S106 report - Jon Medlin

Noted Committee 1 paper

Central Hounslow Area Committee (monitoring) noted this item on Thursday 2 February 2006. Below is the council's own wording, with the papers it was decided on.

Item81

Resolved

Resolved - To note the report.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Central Hounslow Area Committee (monitoring)

Contact: Jon Medlin Tel: 020 8583 5207 E-Mail: [email protected] Central Hounslow Area Committee Monitoring - 2 February 2006

S106 MONITORING UPDATE

Report by: Borough Planning Officer

Summary To inform Members of recently received S106 contributions and recently signed agreements where the money has not yet been received

1.0RECOMMENDATION 1) That Members approve the recommendations set out in section 2, paragraph 2.2 2) That Members note the new Section 106 agreements referred to in Section 3 of this report.

2.0RECENTLY RECEIVED CONTRIBUTIONS 2.1 There has been one contribution totaling £1,560 received since the last report to the Area Committee in September. These are to be reported to the Sustainable Development Committee on 23 February 2006. It is recommended that the allocations be made in accordance with the terms of the legal agreements as follows:

2.21 Cavendish Parade, Bath Road, Hounslow (£1,560) The development involves the installation of a new shop front and cladding. The agreement was signed on 22.9.05. A contribution of £1,560 was received on 22.09.05. and is to be used to raise the pavement at the front of the premises to improve access to the commercial unit. It is proposed that this contribution be noted and reported to Central Hounslow Area Committee. It is proposed that this contribution be noted.

3.0SECTION 106 AGREEMENTS SIGNED SINCE SEPTEMBER 3.1 There have been 3 new agreements signed, for which contributions have not yet been received, since the last S106 monitoring report to the area Committee on 29 September 2005. These are to be reported to the Sustainable Development Committee on 23 February 2006.

3.2Land between 13 & 17 Pownall Road, Hounslow The development relates to the erection of two 2-bedroom and two 3-bedroom semi detached houses. The agreement was signed on 12 August 2005 and will contribute the following: £16,300 to be used as follows: a) To fund the full cost of the relocation of the telegraph pole located between 9 and 19 Pownall Road the cost of which will not exceed £9,000. b) To fund the full costs of the relocation of the CPZ parking sign located on the footpath between 9 and 19 Pownall Road the cost of which will not exceed £300. c) To fund the full costs of the required changes to Traffic Orders for the CPZ for the Hounslow Town Centre area which will not exceed £3,000. d) To fund the full cost of four vehicle crossovers and the reinstatement of the existing dropped kerb on Pownall Road the cost of which will not exceed £4,000. 3.3 218-220 Bath Road, Hounslow The development relates to the demolition of the existing building on site and the erection of a 3 storey 29-bed bed and breakfast hotel with associated parking. The unilateral undertaking was signed on 6 December 2005 and will contribute the following: £3,600 towards the expansion of the Hounslow West CPZ £3,000 towards environmental improvements in the area.

3.4Smoothfields, Staines Road, Hounslow The development comprises of the demolition of existing buildings and erection of 100 one and two bedroom flats (including 50 affordable housing units) with associated landscaping, parking and access. The agreement was signed on 22 November 2005 and will contribute the following. £165,000 Education contribution £25,000 Environmental improvements contribution £25,000 Highway improvements contribution

4.0ENVIRONMENTAL IMPLICATIONS 4.1 The S106 contributions will help to offset the adverse impacts of developments and contribute to public transport, traffic calming, open space provision and environmental improvements.

5.0EQUAL OPPORTUNITIES 5.1 The S106 contributions are sought to widen opportunities through the provision of additional affordable housing and additional community facilities, education places and provision of employment training.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
S106 report: Jon MedlinReport 13 KB DownloadRead as text

At this meeting

Whole meeting

More from Hounslow Central Hounslow Area Committee (monitoring)

All decisions
MeetingDecisionOutcome
24 Mar 2011 S.106 Funding for Environmental Improvement SchemesThat the allocation of the sums available for the proposed works, totalling £308,155.19 as set out in Appendix 1 of t... Approved Open
20 Jan 2011 Appointment of Co-opted MembersThat [name removed], [name removed] and [name removed] be appointed at Co-opted Members to Central Hounslow Area Comm... Decided Open
18 Mar 2010 Declarations of Interest and any other Communication from MembersCouncillor Sharma presented a petition in objection to the red bus route opposite Hounslow West Tube station. Action:... Decided Open
18 Mar 2010 Minutes of the meeting held on 3 December 2009Agreed. Agreed Open
18 Mar 2010 Minutes of the meeting held on 21 January 2010Agreed, with the following addition: Councillor L. Davies asked the Area Committee for funding to support the Wii Oly... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies