Resolved : It was agreed that the following schemes be approved; that consideration of the remaining projects be deferred, with the exception of the following schemes, which were approved : i) That £ 10,800 from Scheme 60 is approved for use by Westmacott Action partnership (WAP) for works identified at the Southville Centre in combination with £ 25,000 from a successful bid to Barclays. ii) That £31, 000 from schemes 128 and 141 is used in combination With £49,750 Marathon Fund to refurbish Bear Road Recreation Ground.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Progress Report on S106 - Leisure and Cultural Projects Report by: Corporate Director for Lifelong Learning, Leisure and Cultural Services
Summary This report advises Members on Progress of S106 schemes which have been identified within the Leisure and Cultural Services portfolio. This report should be read in conjunction with review of S106 schemes by the Borough Planning Officer else where on this agenda.
This report also suggests a framework for the possible allocation of future S106 schemes based on Comprehensive Project Areas as a way of prioritising improvements to areas within the West Area Committee.
1. RECOMMENDATIONS 1.1 That £10,800 from Scheme 60 is approved for use by Westmacott Action partnership (WAP) for works identified at the Southville Centre in combination with £25,000 from a successful bid to Barclays.
1.2That £31,000 from schemes 128 and 141 is used in combination with £49,750 Marathon Funding to refurbish Bear Road Recreation Ground.
1.3That Members confirm their decision of 29th May 2003 to use £2,265 from Scheme 138 and £10,000 from scheme 203 for environmental improvements to Bridge House Pond. [See Appendix A]
1.4That £12,600 from Scheme 243 to be allocated for used for identified improvements to Ludlow Recreation Ground.
1.5That £15,000 from scheme 260 can be used for identified improvements to Hanworth Park.
1.6That Members note that scheme 174 has been completed and spent.
2.0PROGRESS ON EXISTING S106 SCHEMES 2.1.1 Scheme 60 Barclays Bank plc, Hanover Property Trust, Clockhouse Place, Bedfont, Feltham £38,000 2.1.1 Background £10,000 was intended for the Bedfont Youth Project. In addition £800 unspent from community projects was agreed by WAC in March 2002 to spend on the Bedfont Youth Project. £20,000 was intended as landscaping works to the ex urban farm site off Bedfont Road.
2.1.2 Progress The capital for the Bedfont Youth Project should be used to support youth and other activities at the Southville Centre enabled by establishment of the WAP has already led to a successful bid from the ‘Barclays Spaces for Sports’ grant scheme of £25,000 for an external multi games pitch and fencing on the old tennis courts. Match funding totalling £22,798 is required from other sources, and £10,800 from Scheme 60 would provide a substantial part of this. The capital for the ex urban farm site is more problematical. Spending £20,000 on a site which may be developed, or refurbished as part of development proposals, ref Techno Park, could be considered unnecessary. Suitable options could include: Clear fly tipping from boundaries and provide measures to prevent access since motorcycling especially is a problem. Provide planting as amenity screening to boundaries. Prioritising environmental improvement projects within CPA1 (Comprehensive Project Area) and combine this and other available S106 to achieve this. Establish an Urban forestry scheme on the site.
2.2Scheme 81 Speyhill Properties Ltd, Faggs Road, Feltham £15,000 2.2.1 Background £15,000 was detailed as available to purchase and improve the amenity of a small privately owned site known as Pollacks Cottages adjacent the Urban Farm. Insufficient funds to complete the project and problems in negotiations with the landholder have led to this project not going anywhere. 2.2.2 Progress The site lays within CPA 5 and adjacent the urban farm. Although it may be possible to integrate the site within a wider countryside park including the urban farm the sum will be less able to purchase the land now. An alternative would be to combine this and other available S106 to fund environmental improvement projects that have been prioritised within CPA5.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.