occupier sector in a fully-integrated manner. The Powergen Heatstreets project offers a comprehensive management programme of works (no management or survey costs sub-contracted out to other agents). This maximises the effectiveness of the Local Authority's funding with 100% of the funding being spent on measures.

3.4.2 All Council investment is targeted at energy efficient improvements. There are no fixed administrative/operational costs.

3.4.3 The scheme allows for flexible targeting of specific areas.

3.4.4 Powergen offers scheme flexibility within the seven boroughs. All boroughs have different levels of data available and different stock, so approach will be tailored to each borough.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Energy Efficiency Measures: Report A: Heatstreets ProjectsReport 89 KB DownloadRead as text

More from Hounslow Executive

All decisions
MeetingDecisionOutcome
8 Mar 2011 Minutes of the meeting held on 8 February 2011The minutes of the meeting held on 8 February 2011 were confirmed. Decided Open
8 Mar 2011 Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed, with one amendment – page 21, paragraph 2 – amend... Decided Open
8 Mar 2011 Quarter 3 (October - December 2010) Quarterly Performance Management Pack 2010/11The report was noted. Noted Open
8 Mar 2011 Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The... Agreed Open
8 Mar 2011 Monthly Revenue Financial Monitoring - 31 December 2010The recommendations of the report were agreed. The recommendations of the report were agreed, namely that: The Execut... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies