Resolved
It was agreed to vary the rate from the current £7.90 per session to as little as £7.00 over the three terms if that proved necessary. Alison Leake left at this point.
Early Years Development and Childcare Partnership agreed this item on Thursday 9 March 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed to vary the rate from the current £7.90 per session to as little as £7.00 over the three terms if that proved necessary. Alison Leake left at this point.
Draft Paper for DMT Early Years Education Funding
Background Under previous arrangements funding for 3 and 4 year old children in the private and voluntary sector was paid to the LA through a combination of SSA and specific grant (Nursery Education Grant).
Nursery Education grant was paid to the LA for 3 and 4 year-olds to 2000-01 and then a flat rate factor introduced into SSA (Standard Spending Assessment) in 2001-02 for 4 year-olds and the nursery education grant for these 4 year-olds therefore ceased.
The 2002 Education Act regulations stated that Nursery Education Grant (3 year-olds) should be transferred into ESS (Education Spending Share) for 2003-04 and there would no longer be flat rate allocations as there had previously been for nursery education grant. Ministers agreed that to help smooth the transfer of nursery education grant into ESS the funding per pupil in 2003-04 for all authorities should allow them to continue to fund under 5 settings at the same level in real terms as in 2002-03. This would ensure that authorities with low deprivation did not lose out in nursery education funding, and that all LAs were adequately resourced to achieve universal provision for 3 year-olds. Therefore as from 2003-04 the specific Nursery Education Grant ceased to exist but now forms part of the overall School's block budget and competes with other areas within the Schools Block with regard to funding allocations.
Note: Nursery Education Grant (NEG) relates to nursery places in the private sector where the LA pays a grant at an agreed rate per child and reclaims it via the DfES nursery education grant prior to 2003-04.
The Story This year has seen a large percentage increase in claims for 3 and 4 year-old funding, notably from independent schools recently opened in the borough. The policy, recommended by DfES, is to fund all 3 and 4 year-olds attending early years settings in the borough, whether or not the family lives in the borough. It appears that this year the independent schools in Hounslow have attracted a large number of children who live outside the borough, and this is one reason why the numbers claiming the funding has increased Irene Canton.
NEG Comparison 2004/05 2005/06 % increase
Summer Term 3 yr olds - no. of sessions 42,405 48,680 14.80 4 yr olds - no. of sessions 10,659 12,713 19.27 Total number of sessions 53,064 61,393 15.70
Autumn Term 3 yr olds - no. of sessions 22,792 24,191 6.14 4 yr olds - no. of sessions 3,423 4,885 42.71 Total number of sessions 26,215 29,076 10.91
Spring Term 3 yr olds - no. of sessions 35,503 36,635 3.19 Actual 4 yr olds - no. of sessions 8,090 9,956 23.07 Total number of sessions 43,593 46,591 6.88 Budget for 05/06 £941,600 Spend to date - 2 terms £714,705 Budget remaining £226,895 Current rate per session £7.90 Actual session Spring term 46,591 Total cost for Spring Term £368,068.90
Budget Overspend -£141,173.90
Figures of three and four year-old children claiming funding this year 2005-06 Summer Term 2005 3 Year Olds = 988 4 Year Old's = 269
Autumn Term 2005 3 Year Old's 480 4 Year old's 95
Spring Term 2006 3 Year Old's = 834 4 Year old's = 160
New Entitlement April 2006 From this date the entitlement for 3 and 4 year-old children is being increased from 33 to 38 weeks per year. Currently children are funded for 5 sessions per week of 2.5 hours early years education (12.5 hours). We pay a max of 55 sessions per term.
There is a dilemma at present in so far as the allocation this year has been under-estimated. There has been a 15% increase in demand for this funding by the day nurseries and pre- schools. There is therefore a shortfall of approximately £140,000 in the budget.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Nursery Education Grant: the way forwardReport | 18 KB | DownloadRead as text |
Follow Early Years Development and Childcare Partnership at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jan 2004 | New Draft Training StrategyIt was agreed that information, procedures and forms should be reviewed to minimise any barriers to people booking on... | Agreed | Open |
| 27 Jan 2004 | Next MeetingIt was agreed that the next meeting be held at 9.30am on 30 March 2004 at the Civic Centre. The July meeting of the P... | Agreed | Open |
| 22 Jul 2003 | Recruitment & Training Sub-GroupIt was agreed that it would be useful for the Partnership to discuss ESF opportunities at a future meeting. | Agreed | Open |
| 22 Jul 2003 | Childcare Development & Sustainability Sub-GroupIt was agreed that the draft terms of reference of the sub-group be revised to avoid any possible confusion with the ... | Agreed | Open |
| 22 Jul 2003 | School Organisation PlanIt was agreed that Irene Canton would work on a report on such options to the Partnership’s November meeting, followi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.